Plan Review Detail
Review Status: Completed
Review Details: PIA - SUBMITTAL
Plan Number - T13PI00010
Review Name: PIA - SUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
07/03/2013 | JOSE ORTIZ | DOT TRAFFIC | REVIEW | Denied | i-2013-010 ACTIVITY NUMBER: T13PI00010 PROJECT NAME: The Bridges Blk 10 PROJECT ADDRESS: PROJECT REVIEWER: Matthew Geweke, Traffic Eng Tech Resubmittal Required: Traffic Engineering does not recommend approval of the PIA Plan; therefore a revised PIA Plan is required for re-submittal. The following items must be revised or added to the plan. Please include a response letter with the next submittal that states how all comments have been addressed. 1. See redlines on the submitted drawing Shts 9 & 10 and address the additional redline comments. (A) Sht 9: modify the Tucson Marketplace Blvd striping to standard. (B) Sht 10: remove unnecessary 25mph & Stop signs. (C) Sht 10: add proper Tucson Marketplace Blvd turn bay signs. During the next submittal please re-submit the original roll of redlines for back checking purposes. 2. Please include omitted signing and striping notes on plans as needed. See redline notes and attachments. If you wish to email me (Matthew.Geweke@tucsonaz.gov) a PDF of Shts 9 & 10 with the revisions of these requested changes, we could expedite the Traffic Eng. acceptance of these plans. I can also be reached at 791-4259 x76665 with any questions. Thanks! Matthew Geweke |
07/03/2013 | BESPINO1 | UTILITY CLEARANCES | COT STREETS DIVISION | Denied | |
07/03/2013 | BESPINO1 | UTILITY CLEARANCES | COT WATER NEW DEVELOPMENT | Denied | |
07/03/2013 | BESPINO1 | UTILITY CLEARANCES | PC WASTEWATER MGMT | Denied | |
07/03/2013 | BESPINO1 | UTILITY CLEARANCES | QUEST COMMUNICATION | Denied | |
07/03/2013 | BESPINO1 | UTILITY CLEARANCES | TUCSON ELECTRIC POWER CO | Denied | |
07/03/2013 | BESPINO1 | UTILITY CLEARANCES | COX COMMUNICATION | Denied | |
07/03/2013 | BESPINO1 | UTILITY CLEARANCES | SOUTHWEST GAS CORP | Denied | |
07/03/2013 | BESPINO1 | UTILITY CLEARANCES | EL PASO NATURAL GAS | Denied | |
07/03/2013 | BESPINO1 | UTILITY CLEARANCES | KINDER MORGAN ENERGY | Denied | |
07/15/2013 | GARY WITTWER | DOT LANDSCAPE | REVIEW | Denied | Thanks for including the NPPO Plans. 1. It appears that there are common areas on the plan. Will they be landscaped and will they have irrigation? Please remember that private irrigation lines can not cross public roadway. (unless you get an irrigation easement) 2. Please submit Landscape and irrigation plans for Common Areas. |
07/24/2013 | LANCE PETERSON | DOT STREET MAINTENANCE | REVIEW | Denied | I have reviewed this plan and have the following questions: 1. The note call out the use of mix number 1 and mix number 2 for the project. I did not see where the differnet mixes will be used. 2. There are different common areas called out on the plans. Common Area "C" is listed as a private drainage but Common Area "A" and "B" are not labeled. Who is responcible for the maintennance of these common areas? No further comments. Lance Peterson, P.E. Streets and Traffic Maintenance 837-6777 |
08/08/2013 | RICHARD LEIGH | PIA COORDINATOR | CUSTOMER CALLED; PLANS @ AMBASSSADOR | Completed | |
08/08/2013 | RICHARD LEIGH | DOT ENGINEERING | REVIEW | Approv-Cond | Please address red line comments prior to submittal of mylar plan set for final approval. Call me if you have ay questions Richard Leigh 837-6647 |
08/08/2013 | RICHARD LEIGH | PIA COORDINATOR | OUT TO CUSTOMER | Completed |