Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T14CM02558
Review Name: COMMERCIAL - TI
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 05/13/2014 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. SHEET A1.0: PROVIDE ON THIS SHEET THE REQUIRED NUMBER OF PLUMBING FIXTURES PER THE IBC TABLE 2902.1, USING THE UPDATED OCCUPANT LOAD. 2. SHEET A1.0; CODE REVIEW (NUMBER OF EXITS): THE LOWER LEVEL INDICATES 3 EXITS ARE REQUIRED. REVISE PER THE IBC SECTION 1015. 3. SHEET A1.0; CODE REVIEW (OCCUPANCY SEPARATION): SECTION 302.3.3 IS REFERENCED FOR SEPARATION. REVISE THE CODE REFERENCE TO THE 2012 IBC. 4. SHEET A1.0; CODE REVIEW (OCCUPANT LOAD): TABLE 1003.2.2 IS REFERENCED FOR OCCUPANT LOAD. REVISE THE CODE REFERENCE TO THE 2012 IBC. 5. SHEET A1.0; CODE REVIEW (NUMBER OF EXITS): TABLE 1005.2.2 IS REFERENCED FOR THE NUMBER OF EXITS. REVISE THE CODE REFERENCE TO THE 2012 IBC. 6. SHEET A1.0; CODE REVIEW (EXIT TRAVEL DISTANCE): TABLE 1004.2.4 IS REFERENCED FOR EXIT TRAVEL DISTANCE. REVISE THE CODE REFERENCE TO THE 2012 IBC. 7. SHEET A3.0; KEYNOTES: NOTE 5 WAS NOT LOCATED ON THE ELEVATIONS. VERIFY. 8. SHEET S2.1; PLAN NOTES (15): IN NOTE 15, REFERENCE THE ARCHITECTURAL SHEET THAT INDICATES THE STRUCTURE SLOPE. 9. GENERAL: PROVIDE WRITTEN RESPONSES TO ALL REVIEW COMMENTS. |
| 05/15/2014 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | 1. Demonstrate energy code compliance for the addition to the building envelope using calculations based on the current code. Reference: Sections C101.4.3, C101.5, and C103.2, International Energy Conservation Code 2012. 2. Clarify the balancing notes for the existing fan coils (e.g. "Rebalance existing fan coil to3,000 CFM 975 CFM"?). Reference: Section 107.2.1, IBC 2012. |
| 05/15/2014 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | Provide secondary (overflow) roof drainage for the new sun deck and porch roof. Reference: Sections 1101, 1106 and 1108, IPC 2012, and Sections 1611.1 and 1611.3, IBC 2012. |
| 05/15/2014 | ROBERT SHERRY | WATER | REVIEW | Approved | |
| 05/15/2014 | STEVE SHIELDS | ZONING | REVIEW | Passed | |
| 05/20/2014 | MARTIN BROWN | FIRE | REVIEW | Approved | |
| 05/21/2014 | LEERAY HANLY | ELECTRICAL-COMMERCIAL | REVIEW | Completed | |
| 05/21/2014 | LHANLY1 | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed |