Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T14CM02729
Review Name: COMMERCIAL - TI
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 09/12/2014 | STEVE SHIELDS | ZONING | REVIEW | Denied | P&DS TRANSMITTAL FROM: Steve Shields, Lead Planner PROJECT: T14CM02729 & DP14-0074 Vida Nueva - Addition 330 W. Nebraska Street TRANSMITTAL: September 12, 2014 COMMENTS: the following comments are relative to an application for a Design Development Option (DDO) (UDC 3.11.1). A portion of this site is located in the R-2 zone (UDC 4.7.9). Religious Use is a permitted use in this zone (Table 4.8-2). 1. Per UDC TABLE 6.3-2.A: DIMENSIONAL STANDARDS FOR THE R-1, R-2, R-3, MH-1, & MH-2 ZONES, Nonres Use to Res Zone the required perimeter yard setback from the proposed addition, canopy addition, to the west property line is 10' or ¾ the height of the exterior wall, which ever is greatest, measured from grade to the highest point of the wall. That said based on a wall height of 23'-5" the required perimeter yard setback from the porch cover to the west property line is 17'-6", proposed perimeter yard based on a 2'-6" overhang is 4'-0". 2. Per UDC TABLE 6.3-2.A: DIMENSIONAL STANDARDS FOR THE R-1, R-2, R-3, MH-1, & MH-2 ZONES, Nonres Use to Res Zone the required perimeter yard setback from the proposed addition to the west property line is 10' or ¾ the height of the exterior wall, which ever is greatest, measured from grade to the highest point of the wall. That said based on a wall height of 29'-9" the required perimeter yard setback from the entry exterior wall to the west property line is 22'-4", proposed perimeter yard is 20'-0". The Building plan and development package cannot be approve until the DDO is approved. |
| 09/12/2014 | MARTIN BROWN | FIRE | REVIEW | Approved | |
| 10/09/2014 | AROMERO4 | MECHANICAL-COMMERCIAL | REVIEW | Needs Review | |
| 10/09/2014 | AROMERO4 | ELECTRICAL-COMMERCIAL | REVIEW | Needs Review | |
| 10/09/2014 | AROMERO4 | WATER | REVIEW | Needs Review | |
| 10/09/2014 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Needs Review | |
| 10/09/2014 | AROMERO4 | WWM | REVIEW | Needs Review | |
| 10/09/2014 | AROMERO4 | PLUMBING-COMMERCIAL | REVIEW | Needs Review | |
| 10/09/2014 | LOREN MAKUS | ENGINEERING | REVIEW | Approved | |
| 10/09/2014 | RONALD BROWN | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Completed |