Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T13CM07522
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
01/03/2014 | GERRY KOZIOL | WWM | REVIEW | Passed | |
12/12/2013 | MICHAEL ST. PAUL | ZONING | REVIEW | Approved | |
12/13/2013 | ROBERT SHERRY | WATER | REVIEW | Approved | |
12/13/2013 | RAY MAJUTA | ELECTRICAL-COMMERCIAL | REVIEW | Denied | T13CM07522 1. Provide 2012 IECC Budget Lighting Calculation, required per C of T---- TI Submittal Requirements. ComCheck ok. Ray Majuta PDSD, Tucson Elect Plan Review 12/13/2013 Ray.Majuta@tucsonaz,gov |
12/13/2013 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Provide justification for the heating and cooling capacities for the two rooftop units. Based on your load calculations, the units are oversized. Reference; section C403.2.2, IECC 2012. 2. Show that the proposed HVAC systems meet the control requirements of Sections C403.2.4 and C403.3. Reference: Section C303.1, International Energy Conservation Code 2012. 3. Show that the specified packaged air conditioning units meet the minimum efficiency requirements. Reference: Section C403.2.3, IMC 2012. 4. Show how the propsed design for the HVAC system provides for relief of the excess air outdor air during economizer operation. Reference: Section C403.3.1.1.3, IECC 2012. 5. Provide calculations to show that the proposed air conditioning units provide adequate ventilation using the current code. Reference: Section 403.2, IMC 2012. |
12/13/2013 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Reqs Change | Provide structural calculations for the Cashwrap soffit suspension system. |
12/13/2013 | JASON GREEN | ENGINEERING | REVIEW | Approved | |
12/13/2013 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Approved | Show how the replacement water heater for the restroom lavatory will limit the water temperature to a maximum of 110 degrees Fahrenheit. |
12/13/2013 | MARTIN BROWN | FIRE | REVIEW | Approved | |
12/13/2013 | RONALD BROWN | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
01/03/2014 | SHANAE POWELL | APPROVAL SHELF | Completed |
01/03/2014 | SHANAE POWELL | OUT TO CUSTOMER | Completed |