Plan Number: T13PI00019
Parcel: Unknown

Address:
4050 E BENSON HY

Review Status: Completed

Review Details: PIA - RESUBMITTAL

Plan Number - T13PI00019
Review Name: PIA - RESUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
04/14/2014 GARY WITTWER DOT LANDSCAPE REVIEW Denied Thanks for sending the letter from Andy D. Please submit your landscape and irrigation plans.
04/25/2014 RLEIGH1 UTILITY CLEARANCES COT STREETS DIVISION Denied
04/25/2014 RICHARD LEIGH DOT ENGINEERING REVIEW Approv-Cond April 24, 2014

SUBJECT: Contera - South Phase Lots 73 - 143.

PROJECT REVIEWER: Richard Leigh, DOT, Permits and Codes Section

RESUBMITTAL REQUIRED: Permits and Codes Section has reviewed the PIA Plan and recommends a conditional approval at this time. The following comments need to be addressed prior to the mylar plan set being submitted for signatures. Please return redlined drawings with next submittal.

1. Sheet 3, Detail G: The cross slope of the ramp/landing area on the ramp must not exceed 50:1. A access ramp based on a ADOT C-Standards C-5.30 may be considered. Also, vehicle access ramps should be based on PC/COT Std. Dtl. 206.

Please Refer to redline plans for additional comments and comment details.

If you have any questions, I can be reached at 837-6647 or Richard.Leigh@tucsonaz.gov
04/25/2014 RLEIGH1 UTILITY CLEARANCES COT WATER NEW DEVELOPMENT Denied
04/25/2014 RLEIGH1 UTILITY CLEARANCES PC WASTEWATER MGMT Denied
04/25/2014 RLEIGH1 UTILITY CLEARANCES QUEST COMMUNICATION Denied
04/25/2014 RLEIGH1 UTILITY CLEARANCES TUCSON ELECTRIC POWER CO Denied
04/25/2014 RLEIGH1 UTILITY CLEARANCES COX COMMUNICATION Denied
04/25/2014 RLEIGH1 UTILITY CLEARANCES SOUTHWEST GAS CORP Denied
04/25/2014 RLEIGH1 UTILITY CLEARANCES EL PASO NATURAL GAS Denied
04/25/2014 RLEIGH1 UTILITY CLEARANCES KINDER MORGAN ENERGY Denied
05/02/2014 LANCE PETERSON DOT STREET MAINTENANCE REVIEW Approved
05/07/2014 LINZUNZA PIA COORDINATOR CUSTOMER CALLED; PLANS @ AMBASSADOR Completed Please submit Utility Plan Receipts.
05/07/2014 LINZUNZA PIA COORDINATOR OUT TO CUSTOMER Completed Please submit Utility Plan Receipts.
06/18/2014 JOSE ORTIZ DOT TRAFFIC REVIEW Approv-Cond PLANS # i-2013-016
ACTIVITY NUMBER: T13PI00019
PROJECT NAME: Cantera S Phase 73-142
PROJECT ADDRESS: Benson Hwy & Alvernon Wy
PROJECT REVIEWER: Matthew Geweke, Traffic Eng. Tech

Resubmittal Required: Traffic Engineering does not recommend approval of the PIA Plan; therefore a revised PIA Plan is required for re-submittal. The following items must be revised or added to the plan. Please include a response letter with the next submittal that states how all comments have been addressed and resubmit the original redline set of plans for back checking purposes.

See redlines on the submitted drawing Shts. 12, 13, 14, 18 to address these comments.

Sht. 12:
- Please do not add STOP signs to the internal non-arterial intersections.

- Please use Striping Standard 6-4 to create proper signing & striping for the beacon pedestrian crossing;
Give proper distance to W11-2 signs from the leg of crosswalk.
Make sure WS8 placement and lengths are correct.

- Remove the superfluous/confusing measurements and markings.

- Do provide proper lane widths (and lengths when needed), also use the proper stripe nomenclatures.

- The 9-R9-3a signs are an option if you feel they are necessary for this install.
(if so, please see red-line comment and add median sign at Sta 58+50 +/-)

- If Sta 63+50 is a bus stop (present or planned), please see redline comment.

- Please use the right turn traffic island Striping Standard 5-16 & Signing Standard 9-5b for N-bound Alvernon Wy at Sta 68+00

- Suggest showing the R10-23 signs on the Signing Sht.
(a courtesy to the sign contractor)

- Take care to research which larger signs do require double posts, and note the correct configuration for color and size of signs. This will help prevent sign manufacture confusion.

Sht 13:
- Nice detail for the future sign 'and post' removal.
(yes, you do need to tell them to remove the post please)

Sht 14:
Suggest adding street name sign size note for sign manufacturer.

Sht 18:
Suggest adding sign nomenclature for the beacon push-button instruction sign.


Please do email me at Matthew.Geweke@tucsonaz.gov with a PDF of redlines and the corrected Shts with the revisions of these requested changes so we can expedite the Traffic Eng. acceptance/approval of these plans.

I can also be reached at 791-4259 x76665 with any questions.
Thanks