Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T14CM06498
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
10/09/2014 | ROBERT SHERRY | WATER | REVIEW | Completed | |
10/10/2014 | LEERAY HANLY | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | Plan review has been completed and the following corrections are required. Please provide a written response to comments with plan re-submittal. 1) Restroom exhaust fans to be set on timers (on whenever store is occupied) or interlocked with the A/C system serving the restrooms. Reference 2012 IMC 403.2.1(3) 2) Provide IECC lighting compliance report (com-check) for interior lighting. Reference IECC section 405 If there are questions regarding this review contact: LeeRay 520-837-4906 LeeRay.Hanly@tucsonaz.gov |
10/10/2014 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | 1. Coordinate the natural gas loads for RTU-3 and RTU-4 as shown on P-1R with the mechanical schedules. Reference: Section 107.2.1, IBC 2012. 2. Verify that the pipe sizes called out for the flush valves will not result in water velocities greater than that recommended by the pipe manufacturer (e.g. limit the water velocity to less than 8 FPS for copper piping). At a minimum design flow rate of 25 GPM for a siphonic, flush-valve water closet, a 1" Type L copper pipe has a flow velocity of 9.7 FPS. Reference: Table 604.3, IPC 2012. 3. Verify that the specified faucet and mixing valve providing tempered water for the lavatories are listed as conforming to ASSE 1070. Reference: Sections 416.5 and 607.1.2, IPC 2012. 4. Clarify the installation of the two trap primers located over the restrooms. The above-floor plumbing plan and detail 8/P-3 show the two units being individually connected to the 2" cold water supply to the restroom but the domestic water riser diagram shows the trap primers being connected to a dead-end branch from the 2" cold water supply to the restroom. Coordinate the drawings and verify that the installation conforms to the manufacturer's installation instructions. Reference: Section 303.2, IPC 2012. 5. Direct water supply connections to coffee makers shall be protected with backflow preventers conforming to ASSE 1022. Reference: Section 608.16.10, IPC 2012. |
10/10/2014 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | 1. Revise the font size used on the drawings to a minimum height of 3/32-inch (i.e. both upper and lower case fonts must be at least 3/32" high). Reference: Section 107.2.1, IBC 2012. 2. Provide heating and cooling load calculations that justify the capacities of the heating and cooling equipment specified for the project using the exterior design conditions shown in Section 302.2, IECC 2012, as modified by the City of Tucson. Reference: Sections C403.2.1 and C403.2.2, IECC 2012. 3. Provide the heating sections for RTU-5 and RTU-7 with a combustion efficiency of at least 80%. Reference: Section 403.2.3, IECC 2012. 4. Note P on the Rooftop Unit Schedule states that for indoor air quality, "0 PPM for start open 2000 PPM for full open". Clarify how this is justified when the minimum ventilation requirement based on the occupancy areas (i.e. CFM per square foot) is not related to the CO2 concentration in the space. Reference: Section 403.5, IMC 2012. |
