Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - NEW
Permit Number - T13CM07058
Review Name: COMMERCIAL - NEW
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
11/29/2013 | MARTIN BROWN | FIRE | REVIEW | Approved | |
12/02/2013 | STEVE SHIELDS | ZONING | REVIEW | Denied | PDSD TRANSMITTAL FROM: Steve Shields Lead Planner PROJECT: P & H Construction - New Storage Building. T13CM07058 Building Plan (1st Review) TRANSMITTAL DATE: December 4, 2013 1. The building plans have been reviewed by Zoning Review Section but cannot approve the plan until all zoning comments or concerns have been addressed. 2. An approved development package is required prior to approval of the building plan. 3. Until the change of rezoning conditions has been approved by Mayor and Council the building plans cannot be approved. 4. Zoning will re-review the building plan on the next submittal to insure compliance with the approved development package and rezoning conditions. Additional comments may be forthcoming. If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956 |
12/04/2013 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Approved | |
12/04/2013 | RONALD BROWN | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Completed | |
12/06/2013 | RAY MAJUTA | ELECTRICAL-COMMERCIAL | REVIEW | Approved | |
12/17/2013 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | Provide the civil plan referenced on the mechanical floor plan of sheet MP-1 to show the origin and route of the water service to the storage building. |
12/17/2013 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | All new construction is required to comply with one of the following: a. ASHRAE 90.1-2010 b. IECC Prescriptive Compliance (Sections C402, C403, C404, C405, and C406, IECC 2012) c. IECC Performance-Based Compliance (Sections C407, C402.4, C403.2, C404, C405.2, C405.4, C405.6, and C405.7) Low energy buildings such as the one proposed for this activity are exempt from the building thermal envelope requirements but are not exempt from the interior lighting requirements. The interior lighting calculations on sheet E-4A reference ASHRAE 90.1 for the lighting power allowance but appear to be using the interior power allowance value from Table C405.5.2 (2), IECC 2012. Clarify which compliance path is to be followed. If the IECC Prescriptive Compliance path is chosen, note that Section C406 will require either an efficient lighting system (Section C406.3) or on-site supply of renewable energy. Reference: Sections C101.5.2, C401.2, and C406, IECC 2012. |
12/17/2013 | ROBERT SHERRY | WATER | REVIEW | Denied | Clarify the purpose of the double check valve at the storage building; the water calculations refer to a 1-1/2" meter with a 1-1/2" reduced pressure backflow preventer serving the property. If the 1" water service line for the storage building is connected to a separate meter, a reduced pressure backflow preventer will be required after the meter. Reference: Chapter XXVII, Article V, Section 27-75 (b), the Tucson Code, http://cms3.tucsonaz.gov/sites/default/files/water/docs/backflow-ordinance.pdf |
12/23/2013 | LOREN MAKUS | ENGINEERING | REVIEW | Denied | Development package must be approved first. |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
01/14/2014 | CPIERCE1 | REJECT SHELF | Completed |