Permit Number: T13CM07487
Parcel: 107020150

Review Status: Completed

Review Details: COMMERCIAL - NEW

Permit Number - T13CM07487
Review Name: COMMERCIAL - NEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
01/22/2014 MARTIN BROWN FIRE REVIEW Approved
01/24/2014 MICHAEL ST. PAUL ZONING REVIEW Reqs Change DP13-0245 approval is required.
01/24/2014 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Denied 1. SHEET A2.0; NORTH ELEVATION: NOTE 7 ON THIS ELEVATION IS NOT CORRECT. REVISE.
2. SHEET A2.0; SOUTH AND EAST ELEVATIONS: REVISE NOTE 7 ON THESE ELEVATIONS TO NOTE 8.
3. SHEET A4.0; METAL BUILDING NOTE: ADD VERBIAGE TO THIS NOTE INDICATING THE DRAWINGS AND CALCULATIONS OF THE METAL BUILDING MANUFACTURER HAVE BEEN APPROVED FOR CONFORMANCE TO THE STRUCTURAL DESIGN. THE APPROVAL NOTE MUST BE SIGNED AND DATED BY THE ENGINEER OF RECORD PRIOR TO SUBMITTAL OF THE METAL BUILDING DRAWINGS TO THE CITY OF TUCSON.
4. SHEET S1.0; STRUCTURAL NOTES (GENERAL CONSTRUCTION): NOTE 7 MUST ALSO INCLUDE VERBIAGE IN THIS NOTE INDICATING THE DRAWINGS AND CALCULATIONS OF THE METAL BUILDING MANUFACTURER HAVE BEEN APPROVED FOR CONFORMANCE TO THE STRUCTURAL DESIGN. THE APPROVAL NOTE MUST BE SIGNED AND DATED BY THE ENGINEER OF RECORD PRIOR TO SUBMITTAL OF THE METAL BUILDING DRAWINGS TO THE CITY OF TUCSON.
5. SHEET S1.0; STRUCTURAL NOTES (GENERAL CONSTRUCTION): THE SEISMIC LOAD REFERENCES THE 2006 IBC AND SECTION 1617.5. REVISE THE CODE EDITION AND SECTION TO THE 2012 IBC.
6. SHEET S1.0; STRUCTURAL NOTES (GENERAL CONSTRUCTION): THE SOIL BEARING REFERENCES THE IBC TABLE 1804.2. REVISE THE TABLE TO THE 2012 IBC.
7. SHEET S1.0; STRUCTURAL NOTES (CONCRETE FOUNDATION): THE TABLE REFERENCE IN NOTE 1 IS NOT CORRECT FOR THE 2012 IBC. REVISE.
8. SHEET S1.0; STRUCTURAL NOTES (CONCRETE FOUNDATION): THE IBC SECTION REFERENCE IN NOTE 10 IS NOT CORRECT FOR THE 2012 IBC. REVISE.
9. SHEET S1.0; STRUCTURAL NOTES (CONCRETE MASONRY): THE IBC TABLE REFERENCE IN NOTE 2 IS NOT CORRECT FOR THE 2012 IBC. REVISE.
10. SHEET S1.1; FOUNDATION KEY PLAN NOTES: NOTE 3 WAS NOT LOCATED ON THE PLAN. VERIFY.
11. GENERAL: PROVIDE WRITTEN RESPONSES TO ALL REVIEW COMMENTS.
01/24/2014 ERIC NEWCOMB COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Passed
01/27/2014 JASON GREEN ENGINEERING REVIEW Reqs Change ENG will provide approval of the building plan upon approval of the DP Package. JG
01/29/2014 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Passed
01/29/2014 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied Clarify the size of the water service to the building. Keynote 5 on sheet P1.0 calls for a 1" service from the existing ¾" meter but keynote 22 on sheet C1.0 calls for a 1-1/4" water service to the building.
01/29/2014 ROBERT SHERRY WATER REVIEW Passed
02/03/2014 JEFF DRUMM LANDFILL REVIEW Approved
02/04/2014 LEERAY HANLY ELECTRICAL-COMMERCIAL REVIEW Completed

Final Status

Task End Date Reviewer's Name Type of Review Description
02/06/2014 FERNE RODRIGUEZ OUT TO CUSTOMER Completed
02/06/2014 CPIERCE1 REJECT SHELF Completed