Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - NEW
Permit Number - T14CM00889
Review Name: COMMERCIAL - NEW
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
02/20/2014 | DAVID RIVERA | ZONING | REVIEW | Reqs Change | Project: T14CM00889 Date: February 20, 2014 From: David Rivera Principal Planner 1. Comment: Zoning has reviewed the building plans but cannot approve them at this time. The development package site plan is under review and has not been approved as of this building plan review. While the building plans are consistent with the development package site plan as it applies to the zoning review purview, the plans cannot be approved until the DP and the commercial plans reviewers have approved the building plans. Zoning will review the building plans for compliance with the approved DP site plan (if it is approved) on the next submittal and if possible approve the building plans. |
02/21/2014 | LOREN MAKUS | ENGINEERING | REVIEW | Denied | The Development Package must be approved first. |
02/25/2014 | KEN BROUILLETTE | FIRE | REVIEW | Denied | Please include the following fire sprinkler design criteria to the plans. 1. Flow data (static pressure, residual pressure, GPM) Performed by sprinkler company. 2. The standard to be used in development of sprinkler system. (NFPA 13, NFPA 13R, or NFPA 13D) 3. The hazard classification of the building, including any special hazards. 4. The density required of the water supply. 5. Need storage plan. Per 2012 International Fire Code, mattresses are a "high hazard" commodity. Chapter 2 and Table 3602.6 indicate if storage height is greater than 6'-0" above finished floor, smoke and heat removal systems must be installed (or ESFR sprinklers). |
02/26/2014 | LEERAY HANLY | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | 1. Minimum font size for City of Tucson submittals is 3/32". Please adjust details 1 & 2 pp E1.1 and 1-line diagram language pp E2.1. 1.a Errata...One line diagram indicates 200 A upstream main instead of the actual 400A. 2. Connecting exhaust fans in restrooms to an occupancy sensor results in a violation of IMC 403.2.1 (recirculation of air when A/C is on). Interconnection of exhaust to RTU-1 or placing exhaust on a timer (on while building occupied) will resolve this conflict. |
02/27/2014 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Reqs Change | GENERAL 1. Please provide structural calculations 2. Provide certification of special inspectors SHEET A0.2 3. Detal 7: Main accessible sign to be 7'-0" a.f.g. 4. Detail A, B and Floor Plan: a. Provide vertical grab bar as per 2009 ICC A117.1, Section 604.5.1. b. Provide dimensions as per 604.5.1 and 604.5.2. c. Provide water closet clearance as per Section 604.3. 5. Accessible Sign Notes: RE: Delete all references to ADAAG and provide requirements as per the 2012 IBC, Chapter 11 and the 2009 ICC A117.1, Chapter 7. 6. Notes: Delete all references to ADAAG and provide requirements as per the 2012 IBC, Chapter 11 and the 2009 ICC A117.1. END OF REVIEW |
03/03/2014 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Provide tempered water for the lavatories using approved devices conforming to ASSE 1070. Reference: Sections 416.5 and 607.1.2, IPC 2012. 2. Provide a vacuum relief valve for the specified bottom-fed storage-type water heater. Reference: Section 504.2, IPC 2012. 3. Provide a watertight pan of galvanized steel (minimum 24-gage) or other approved material under the water heater with a drain to an approved location. Reference: Section 504.7, IPC 2012. 4. Provide cleanouts for all horizontal drains (e.g. the 4" building drain); the cleanouts shall be sized per Section 708.7, IPC 2012. Reference: Sections 708.3.1, IPC 2012. |
03/03/2014 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Demonstrate energy code compliance for the building envelope and the mechanical systems using calculations based on the current code (the 2009 IECC and 2000 IMC are referenced on sheet MP1.1). Provide sufficient detail on the drawings to evaluate the energy compliance of the building envelope. The information shall, as a minimum, include U-factors of the fenestration components and the SHGC for the fenestration. Reference: Sections C101.3, C101.5, C103.2, and C401.2, International Energy Conservation Code 2012. 2. Show that the proposed HVAC system meets the requirements of Sections C403.2, C403.3 and, if neither the efficient lighting system nor the on-site renewable energy options are selected, C406.2, IECC 2012 (using the mechanical energy code compliance certification from COMcheck is acceptable). Reference: Section C303.1, International Energy Conservation Code 2012. 3. Provide heating and cooling load calculations that justify the capacities of the heating and cooling equipment specified for the project. Reference: Sections C403.2.1 and C403.2.2, IECC 2012. 4. Provide automatic shutoff dampers for the outdoor air supply. Reference: Section C403.2.4.4, IECC 2012. 5. Show how excess outside air relief from the building is to be accomplished. Reference: Section C403.3.1.1.4, IECC 2012. |
03/03/2014 | ROBERT SHERRY | WATER | REVIEW | Denied | Provide a site drawing showing the size and route of the building water supply along with the location and size of both the water meter and the reduced pressure backflow preventer assembly. Reference: Section 107.2.1, IBC 2012. |
03/03/2014 | GERARDO BONILLAS | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
03/14/2014 | AROMERO4 | OUT TO CUSTOMER | Completed |