| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 07/11/2013 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Provide a site drawing showing the size and route of the building water supply along with the location and size of both the water meter and the reduced pressure backflow preventer assembly. Reference: Section 107.2.1, IBC 2012. 2. Provide site drawing showing the size, route, and slope of the building sewer and the location of its connection to the public sewer. Reference: Section 107.2.1, IBC 2012. 3. Clarify the method used to vent the drinking fountain. Reference: Section 901.2.1, IPC 2012. 4. Verify that all of the vents rise vertically to at least 6" above the flood rims of the fixtures they protect prior to running horizontally. Reference: Section 905.4, IPC 2012. |
| 07/11/2013 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Coordinate the R-value and type of insulation shown for the components in the envelope energy calculations with the components shown on the drawings. The roof appears to have insulation located in the roof cavity (continuous insulation is located above the roof deck) and the walls are shown with R-13 cavity insulation on the drawing but the calculations are based on R-19 cavity insulation in the walls. 2. Verify that the condensate drains for the packaged cooling units do not terminate in an area that is not capable of absorbing the condensate flow without surface drainage. Reference: Section 307.2.1, IMC 2012, as amended by the City of Tucson. 3. Coordinate note 5 of the HVAC specifications on sheet M1 with the fan type and the control scheme for the restroom exhaust fans. The sequence of operation for the restroom exhaust fans shall ensure that all of the air supplied to the restrooms will be exhausted. Reference: Section 403.2.1 (4), IMC 2012. |
| 07/11/2013 | ROBERT SHERRY | WATER | REVIEW | Denied | Water demand calculations based upon Appendix E, 2012 IPC show a total of 17.5 water fixture units and a demand of approximately 19 GPM for this building. Tucson Water limits the use of a 5/8" meter to 15 GPM. Provide a letter from Tucson Water confirming that the use of a 5/8" water meter will be allowed for this project. |
| 07/12/2013 | MARTIN BROWN | FIRE | REVIEW | Approved | |
| 07/19/2013 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Denied | 1. Need approved site plan. 2. Provide structural calculations for the pole mounted lighting foundations. 3. Provide certification for the required special inspectors. END OF REVIEW |
| 07/22/2013 | MICHAEL ST. PAUL | ZONING | REVIEW | Denied | Approval of DP13-0074 required. |
| 07/29/2013 | RAY MAJUTA | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | T13CM04213 3436 N Country Club 1. Outdoor Lighting Calculations on Sheet ES1 are incorrect. The 2012 outdoor Lighting Code, Chapter 4, Table 401.1 under E-3 Option 2 allows only 250,000 lumens rather than 300,000 per acre, Total allowed is 250,000 X .78 acre = 195,000 lumens rather than 234,000. Your total is over. 2. Sheet ES1, describe the 1.5 Strip lighting, is this Full Cut Off or Unshielded ? If Unshielded needs to be included in Unshielded group. 3. Indicate on Sheet ES all outdoor lighting to be limited to 3,500 K per 402.1 of the Outdoor Lighting Code. 4. Cannot locate following circuits, A-6 and C-12,14 ? Ray T Majuta Elect Plan Review DSD, Tucson 7/29/2013 |
| 08/01/2013 | LAITH ALSHAMI | ENGINEERING | REVIEW | Approved |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 09/06/2013 | CPIERCE1 | REJECT SHELF | Completed |