Permit Number: T14CM01996
Parcel: 127022690

Address:
5324 E 1ST ST 12

Review Status: Completed

Review Details: COMMERCIAL - TI

Permit Number - T14CM01996
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
04/11/2014 MARTIN BROWN FIRE REVIEW Approved
04/14/2014 DAVID RIVERA ZONING REVIEW Approved
04/21/2014 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Reqs Change 1. SHEET CS-1.0; BUILDING CODES: THE ACCESSIBILITY CODE REQUIRED FOR THIS PROJECT IS THE 2009 EDITION OF THE ICC/ANSI A117.1. REVISE.
2. SHEET CS-2.0; ACCESSORY MOUNTING HEIGHT INFORMATION: ADD A DIMENSIONED DETAIL FOR A HIGH/LOW DRINKING FOUNTAIN ON THIS SHEET.
3. SHEET A-2.0; NOTES: NOTES 15 AND 16 REFERENCE THE ADA GUIDELINES. REVISE TO THE ICC/ANSI.
4. SHEET A-3.0; NOTES: ADD A NOTE TO REFERENCE SHEET CS-2.0 FOR RESTROOM ACCESSIBILITY INFORMATION.
5. SHEET A-3.0; NOTES: NOTE 5 REFERENCES THE ADA GUIDELINES. REVISE TO THE ICC/ANSI.
6. SHEET A-3.0; ENLARGED FLOOR PLANS 1 AND 2: THE CITY OF TUCSON REQUIRES ALL LETTERING (UPPER AND LOWER CASE) TO BE A MINIMUM OF 3/32" IN HEIGHT. REVISE THE INTERIOR ELEVATIONS SHEET REFERENCE (A-8.2).
7. SHEET A-5.0; ROOF PLAN: AT THE ROOF NORTH OF THE KITCHEN AREA, KEYNOTE 9 IS LOCATED. SHOULD THIS BE KEYNOTE 10? VERIFY.
8. SHEET S011; SECTIONS: A KEYED CONSTRUCTION JOINT IS DETAILED AT THE LOWER LEFT OF THE PAGE, THEN AGAIN AT THE LOWER RIGHT. COORDINATE THESE DETAILS.
9. SHEET S031; TYPICAL WOOD STUD SHEAR WALL DETAIL: REFERENCE IS MADE IN A NOTE TO SEE THE SHEAR WALL SCHEDULE FOR MORE INFORMATION. WHERE IS THE SHEAR WALL SCHEDULE?
10. SHEET S101; FOUNDATION PLAN: THE PLAN INDICATES SW1, SW2, AND SW3. WHERE IS THE SCHEDULE LOCATED FOR THESE SHEAR WALLS?
11. SHEET S101 (FOUNDATION PLAN); SHEET S031 (HOLDOWN SCHEDULE): THE FOUNDATION PLAN REFERENCES HD AT THE END OF SHEAR WALLS, BUT NO SPECIFIC NUMBER FOR EACH HD (HDU2, HDU4, OR HDU5 IN THE SCHEDULE). CLARIFY.
12. SHEET S101 (FOUNDATION PLAN); STRUCTURAL CALCULATIONS: THE CALCULATIONS INDICATE THE COLUMNS ON GRID 1 (TYPICAL OF 4) TO BE HSS7X7X1/2, WHILE THE FOUNDATION PLAN INDICATES THOSE COLUMNS ARE HSS6X6X1/2. CLARIFY.
13. SHEET S101; FOUNDATION PLAN: WHERE ARE THE COLUMN FOOTING SCHEDULE AND THE WALL FOOTING SCHEDULE LOCATED ON THE DRAWINGS?
14. SHEET S101; FOUNDATION PLAN: AT THE INSIDE CORNER OF THE DINING ROOM (TWO LOCATIONS), A WF2.0 TURNS INTO A WF1.5. PROVIDE A DIMENSION WHERE THIS FOOTING TRANSITION IS LOCATED.
15. SHEET S301; ROOF FRAMING PLAN: THE BEAM DESIGNATED AS BEAM 6 IN THE CALCULATIONS (AT THE RESTROOMS) IS NOT LEGIBLE ON THE PLAN. REVISE.
16. SHEET S301; ROOF FRAMING KEYNOTES: ADD A NOTE TO REFERENCE SHEET S031 FOR THE LINTEL SCHEDULE.
17. SHEET S301; ROOF FRAMING PLAN: THE TWO STRUCTURAL MEMBERS (DIAGONAL) FROM THE NORTHWEST CORNER AND THE SOUTHWEST CORNER OF THE DINING AREA ARE NOT DESIGNATED FOR SIZE. PROVIDE.
18. SHEET S301; ROOF FRAMING KEYNOTES: NOTE 1 WAS NOT LOCATED ON THE PLAN. VERIFY.
19. SHEET S301 (KEYNOTE 1); SHEET S602 (SECTION 305); SECTION S603 (SECTION 316): THE KEYNOTE INDICATES ROOF PLYWOOD IS 1/2", WHILE THE TWO SECTIONS INDICATE 5/8". CLARIFY.
20. SHEET S602; SECTION 311 (NOTE 1): IS THIS MEMBER A WOOD BEAM OR A WOOD TRUSS? VERIFY.
21. STRUCTURAL CALCULATIONS: A CALCULATION IS PROVIDED FOR 'STEEL COLUMNNS GRID 1 CENTER BAY', AND IS LISTED AS A HSS6X6X3/8. WHERE ARE THESE COLUMNS ON THE FOUNDATION PLAN DRAWINGS? VERIFY.
22. GENERAL: PROVIDE WRITTEN RESPONSES TO ALL REVIEW COMMENTS.
04/23/2014 ERIC NEWCOMB COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Approved
04/29/2014 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Reqs Change 1. Replot the plumbing plans (P1.0, P1.1, P1.2, and P2.0) to make the backgrounds and lettering legible. Reference: Section 107.2.1, IBC 2012.
