Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T13CM05187
Review Name: COMMERCIAL - TI
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 08/27/2013 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Provide construction documents that are complete and clearly indicate the extent of the proposed work (i.e. remove the "Preliminary, not for Construction" label from the drawings.). Reference: Section 107.2.1, IBC 2012. 2. Clarify the discrepancy between the specified lavatory faucets (0.50 GPM and 15 seconds per activation cycle) and the requirement to provide a 0.75 GPM aerator for each lavatory faucet (WH-4 specification). Also, how will the specified temperature mixing valve work with the thermostatically-controlled water heater? |
| 08/27/2013 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | Provide construction documents that are complete and clearly indicate the extent of the proposed work (i.e. remove the "Preliminary, not for Construction" label from the drawings.). Reference: Section 107.2.1, IBC 2012. |
| 08/27/2013 | ROBERT SHERRY | WATER | REVIEW | Approved | |
| 09/04/2013 | JASON GREEN | ENGINEERING | REVIEW | Reqs Change | Building Plan cannot be approved until a DP Package has been reviewed and approved for all onsite changes as shown on the proposed site plan Sheet AS-1. Per the proposed site plan it appears that a new sidewalk is proposed to connect the building on adjacent lots. Sidewalk needs to be reviewed for ADA compliance. Also verify that all carport as seen on the 2012 aerials have a last approved site plan and delineate them on this site plan as well. JG |
| 09/09/2013 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Denied | 1. At detail 2/A3, Rooms 123 and 124, Section 1109.2.2 of the 2012 IBC, where there are 6 or more water closets or urinals provide in a toilet room, one abulatory accessible water closet compartment shall be provided. END OF REVIEW |
| 09/10/2013 | RAY MAJUTA | ELECTRICAL-COMMERCIAL | REVIEW | Approved | |
| 09/11/2013 | MICHAEL ST. PAUL | ZONING | REVIEW | Reqs Change | Development Package required. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 09/12/2013 | CPIERCE1 | OUT TO CUSTOMER | Completed |
| 09/12/2013 | CPIERCE1 | REJECT SHELF | Completed |