Plan Number: T13PI00017
Parcel: Unknown

Address:
695 S MAIN AV

Review Status: Active

Review Details: PIA - SUBMITTAL

Plan Number - T13PI00017
Review Name: PIA - SUBMITTAL
Review Status: Active
Review Date Reviewer's Name Type of Review Description Status Comments
09/19/2013 ANY DOT ENGINEERING REVIEW Active
09/19/2013 ANY PIA COORDINATOR CUSTOMER CALLED; PLANS @ AMBASSSADOR Active
09/19/2013 ANY PIA COORDINATOR OUT TO CUSTOMER Active
09/24/2013 JOSE ORTIZ DOT TRAFFIC REVIEW Denied i-2013-015
ACTIVITY NUMBER: T13PI00017
PROJECT NAME: 18th St. & Main Ave. Offsite Improvements
PROJECT ADDRESS: 695 S Main Ave.
PROJECT REVIEWER: Matthew Geweke, Traffic Eng Tech

Resubmittal Required: Traffic Engineering does not recommend approval of the PIA Plan; therefore a revised PIA Plan is required for re-submittal. The following items must be revised or added to the plan. Please include a response letter with the next submittal that states how all comments have been addressed.

1. See redlines on the submitted drawing Shts 1 & 2 and address the additional redline comments.
- Please fix or include omitted signing notes on plans Sht 1.
- Please do replace with new; post and D11-1 sign on Sht 2
- Please do use TDOT sign post & foundation Standard 8-2A

If you wish to email me (Matthew.Geweke@tucsonaz.gov) a PDF of plans with the revisions of these requested changes, we could expedite the Traffic Eng. acceptance of these plans.

I can also be reached at 791-4259 x76665 with any questions.
Thanks…!
Matthew Geweke
10/21/2013 LANCE PETERSON DOT STREET MAINTENANCE REVIEW Denied We have reviewed this plan and have the following comments:

1. Sheet 1 - Please provide a Streets and Traffic Maintenance Signature line in the title block.
2. Sheet 1 - Note 5 - This note mentions matching pavement section of 22nd Street. How was this determined given that the project is off of 18th Street and Main Avenue. What is the pavement section?
3. Sheet 2 - The two driveways off of 18th should continue through the new sidewalk or need to call for a 6" thick concrete sidewalk at these locations.
4. Sheet 2 - The driveway centered at Station 10+69.01 appears to need an additional station and offset for the start of the transition or the start of the depressed curb to locate.
5. Sheet 2 - Is there another curb transition needed for the driveway centered at Station 11+22.75?

No further comments.

Lance Peterson, P.E.
Streets and Traffic Maintenance
520-837-6777
12/03/2013 BESPINO1 UTILITY CLEARANCES COT STREETS DIVISION Denied
12/03/2013 GARY WITTWER DOT LANDSCAPE REVIEW Approved
12/03/2013 BESPINO1 UTILITY CLEARANCES COT WATER NEW DEVELOPMENT Denied
12/03/2013 BESPINO1 UTILITY CLEARANCES PC WASTEWATER MGMT Denied
12/03/2013 BESPINO1 UTILITY CLEARANCES QUEST COMMUNICATION Denied
12/03/2013 BESPINO1 UTILITY CLEARANCES TUCSON ELECTRIC POWER CO Denied
12/03/2013 BESPINO1 UTILITY CLEARANCES COX COMMUNICATION Denied
12/03/2013 BESPINO1 UTILITY CLEARANCES SOUTHWEST GAS CORP Denied
12/03/2013 BESPINO1 UTILITY CLEARANCES EL PASO NATURAL GAS Denied
12/03/2013 BESPINO1 UTILITY CLEARANCES KINDER MORGAN ENERGY Denied