Permit Number: T14CM08559
Parcel: 12801005H

Review Status: Completed

Review Details: COMMERCIAL - TI

Permit Number - T14CM08559
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
12/15/2014 DAVID RIVERA ZONING REVIEW Approved
12/15/2014 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Reqs Change 1. Clarify the ductwork for the economizer operation, i.e. where and how does the 40x16 duct terminate?
2. Provide structural calculations and details to show how the air handler is to be connected to the building structure. Reference: Section 302.1, IMC 2012.
3. Clarify the reason for using an A/C unit with a capacity of 135 MBH cooling when the load calculations show a total load of 96.1 MBH. Reference: Sections C403.2.1 and C403.2.2, IECC 2012.
4. Provide information on the sequence of operation for the restroom exhaust fans to show that all of the air supplied to the restrooms will be exhausted. Reference: Section 403.2.1 (4), IMC 2012.
12/15/2014 KEN VAN KARSEN ELECTRICAL-COMMERCIAL REVIEW Completed
12/15/2014 ROBERT SHERRY WATER REVIEW Completed
12/15/2014 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Reqs Change 1. Provide calculations showing how the water supply piping has been sized. Reference: Sections 604.1 and 604.3, IPC 2012.
2. Verify that the pipe sizes called out will not result in water velocities greater than that recommended by the pipe manufacturer (e.g. limit the water velocity to less than 8 FPS for copper). With a total of 17.5 water fixture units for the two restrooms, the ¾" main water supply line will have a velocity of 12.4 FPS. Reference: Table 604.3, IPC 2012.
12/15/2014 RSHERRY1 WWM REVIEW Passed No water meter size change.
12/15/2014 JASON GREEN ENGINEERING REVIEW Approved
12/16/2014 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Approved
12/16/2014 MARTIN BROWN FIRE REVIEW Approved
12/16/2014 ERIC NEWCOMB COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Passed