Review Status: Completed
Review Details: COMMERCIAL - NEW
Permit Number - T14CM01172
Review Name: COMMERCIAL - NEW
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 04/25/2014 | MARTIN BROWN | FIRE | REVIEW | Approved | |
| 04/29/2014 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. SHEET A-2; BUILDING CODE CHART: UNDER 'SEPARATION RATINGS', COMPLETE THE LAST DISTANCE ('DISTANCE MORE THAN __'). 2. SHEET A-4; NOTES: NOTE 3 INDICATES TO 'REFERENCE S DRAWINGS FOR HP, LP, AND SLOPE OF CAST-IN-PLACE CONCRETE. VERIFY WHERE THOSE ARE FOUND ON THE STRUCTURAL DRAWINGS. 3. SHEET S-1; CAST-IN-PLACE CONCRETE: PROVIDE A NOTE INDICATING THE CLASS OF CONCRETE USED FOR THE VARIOUS DESIGN ELEMENTS (FOOTINGS, SLABS, WALLS, ETC.). 4. SHEET S-6; FOUNDATION PLAN NOTES: NOTE 1 INDICATES AN ALLOWABLE BEARING PRESSURE OF 3000 PSF. THE GEOTECHNICAL REPORT (PAGE 9) INDICATES A DESIGN CONTACT STRESS OF 2500 PSF. MAXIMUM. CLARIFY AND REVISE. 5. SHEET S-10: NO STRUCTURAL CALCULATIONS WERE LOCATED FOR THIS STRUCTURE. PROVIDE. 6. SHEET S-10; BUILDING SECTION C: A NOTE BELOW THE FOOTING TABLE INDICATES THE FOOTING WIDTH AND DEPTH INDICATED "REQUIRES WRITTEN APPROVAL FROM THE STRUCTURAL ENGINEER OF RECORD". EXPLAIN. 7. SHEET S-10 (BUILDING SECTION C); SHEET S-11 (FOUNDATION EARTHWORK NOTES): NOTE 1 INDICATES THE FOOTINGS WILL BE A MINIMUM OF 1'-6" BEARING DEPTH, WHILE THE SECTION (FOOTING TABLE) INDICATES A MINIMUM BEARING DEPTH "D" OF 12". CLARIFY. 8. SHEET S-10; FLOOR PLAN: KEY NOTE 21 IS INDICATED IN THE NORTHEAST CORNER OF THE BUILDING. IS THIS NOTE CORRECT AT THAT LOCATION? 9. GENERAL: THE CHEMICAL AREA STRUCTURE (1200 SF) AND THE SECURITY WALL (1082') WERE NOT INCLUDED IN THE ORIGINAL VALUATION. THESE HAVE BEEN ADDED DURING THIS REVIEW. 10. GENERAL: PROVIDE WRITTEN RESPONSES TO ALL REVIEW COMMENTS. |
| 05/01/2014 | JASON GREEN | ENGINEERING | REVIEW | Reqs Change | Building Plan can not be approved until approval of the DP Package (DP14-0033). |
| 05/06/2014 | MICHAEL ST. PAUL | ZONING | REVIEW | Needs Review | Approval of DP14-0033 is required. |
| 05/08/2014 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Approved | |
| 05/08/2014 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Approved | |
| 05/08/2014 | ROBERT SHERRY | WATER | REVIEW | Approved | |
| 05/14/2014 | LEERAY HANLY | ELECTRICAL-COMMERCIAL | REVIEW | Completed |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 05/15/2014 | AROMERO4 | OUT TO CUSTOMER | Completed |