Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
08/02/2013 | DAVID RIVERA | ZONING | REVIEW | Approved | |
08/02/2013 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Demonstrate energy code compliance for the proposed rooftop air conditioner. Reference: Sections C101.4.3, C101.5, and C103.2, International Energy Conservation Code 2012 2. Show that the proposed HVAC system meets the control requirements of Sections C403.2 and C403.3. Reference: Section C303.1, International Energy Conservation Code 2012. 3. Provide calculations demonstrating adequate ventilation. Reference: Section 403.2, IMC 2012. 4. Provide the installed weight of the proposed Type I hood and provide structural calculations and details to show that the Type I hood is supported from the building structure in accordance with Section 507.6, IMC 2006. Reference: Section 302.1, IMC 2012. 5. Unless the proposed Type I hood has been factory-built and tested in accordance with UL 710, the minimum air flow rates shall conform to the requirements of Section 507.13, IMC 2012 for a medium-duty appliance. Reference: Section 507.1, IMC 2012. 6. Show that the operation of the proposed Type I hood complies with the requirements of Section 507.2.1.1, IMC 2012. |
08/02/2013 | RAY MAJUTA | ELECTRICAL-COMMERCIAL | REVIEW | Denied | T13CM04737 7055 E Broadway Little Ceaser's 1. Sheet E2, the feeders to RTU-1 shows 4-3/0,#6 grd, the 3# 10's are correct, remove the 3/0"s. 2. Sheet E2, the feeder shown from Panel K to the ovens is incorrect, each oven to have it's own feeder from panel since they each have a 50 amp breaker. Remove the 3/0 feeder to the wireway. 3. Sheet E1, assign a circuit # and Panel, insert load in panel. 4. Sheet E1, lighting, show how switched, and show what circuit the emergency light is connected to. Ray T Majuta Elect Plan Review DSD, Tucson 8/2/2013 |
08/02/2013 | ROBERT SHERRY | WATER | REVIEW | Denied | Provide a site drawing showing the size and route of the building water supply along with the location and size of both the water meter and the reduced pressure backflow preventer assembly. Reference: Section 107.2.1, IBC 2012. |
08/02/2013 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Approved | |
08/02/2013 | LOREN MAKUS | ENGINEERING | REVIEW | Approved | |
08/02/2013 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Provide a cleanout downstream of the grease interceptor. Reference: Section 303.2, IPC 2012. 2. Show how accommodation for the thermal expansion of the hot water system is being provided. Reference: section 607.3, IPC 2012. 3. Provide listing information for the proposed reduced pressure backflow preventer (Watts N-9). Reference: Section 608.1, IMC 2012. 4. Verify that separate indirect waste pipes for each compartment of the 3-compartment sink are being provided to protect against cross-contamination or fouling. Reference: Sections 801.2 and 802.1.8, IPC 2012 5. Verify that all of the vents rise vertically to at least 6" above the flood rims of the fixtures they protect prior to running horizontally. Reference: Section 905.4, IPC 2012. 6. Show how the vented flow control device for the grease interceptor can be installed below the floor level and in accordance with the manufacturer's instructions. Reference: Sections 202 and 1003.4.2, IPC 2012. |
08/02/2013 | RONALD BROWN | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | |
09/03/2013 | AROMERO4 | WWM | REVIEW | Needs Review | |
09/03/2013 | AROMERO4 | FIRE | REVIEW | Needs Review |