Permit Number: T13CM07742
Parcel: 13014039A

Review Status: Completed

Review Details: COMMERCIAL - NEW

Permit Number - T13CM07742
Review Name: COMMERCIAL - NEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
01/06/2014 ROBERT SHERRY WATER REVIEW Approved
01/07/2014 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied 1. Clarify the labeling of the details on sheet P5; all of the details are noted as being on sheet P6.
2. Coordinate the soil and vent riser (5/P3) for the west restrooms (3/P3 and 4/P3) to show the same number of water closets on the first floor.
3. Clarify the soil and vent riser (3/P5); is it for the east restrooms (3/P3 and 4/P3) or the west restrooms - it has some aspects of both.
4. Verify that the thermostatic mixing valves for the lavatories will be listed as complying with ASSE 1070. Reference: Sections 416.5 and 607.1.2, IPC 2012.
5. Verify that the roof drains used for the secondary (overflow) roof drainage system conform to ASME A112.6.4 0r ASME A112.3.1 (see detail 3/A12). Reference: Section 1102.6, IPC 2012.
01/08/2014 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Denied 1. Revise the energy code analysis for the building envelope, coordinating the building components used in the analysis with those shown on the drawing (e.g. R-11 insulation for the exterior walls in COMcheck but R-5 insulation shown on the wall sections). Reference: Section C303.1, IECC 2012, as amended by the City of Tucson.
2. Complete the Envelope Compliance Certificate by checking the appropriate line items in Section 3, the Air Leakage, Component Certification, and Vapor Retarder Requirements. Supporting documentation shall be either on the drawings or in the project manual.
3. The body of the schedule for the second-floor packaged heat pumps refers to note #14 but no note #14 is included. Is note #15 mis-numbered?
4. Verify the required fire-rating for the duct chases with the architect. Reference: Section 607.5, IMC 2012.
01/09/2014 STEVE SHIELDS ZONING REVIEW Denied PDSD TRANSMITTAL

FROM: Steve Shields
Lead Planner

PROJECT: 3950 E Juarez Street
T13CM07242
Building Plan (1st Review)

TRANSMITTAL DATE: January 9, 2014

1. The building plans have been reviewed by Zoning Review Section but cannot approve the plan until all zoning comments or concerns have been addressed.

2. Zoning has reviewed the building plans and it appears that they meet the requirements of the development package. Once all other PDSD review agencies have approved the building plan Zoning will approve the plan.

3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved development package. Additional comments may be forthcoming.

If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956
01/09/2014 RONALD BROWN COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Completed
01/09/2014 RONALD BROWN BUILDING-COMMERCIAL REVIEW Reqs Change SHEET T1
1. Please provide code analysis summary for building component fire rating requirements as per table 602 of the 2012 IBC.
2. Please provide code analysis for all vertical shaft fire ratings.
SHEET A1
3. Please identify all fire rated partitions such as stair wells, elevator shafts, elevator equipment room, mechanical shafts and etc.
4. Please provide an emergency egress plan.
SHEET A2
5. Please identify all fire rated partitions such as stair wells, elevator shafts, elevator equipment room, mechanical shafts and etc.
6. Add rated doors to both stair wells to maintain a fire protected vertical stair shaft as per the 2012 IBC, Sections 712, 713 and 1022.
7. Provide fire protection at the two atriums as per the 2012 IBC, Section 404.
a. Section reference 2/A5 shows a handrail detail where as the floor plan shows a continous wall. Please correct as required by code.
8. For both floor plans, please provide a partition reference schedule and identify all partition types accordingly.
a. Identify all required fire rated partitions.
SHEET A3
9. At note 2, show the painting spectification page number.
SHEET A7
10. At detail 3, provide a min distance of 4'-8" from the side of the lavarory to the water closet back wall of the single toilet room.
a. Provide a room number for this toilet room.
11. Provide another partial plan for the second floor. Detail 1 is not typical for both floors.
a. Insure a complete fire rated stair well enclosure by adding rated doors and walls for both stair wells.
SHEET A8
12. At detail 8, extend the handrails 12" from the bottom riser.
STRUCTURAL CALCULATIONS.
13. Up date the roof framing plan by including all the roof penetrations and beam additions.
14. Provide structural calculations for the light pole foundation.
END OF REVIEW.
01/15/2014 LAITH ALSHAMI ENGINEERING REVIEW Approved
12/27/2013 KEN BROUILLETTE FIRE REVIEW Approved
12/31/2013 LEERAY HANLY ELECTRICAL-COMMERCIAL REVIEW Approved

Final Status

Task End Date Reviewer's Name Type of Review Description
01/17/2014 CPIERCE1 REJECT SHELF Completed