Permit Review Detail
Review Status: Completed
Review Details: CELL TOWER/ANTENNAS
Permit Number - T14CM07593
Review Name: CELL TOWER/ANTENNAS
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 10/26/2015 | PETER MCLAUGHLIN | PLANNING-CITY HALL | REVIEW | Approved | |
| 11/28/2014 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. GENERAL: INCLUDE THE STRUCTURAL DRAWINGS (TWO SHEETS 8 1/2 X 11 SUBMITTED) OF THE POLE ELEVATION AND DETAILS, AND THE FOUNDATION SECTION AND DETAILS, ON FULL SIZE DRAWINGS. |
| 11/28/2014 | MARTIN BROWN | FIRE | REVIEW | Approved | |
| 12/08/2014 | KEN VAN KARSEN | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | T14CM07593 1. Single line diagram of service: a. Update the fault current calculation with the 13,900 AIC at the service entrance. The corrected calculation changes the Isca shown at the service cabinet on the System Diagram, sheet #17. 2. Panel schedule information: a. Show a 2 pole breaker at circuit 22/24. Panel A is not a three phase panel. b. Remove the "Spare" label from circuit #12 used for tech lighting. Ken Van Karsen Electrical Plan Review PDSD, City of Tucson 520-837-4906 Kenneth.VanKarsen@tucsonaz.gov |
| 12/11/2014 | MICHAEL ST. PAUL | ZONING | REVIEW | Approved | |
| 12/17/2014 | ELIZABETH LEIBOLD | ENGINEERING | REVIEW | Reqs Change | T14CM07593 PDSD Engineering comments 17DEC14: Special Exception SE-14-22 conditions 9, 11, 14, & 15 were not clearly found on plans for review - however the plans did not necessarily indicate non-conformance with these conditions, so the following comments are provided: 1) add note or explain where the Special Exception condition 9 is showing compliance with regard to antennas being installed/painted to blend & minimize visual impact etc; 2) add note or explain where the Special Exception condition 11 is showing compliance with regard to any graffiti being removed in 10 days etc; 3) add note or explain where the Special Exception condition 9 is showing compliance with regard to any generator to be proposed that shall comply with condition 14 etc.; 4) add recordation sequence number to sheet 05 next to easement or explain where the Special Exception condition 15 is showing compliance with regard to recordation information for access easement etc. Regarding Special Exception condition #16, applicant stated they have already had, and will have, TEP power coordination meetings. Provide clear response letter identifying location of the notes and addressing the above comments. Call me if you have questions. - Elizabeth Leibold P.E. 520-837-4934 |
| 12/19/2014 | CPIERCE1 | COMMUNICATIONS | REVIEW | Completed | PER THOMAS F. JEFFERSON |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 10/28/2015 | AROMERO4 | OUT TO CUSTOMER | Completed |