Permit Number: T14CM06390
Parcel: 114600810

Review Status: Completed

Review Details: COMMERCIAL - TI

Permit Number - T14CM06390
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
10/02/2014 MARTIN BROWN FIRE REVIEW Approved
10/03/2014 ROBERT SHERRY WATER REVIEW Completed
10/06/2014 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Reqs Change 1. Provide structural calculations for the mounting shelf for the water heater to show that the water heater will be safely supported from the building structure. Reference: Section 301.2, IPC 2012.
2. Coordinate the electrical requirements for the water heater with the electrical engineer. Reference: Section 303.2, IPC 2012.
3. The fixture drain serving an automatic clothes washer shall connect to a fixture branch that is at least 3 inches in diameter. Reference: Section 406.2, IPC 2012.
4. Verify the size of the water service: the drawings for the shell building show a 1" RPBP and a 1" water service pipe to the suite as compared to the 1-1/4" water service pipe and the current plumbing plan shows a 1" RPBP but the water calculation calls out a 1-1/4" RPBP. Reference: Section 107.2.1, IBC 2012.
10/06/2014 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Reqs Change 1. The portion of the building shell being modified in this activity does not appear to have been conditioned. Section C101.4.5, IECC 2012 requires the space to be brought into full compliance with the current energy code as if it was new construction. Provide energy code compliance calculations for the building envelope; use the "new construction" project type. Provide sufficient detail on the drawings to evaluate the energy compliance of the building envelope. Reference: Sections C103.2, C401.2, and C406.1, International Energy Conservation Code 2012.
2. Provide NFRC fenestration product ratings for the U-factor and the SHGC values on COMcheck or use the appropriate default U-factor and SHGC values from Tables C303.1.3 (1) and C303.1.3.(2), IECC 2012. Reference: Section C303.1.3, IEC 2012.
3. Provide heating and cooling load calculations that justify the capacities of the heating and cooling equipment specified for the project. Reference: Sections C403.2.1 and C403.2.2, IECC 2012.
4. Revise the Mechanical Compliance Certificate to coordinate with the current activity (only four heat pumps are being installed on the roof, not five). Reference: Section 107.2.1, IBC 2012.
5. Clarify the ventilation calculations. Two closets are included in the calculation but on the plans, they do not have any supply air. On the ventilation calculation chart, none of the three restrooms indicate that they require exhaust, they are labeled as "intermittent" but they have continuous operation during occupied hours. The break room shows a required 68 CFM of exhaust but there is no exhaust shown on the plans (per Section 507.2.2, IMC 2012, 70 CFM is required due to the presence of the microwave). Reference: Section 403.3, IMC 2012.
6. Provide signage indicating the total equivalent length of the concealed dryer exhaust duct. Reference: Section 504.6.5, IMC 2012.
7. Provide make-up air for the dryer installation. Reference: Section 504.5, IMC 2012.
10/10/2014 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Reqs Change 1. SHEET TS1; CODE ANALYSIS DATA: REVISE THE ACCESSIBILITY CODE TO THE 2009 EDITION.
2. SHEET TS1; CODE ANALYSIS DATA: REVISE THE NEC TO THE 2011 EDITION.
3. SHEET TS1; GENERAL BUILDING SUMMARY: REFERENCE IS MADE TO THE IBC SECTION 503 FOR THE TYPE OF CONSTRUCTION. REVISE THE SECTION REFERENCE.
4. SHEET TS1; GENERAL BUILDING SUMMARY: REFERENCE IS MADE TO THE IBC SECTION 1004.3.2.1 FOR THE SPRINKLER SYSTEM. REVISE THE SECTION REFERENCE.
5. SHEET TS1; CODE STUDY: REFERENCE IS MADE TO THE IBC TABLE 503 FOR THE TYPE OF CONSTRUCTION. REVISE THE SECTION REFERENCE.
6. SHEET TS1; CODE STUDY: REFERENCE IS MADE TO THE IBC TABLE 1016.1 FOR SPRINKLERS. REVISE THE TABLE REFERENCE.
7. SHEET TS1; CODE STUDY: REFERENCE IS MADE TO THE IBC TABLE 803.5 FOR FLAME SPREAD RATINGS. REVISE THE TABLE REFERENCE.
8. SHEET TS1; CODE STUDY: REFERENCE IS MADE TO THE IBC TABLES 1014.1 AND 1015.1 FOR OCCUPANT LOADS. ARE THESE PERTINENT TO THE OCCUPANT LOAD? REMOVE/REVISE AS REQUIRED.
9. SHEET TS1; CODE STUDY: REFERENCE IS MADE TO THE IBC TABLES 1005.1 AND 1014.1 FOR NUMBER OF EXITS AND EXIT WIDTHS. REVISE THE TABLE REFERENCES.
10. SHEET TS1: PROVIDE CALCULATIONS ON THIS SHEET FOR PLUMBING FIXTURE REQUIREMENTS PER THE IBC TABLE 2902.1.
11. SHEET TS1 (SITE PLAN); SHEET A3.0 (ROOF PLAN): THE ROOF PLAN INDICATES THE WEST BUILDING IS 4192 SF, WHILE THE SITE PLAN INDICATES 4133 SF. CLARIFY.
12. SHEET A1.0; ENLARGED PLANS 2 AND 3: INDICATE ON THE PLANS THAT THE TURNING SPACE REQUIREMENTS OF THE ICC/ANSI SECTION 304.3 ARE MET.
13. SHEET A1.0; FLOOR PLAN: THE INTERIOR CORRIDOR (PASSAGE 113) CREATES A DEAD END CORRIDOR THAT EXCEEDS THE ALLOWABLE DISTANCE (IBC SECTION 1018.4). REVISE THE PLAN AS REQUIRED.
14. SHEET A1.0; FLOOR PLAN: THE BUILDING SECTION REFERENCE ON THE PLAN IS 1/A3.0. REVISE THE REFERENCE.
15. SHEET A1.0; FLOOR PLAN: ADD THE ENLARGED PLAN 3 INDICATION ON THE PLAN.
16. SHEET A1.0; WALL TYPE 4B: REFERENCE IS MADE IN A NOTE TO THE IBC SECTION 1607.13 FOR WALL BRACING. REVISE THE REFERENCE.
17. SHEET A1.0; WALL TYPE 4A: REFERENCE IS MADE IN A NOTE TO THE IBC SECTION 1621.2.7 FOR WALL BRACING. REVISE THE REFERENCE.
18. SHEET A1.0; ENLARGED LAUNDRY PLAN 2: REFERENCE IS MADE ON THE PLAN IN KEY NOTES 6.9, 6.10 (TWO LOCATIIONS), 6.11, AND 15.13 (TWO LOCATIONS). THESE NOTES ARE NOT LISTED. CLARIFY.
19. SHEET A1.0; ENLARGED LAUNDRY PLAN 2: REFERENCE IS MADE ON THE PLAN IN KEY NOTES 10.13 AND 10.14 AT THE WASHER AND DRYER. REVISE THE REFERENCE NUMBERS.
20. SHEETS A1.0, A2.0, AND A3.0; KEY NOTES: FINISH NOTE 15.7.
21. SHEET A2.0; BREAK ROOM ELEVATION 5: INDICATE A 2'-10" DIMENSION FROM THE FINISH FLOOR TO THE TOP OF THE COUNTER.
22. GENERAL: PROVIDE WRITTEN RESPONSES TO ALL REVIEW COMMENTS.
10/20/2014 STEVE SHIELDS ZONING REVIEW Approved
10/27/2014 LEERAY HANLY ELECTRICAL-COMMERCIAL REVIEW Completed