Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Plan Review Detail
Review Status: Completed
Review Details: PIA - RESUBMITTAL
Plan Number - T13PI00008
Review Name: PIA - RESUBMITTAL
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 11/15/2013 | GARY WITTWER | DOT LANDSCAPE | REVIEW | Approved | |
| 11/15/2013 | BESPINO1 | UTILITY CLEARANCES | COT STREETS DIVISION | Completed | |
| 11/15/2013 | LANCE PETERSON | DOT STREET MAINTENANCE | REVIEW | Approved | |
| 11/15/2013 | BESPINO1 | UTILITY CLEARANCES | COT WATER NEW DEVELOPMENT | Completed | |
| 11/15/2013 | JOSE ORTIZ | DOT TRAFFIC | REVIEW | Approved | |
| 11/15/2013 | BESPINO1 | UTILITY CLEARANCES | PC WASTEWATER MGMT | Completed | |
| 11/15/2013 | BESPINO1 | UTILITY CLEARANCES | QUEST COMMUNICATION | Completed | |
| 11/15/2013 | BESPINO1 | UTILITY CLEARANCES | TUCSON ELECTRIC POWER CO | Completed | |
| 11/15/2013 | BESPINO1 | UTILITY CLEARANCES | COX COMMUNICATION | Completed | |
| 11/15/2013 | BESPINO1 | UTILITY CLEARANCES | SOUTHWEST GAS CORP | Completed | |
| 11/15/2013 | BESPINO1 | UTILITY CLEARANCES | EL PASO NATURAL GAS | Completed | |
| 11/15/2013 | BESPINO1 | UTILITY CLEARANCES | KINDER MORGAN ENERGY | Completed | |
| 11/26/2013 | RICHARD LEIGH | DOT ENGINEERING | REVIEW | Approved | 1. Sheet 3, Structural section No. 1: Indicate mix No. per SSPI , Sec. 406 for asphaltic pavement. 2. Sheet 5, Sidewalk Ramp Detail: Place a note indicating that the curb access ramp and adjoining sidewalk may need to be field fitted to accommodate existing roadway infrastructure. |
| 11/26/2013 | RICHARD LEIGH | PIA COORDINATOR | CUSTOMER CALLED; PLANS @ AMBASSADOR | Completed | |
| 11/26/2013 | RICHARD LEIGH | PIA COORDINATOR | OUT TO CUSTOMER | Completed |