2. Provide tempered water for the lavatories using approved devices conforming to ASSE 1070. Reference: Sections 416.5 and 607.1, IPC 2012.
3. The specified backflow prevention device, Watts model 9BD, is not listed for ASSE 1022 as required for coffee machines or non-carbonated beverage dispensers. Reference: Section 608.16.10, IPC 2012.
04/29/2014 ROBERT SHERRY WATER REVIEW Reqs Change Coordinate the civil and plumbing plans with respect to the water service for the new kitchen. The civil plan (C3) shows a 1" service pipe connecting to an existing 3" water meter to serve the kitchen as compared to the plumbing plans which call for a new 1" meter, a 1-1/4" RPBP, and a 1-1/4" service pipe.
04/30/2014 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Reqs Change 1. Replot the mechanical plans (M1.0, M2.0, and M3.0) to make the backgrounds and lettering legible. Reference: Section 107.2.1, IBC 2012.
2. Revise the font size used on the drawing M1.0 to a minimum height of 3/32-inch. Reference: Section 107.2.1, IBC 2012.
3. Revise the Mechanical Notes on sheet M3.0 to reflect the current codes (e.g. notes 3, 4, 5, 6, and 11 cite incorrect section numbers).
4. The 2012 International Energy Compliance Code is the relevant energy code for this project. Revise the COMcheck mechanical compliance report shown on sheet M0.0 to reflect the correct code. Submit the report on 8.5" x 11" paper for legibility. Note that the mechanical design has been selected by the Architect as the method to be used to comply with the "Additional Efficiency Package Requirements" (C406, IECC 2012).
5. Provide heating and cooling load calculations that justify the capacities of the heating and cooling equipment specified for the project. Reference: Sections C403.2.1 and C403.2.2, IECC 2012.
6. Verify the installation requirements of EF-3 and EF-4 (e.g. does a ceiling-mounted exhaust fan such as EF-3 really require a roof curb?). Reference: Section 304.1, IMC 2012.
7. Show the size, routing, and termination of the condensate drains. Reference: Section 307.2.1, IMC 2012 as amended by the City of Tucson.
8. Revise the exhaust flow rate for the restroom exhaust fan, EF-4, so that all of the air supplied to the restrooms will be exhausted. Reference: Section 403.2.1 (4), IMC 2012.
9. Verify the outside air balancing data for the rooftop heat pumps as shown in the air balance schedule. Reference: Section 107.2.1, IBC 2012.
10. Clarify the size and type of exhaust duct for the hood served by EF-1. On sheet M1.0 it is a rectangular 24" x 24" grease duct with a field-applied grease duct enclosure but the shop drawing (M5.5) displays three separate choices for a 16" diameter factory-built, double-walled grease duct. Indicate the type and size of grease duct that will be employed. Reference: Section 107.2.1, IBC 2012.
11. The proposed Type I hood is listed as a wall-type canopy hood; provide information that shows that the listing of the hood allows the wall behind the hood can have a 60" wide x 30" high opening (keynote 4, A-2.0) without adversely affecting the performance of the hood.
05/06/2014 LEERAY HANLY ELECTRICAL-COMMERCIAL REVIEW Reqs Change Plan review has been completed and the following corrections are required. Please provide a written response to comments with plan re-submittal.

1) Electrical specifications do not meet the minimum 3/32" font size required by the City of Tucson.
2) Specify that luminaires SA1 and SA2 are to be full cut-off fixtures or provide sufficient information to show that site is in compliance with the Outdoor Lighting Code.


If there are questions regarding this review contact:

LeeRay
520-837-4906
LeeRay.Hanly@tucsonaz.gov Plan