Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T14CM00820
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
02/11/2014 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. SHEET TS1: EACH OF THE FOUR SUITES WILL REQUIRE A SEPARATE PERMIT. PROVIDE A SQUARE FOOTAGE FOR EACH SUITE (TOTAL 3527 SF). SINCE THESE ARE GREY BOXES, NO OCCUPANCY LOAD WILL BE REQUIRED UNTIL THE FIRST TENANT MOVES IN AND APPLIES FOR A C OF O OR TI. 2. SHEET A1; DETAILS 3 AND 4: PROVIDE THE CONNECTION SIZE AND QUANTITY FOR THE DIAGONAL BRACES TO THE STRUCTURE ABOVE AND TO THE WALL. BRACES WOULD NOT BE REQUIRED IF WALL STUDS ARE CONNECTED DIRECTLY TO THE STRUCTURE ABOVE. |
02/11/2014 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Show that the proposed HVAC split system meets the requirements of Sections C403.2.2, C403.2.3, C403.2, and C403.3 (e.g. provide the mechanical energy code compliance certification from COMcheck). Reference: Section C303.1, International Energy Conservation Code 2012. 2. Provide heating and cooling load calculations that justify the capacities of the heating and cooling equipment specified for the project. Reference: Sections C403.2.1 and C403.2.2, IECC 2012. |
02/11/2014 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | Provide structural details and calculations for the mounting shelf for the water heater to show that the water heater will be safely supported from the building structure. Reference: Section 301.2, IPC 2012. |
02/11/2014 | ROBERT SHERRY | WATER | REVIEW | Approved | |
02/11/2014 | ERIC NEWCOMB | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | |
02/12/2014 | JASON GREEN | ENGINEERING | REVIEW | Approved | |
02/12/2014 | LEERAY HANLY | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | 1) There are references to "existing" lighting. Provide the activity #'s for any such existing lighting that may be planned to be installed in these empty shell spaces. (IBC 107.1) 2) All panels and service disconnects to be labeled in accordance with TEP rules and standard formatting. (the suite/panel addresses do not match the legal street addresses) |
02/12/2014 | MICHAEL ST. PAUL | ZONING | REVIEW | Approved | |
02/12/2014 | MARTIN BROWN | FIRE | REVIEW | Denied | Please correct address on every sheet. Correct suite numbers should be annotated on every sheet. Calculate occupant loads for each suite. |
03/03/2014 | SPOWELL1 | WWM | REVIEW | Needs Review |