10/13/2014 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. SHEET A0.01; CODE ANALYSIS (CHAPTER 10): REFERENCE IS MADE TO TABLE 1004.1.1 FOR FLOOR AREA ALLOWANCES PER OCCUPANT. REVISE THE TABLE REFERENCE. 2. SHEET A0.01; CODE ANALYSIS (CHAPTER 10-EGRESS WIDTH): THE REQUIRED EXIT WIDTH IS BASED ON 572 OCCUPANTS, WHILE THE TOTAL OCCUPANT LOAD IS LISTED AS 573. CLARIFY. 3. SHEET A0.01; FLOOR PLAN: THE CITY OF TUCSON REQUIRES ALL LETTERING (UPPER AND LOWER CASE) TO BE A MINIMUM OF 3/32" IN HEIGHT. REVISE THE VERBIAGE ON THIS SHEET. 4. SHEET A0.01; CODE ANALYSIS (CHAPTER 10-EXIT DOOR TACTILE SIGNS): REFERENCE IS MADE TO SECTION 1006.3.4 FOR EXIT DOOR TACTILE SIGNS. REVISE THE SECTION REFERENCE. 5. SHEET A0.01; CODE ANALYSIS (CHAPTER 10-COMMON PATH OF EGRESS TRAVEL): THE MAXIMUM COMMON PATH OF EGRESS TRAVEL IS LISTED AS 100'-0". TABLE 1014.3 INDICATES 75' FOR THAT DISTANCE ("ALL OTHERS" OCCUPANCY). VERIFY. 6. SHEET A0.01; CODE ANALYSIS (CHAPTER 29-MINIMUM NUMBER OF REQUIRED PLUMBING FIXTURES): THE TOTAL OCCUPANT LOAD IS LISTED AS 572 FOR PLUMBING FIXTURES, WHILE THE TOTAL OCCUPANT LOAD IS LISTED AS 573. CLARIFY. 7. SHEET A0.01 (CODE ANALYSIS); SHEET A1.00 (SITE PLAN): THE SITE PLAN ON SHEET A1.00 INDICATES THE TENANT SPACE OCCUPIES 22,546 SF, THE NOTE UNDER THE FLOOR PLAN TITLE ON SHEET A0.01 INDICATES 21,546 SF, AND THE SUM OF THE SF INDICATED ON THE FLOOR PLAN ON A0.01 IS 20,418 SF. COORDINATE. 8. SHEETS A0.02 THROUGH A0.05: THE CITY OF TUCSON USES THE 2012 IBC AND THE 2009 ICC/ANSI A117.1 FOR ACCESSIBILITY. VERIFY THESE SHEETS FOLLOW THOSE REQUIREMENTS. 9. SHEET D1.10: THE CITY OF TUCSON REQUIRES ALL LETTERING (UPPER AND LOWER CASE) TO BE A MINIMUM OF 3/32" IN HEIGHT. REVISE THE BOXED NARRATIVE VERBIAGE. 10. SHEET D2.00; ELEVATIONS 4 AND 5: BOTH ELEVATIONS HAVE AN ARROW INDICATED WITH NO VERBIAGE. VERIFY. 11. SHEET D2.00; DEMOLITION KEY NOTES: ADD A NOTE INDICATING ALL KEY NOTES LISTED ARE NOT SHOWN ON THE ELEVATIONS. 12. SHEET A1.15: THE CITY OF TUCSON REQUIRES ALL LETTERING (UPPER AND LOWER CASE) TO BE A MINIMUM OF 3/32" IN HEIGHT. REVISE THE GENERAL NOTES AND THE GENERAL ROOF NOTES. 13. SHEET A1.40; KEYED NOTES: NOTE 22 REFERENCES A SIGN AT THE ELECTRICAL ROOM. THAT ROOM IS NOT SHOWN ON THIS SHEET. VERIFY. 14. SHEETS A1.42 AND A1.43: THE CITY OF TUCSON REQUIRES ALL LETTERING (UPPER AND LOWER CASE) TO BE A MINIMUM OF 3/32" IN HEIGHT. REVISE THE VERBIAGE. 15. SHEET A1.46: THE CITY OF TUCSON REQUIRES ALL LETTERING (UPPER AND LOWER CASE) TO BE A MINIMUM OF 3/32" IN HEIGHT. REVISE THE VERBIAGE. 16. SHEET A4.01; DETAILS 08 AND 09: AT THE METAL STUD BRACES, INDICATE THE SIZE AND NUMBER OF CONNECTORS AT THE VERTICAL STUDS. IN ADDITION, PROVIDE A DETAIL ON THIS SHEET OF THE BRACE CONNECTION TO THE EXISTING STRUCTURE ABOVE. 17. SHEET A4.11: THE CITY OF TUCSON REQUIRES ALL LETTERING (UPPER AND LOWER CASE) TO BE A MINIMUM OF 3/32" IN HEIGHT. REVISE THE VERBIAGE. 18. SHEET A4.11; DETAILS 04, 05, 09, AND 11: AT THE METAL STUD BRACES, INDICATE THE SIZE AND NUMBER OF CONNECTORS AT THE VERTICAL STUDS. IN ADDITION, PROVIDE A DETAIL ON THIS SHEET OF THE BRACE CONNECTION TO THE EXISTING STRUCTURE ABOVE. 19. GENERAL: PROVIDE WRITTEN RESPONSES TO ALL REVIEW COMMENTS. |
10/15/2014 | MARTIN BROWN | FIRE | REVIEW | Approved |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
10/27/2014 | SHANAE POWELL | OUT TO CUSTOMER | Completed |
10/27/2014 | CPIERCE1 | REJECT SHELF | Completed |