Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
06/23/2014 | STEVE SHIELDS | ZONING | REVIEW | Approved | |
06/23/2014 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | Provide the heating/cooling load calculations to justify the capacity of the new heat pump. |
06/23/2014 | LEERAY HANLY | ELECTRICAL-COMMERCIAL | REVIEW | Completed | |
06/23/2014 | ROBERT SHERRY | WATER | REVIEW | Approved | |
06/23/2014 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. SHEET TS1; PROJECT CODE REVIEW: REVISE THE OCCUPANCY GROUP TO THE 2012 IBC CLASSIFICATION. 2. SHEET TS1; PROJECT CODE REVIEW (OCCUPANCY LOADS): REVISE THE SF/OCCUPANT USED (85) ON THIS DRAWING TO THE IBC TABLE 1004.1.2 REQUIREMENT. 3. SHEET A1.0; FLOOR PLAN (KEYNOTES): INCLUDE IN NOTE 11 (OR ADD A DETAIL) THAT THE NEW COUNTER SHALL BE 2'-10" ABOVE FINISH FLOOR. 4. SHEET A1.0; FLOOR PLAN: THE MOVIE THEATER ROOM REQUIRES 2 EXITS WITH PROPER SEPARATION PER SECTION 1015.2.1. 5. SHEET A3.0; KEYNOTES: SEVERAL KEYNOTES ARE MISSING FROM THE ELEVATIONS. VERIFY. 6. GENERAL: PROVIDE WRITTEN RESPONSES TO ALL REVIEW COMMENTS. |
06/23/2014 | RSHERRY1 | WWM | REVIEW | Passed | No wastewater plumbing. |
06/23/2014 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Passed | |
06/23/2014 | LOREN MAKUS | ENGINEERING | REVIEW | Approved | |
06/23/2014 | KEN BROUILLETTE | FIRE | REVIEW | Reqs Change | PLEASE UPDATE WITH CORRECT OCCUPANCY CLASSIFICATION AND THE CORRECT OCCUPANT LOAD FACTOR FOR THE LOUNGE AREA |
06/23/2014 | ERIC NEWCOMB | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed |