Permit Number: T14CM03072
Parcel: 117061910

Address:
11 S 6TH AV

Review Status: Completed

Review Details: COMMERCIAL - TI

Permit Number - T14CM03072
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
05/28/2014 MICHAEL ST. PAUL ZONING REVIEW Approved
06/02/2014 KEN BROUILLETTE FIRE REVIEW Reqs Change 1. Waste Cooking Oil Tanks- Indicate how they comply with Section 610 of the 2012 IFC
2. Missing Egress signage and lighting on sheet E1.0
3. Please correct all NFPA code references that are wrong on the plans. Wrong editions.
4. On sheet A0.2-need to show exit path in courtyard. Other pages show seating that obstructs egress path. A complete seating plan needs to be provided in all areas to indicate egress paths. What are the two legal exits from the courtyard?
5. How does gate in courtyard meet Chapt 10 for egress?
6. What pages show slopes of existing ramps and proposed ramp? Not sure why it shows "level" on proposed ramp.
7. Door schedule needs to be corrected. Wrong hardware on egress doors.
8. On the code review sheet a0.2, I need to see all walls in the proposed tenant spaces including any kitchen areas to determine exiting requirements.- Ken B
06/04/2014 RONALD BROWN BUILDING-COMMERCIAL REVIEW Reqs Change GENERAL
1. Provide a completed upper portion of the two part certification form for special inspectors.
2. Confirm with Zoning if a DP package is required for site changes.
3. Provide another set of structural calculations
SHEET A0.1
4. This project is a building shell improvement with no tenants and no Certificate of Occupancy is to be issued. The occupiances should state SHELL and not "B", "A2" and "M".
5. Please break down the new construction into building area and covered patio area.
6. Item 29 used in the shaded area indicates the existing roof framing to remain whereas the structutral framing plan shows new framing members. Please reconcile.
SHEET A3.0
7. Vestibule 33.12 is non-compliant with the 2009 ICC ANSI, Section 404.24. It must be 10-0" deep to meet 4'-0" clearance requirement.
8. Note 15 indicates a handicap ramp and to coordinate with civil drawings:
a. What do the civil drawings have to do with an interior building ramp?
b. On sheet A3.1, the slope of the ramp is indicated to be 1:20. as per ANSI 117.1, Section 405.2, a 1:20 slope is not considered a ramp. Therefore, no handrails are required. c. Please provide grade delineation and slope run dimensions on drawing to confirm 1:20 slope.
9. The new toilet room numbers 014.2, 3 and 4 are non-compliant:
a. As per the 2012 IBC, Section 2902.2, separate facilities shall be provided for each sex when the occupant load being served is 16 or more. The lavatory room is not separate.
b. Table 2902.1 schedules 1 lav for 40 men and 1 lav for 40 women not one gang trough lavatory for both.
c. Section 405.3.2 of the 2012 IPC states that the lavatory must be located in the same room as the water closet.
10. Provide a large scale detail of the ramp and landing in space 030.1 showing all the accessible requirements such as complete dimensions, floor/landing grade elevations, handrails including handrail elevations, slopes and landings.
11. Provide a large scale detail of the landing with steps of room 33.3 showing all accessible requirements incuding complete dimensions, tread and riser dimensions, handrails and handrail elevations, floor/landing grade elevations and landing clearances.
12. Define the corridor width for egress for corridor 33.8 and insure that the in swining doors do not reduce the required width by 1/2: 2012 IBC, Section 1005.7, Encroachment.
SHEET A8.0
13. At detail 3 Lavatory, reference comment 9.
END OF COMMENTS
06/05/2014 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Reqs Change 1. Demonstrate energy code compliance for the addition to the building envelope using calculations based on the current code. Reference: Sections C101.4.3, C101.5, and C103.2, International Energy Conservation Code 2012.
2. Provide heating and cooling load calculations that justify the capacities of the heating and cooling equipment specified for the project. Reference: Sections C403.2.1 and C403.2.2, IECC 2012.
3. Finish filling out the schedule for the split system heat pumps (i.e. include the missing data). Reference: Section 107.2.1, IBC 2012.
4. Show that the HVAC equipment meets the minimum efficiency requirements and has at least the controls and accessories (e.g. dampers, economizer, etc.) required by the 2012 IECC. Reference: Sections C403.2.3 and C403.2.4, IMC 2012.
5. Clarify how excess outside air relief from the building is to be accomplished. Reference: Section C403.3.1.1.4, IECC 2012.
6. Provide structural details to show how the fan coil units are to be connected to the building structure. Reference: Section 302.1, IMC 2012.
7. Show the size, routing, and termination of the secondary condensate drains. Reference: Section 307.2.1, IMC 2012 as amended by the City of Tucson.
06/05/2014 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Reqs Change 1. For public toilet facilities, the required lavatory shall be located in the same room as the water closet. Reference: Section 405.3.2, IPC 2012.
2. Provide details showing how the mat washer area is to be constructed and the joint between the floor drain and the floor surface made to be water-tight. Reference: Sections 405.4 and 405.5, IPC 2012.
3. The water pressure calculations include a 5 PSI pressure drop due to the reduced pressure backflow preventers. Provide specification sheets from the manufacturer that supports that pressure drop. Reference: Section 604.1, IPC 2012.
4. Revise the water service and water distribution piping as required to accommodate the increased demand for water meter #1. Verify that the pipe sizes called out will not result in water velocities greater than that recommended by the pipe manufacturer (e.g. limit the water velocity to less than 8 FPS for copper, PEX, or CPVC piping). Reference: Section 303.2, IPC 2012.
5. Provide a full-open valve for the water service at the building entrance. Reference: Section 606.1(2), IPC 2012.
6. Buildings not located on the same lot shall have separate sewer connections. Provide justification for connecting the grease waste from buildings located on separate lots and utilizing a common grease interceptor prior to connecting to the public sewer. The drawings indicate that up to ten different tenants could be sharing the same grease interceptor. Reference: Section 701.3, IPC 2012.
7. The rim elevation of the next upstream sanitary manhole (2394.72') is higher than the existing first floor elevations (2392.50' and 2393.50). Provide a backwater valve per Section 715.1, IPC 2012, as amended by the City of Tucson.
8. Provide roof drainage calculations for the new roof based on the 100-year hourly rainfall rate for Tucson, 3" per hour. Include in the calculations the effect of any vertical walls that can divert rainfall onto the roof. Reference: Sections 1106.1, 1106.4, and 1108.3, IPC 2012.
9. Clarify the purpose of the new 5" metal gutter (roof plan key note #21 on a3.2). Reference: Section 107.2.1, IBC 2012.
06/05/2014 ROBERT SHERRY WATER REVIEW Reqs Change 1. Reduced pressure backflow prevention assemblies are required to be installed in locations accessible to Tucson Water. Provide verification from Tucson Water that the locations of the three backflow preventers shown in the courtyard are acceptable to Tucson Water. Reference: Chapter XXVII, Article V, Section 27-72, the Tucson Code, http://cms3.tucsonaz.gov/sites/default/files/water/docs/backflow-ordinance.pdf
2. Revise the water pressure calculation for meter #1: the system is predominantly a flush valve system and the demand is much greater than stated. Tucson Water limits a 1" meter to a maximum demand of 37.5 GPM. Reference: Section 604.1, IPC 2012.
06/13/2014 LEERAY HANLY ELECTRICAL-COMMERCIAL REVIEW Reqs Change Plan review has been completed and the following corrections are required. Please provide a written response to comments with plan re-submittal.

1) Provide City of Tucson Outdoor Lighting Code compliance information. Reference OLC section 104.2
2) Architect of record to ensure that Electrical, Mechanical & Plumbing floor plans are coordinated with the reference floor plans. IBC section 107.2.1 (see vestibule 3012 area)
3) Descriptions of lighting fixtures noted under canopy do not appear to match locations. Provide cut-sheets for all exterior lighting fixtures.


If there are questions regarding this review contact:

LeeRay
520-837-4906
LeeRay.Hanly@tucsonaz.gov

Final Status

Task End Date Reviewer's Name Type of Review Description
07/17/2014 SHANAE POWELL OUT TO CUSTOMER Completed
07/17/2014 CPIERCE1 REJECT SHELF Completed