Permit Number: T13CM03957
Parcel: 21114007C

Review Status: Completed

Review Details: RESUBMITTAL

Permit Number - T13CM03957
Review Name: RESUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
08/09/2013 RAY MAJUTA ELECTRICAL-COMMERCIAL REVIEW Denied T13CM03957
14199 W Mile Wide Rd
Oasis Ground Mounted Photovoltaic System
City of Tucson Phase 2

Upon first review 7/15/2013, it was requested that information conerning the equipment be submitted in the way of specification and manufactures sheets.
After review of the submitted information, it has been determined that there is no Labeling, Listing, Approval or Identified Markings on the PCS, Oasis Station as per 2011 NEC, 90.4, 110.2 and 110.3.
"Suitability of equipment may be evidenced by listing or labeling". Please review Listed, Labeled, Approved and Identified as defined in Article of the 2011 NEC.
Looking for a unit approval on the Power Skid Oasis Unit, rather than component or compliance to 90.4-- 2011 NEC.


Ray T Majuta
Elect Plan Review
PDSD, City of Tucson
8/09/2013
Ray.Majuta@tucsonaz.gov
08/12/2013 ELIZABETH EBERBACH ENGINEERING REVIEW Approved TO: Cynthia Harkness P.E.
SUBJECT: Phase II of CAVSARP WTP at Mile Wide Engineering Resubmittal Review
ADDRESS: 14199 W MILE WIDE RD
LOCATION: T14S, R11E, Section 6, NE corner of W Calle Pima and N Luckett Rd
REVIEWER: E Leibold
CASE: DP13-0120, T13CM03957
SUMMARY: PDSD Engineering Division has reviewed the Development Package for the Phase II of CAVSARP WTP and recommends approval of the Development Package, for permit issuance. No Floodplain Use Permit was submitted for the project; if a copy of the approved PCRFCD Floodplain Use Permit is not submitted to the City of Tucson prior to commencement of work, Floodplain Use Permits from City of Tucson will be needed for Elevation Certificates for both equipment pad/structures. Development Package acts as the grading permit for this project. The following conditions apply and shall be addressed during construction activities and before project completion final approvals.
CONDITIONS OF PERMITS:
The following 15 conditions apply to the Development Package DP12-0120 and permit T13CM03957:
1) Site does not need to be entirely reseeded, or gravel applied, if some areas are left undisturbed as determined by coordination with Engineer, Inspector, and Contractor. All other disturbed areas shall have sized gravel or low-height reseed mix - see also notes on plans.
2) Elevation Certificates for pre-slab and Finished Construction shall also be submitted to City of Tucson PDSD Engineering Division.
3) SPECIAL INSPECTIONS ARE REQUIRED FOR ELEVATION CERTIFICATES FOR EQUIPMENT PADS.
4) Copies of Elevation Certificates for pre-slab and Finished Construction shall also be submitted to City of Tucson PDSD Engineering Division.
5) If a copy of the approved PCRFCD Floodplain Use Permit is not submitted to the City of Tucson prior to commencement of work, Floodplain Use Permits from City of Tucson will be needed for Elevation Certificates for both equipment pad/structures.
6) Call for Pre-construction meeting. For a PDSD Engineering Inspection, call IVR (740-6970), or schedule with a Customer Service Representative at Planning & Development Services Department (PDSD), or contact PDSD Engineering at 837-4888, or schedule inspections online at: http://www.ci.tucson.az.us/dsd/Online_Services/Online_Permits/online_permits.html
7) A copy of stamped approved plans, a floodplain use permit either from City of Tucson or PCRFCD, NOI, current AzPDES general permit, geotechnical report/addenda, and other reports shall be kept at site at all times, until final grading approval.
8) Limits of Site Disturbance and/or Grading as shown on approved plans, including Temporary Construction Lay-Down Area, shall be maintained and no disturbance outside of these limits will be allowed.
9) Interim erosion and sediment controls shall be maintained per approved plans along downstream areas of disturbance limits. Interim control measures shall be placed within approved grading limits. Prior to Final Approval all temporary controls shall be removed and permanent controls shall be placed.
10) Stabilized entrances shall be maintained in area of all active access entrances. Use of water trucks or other dust controls shall be utilized, and construction entrances shall be maintained to minimize sedimentation, dust issues, and tracking.
11) Any revisions to the plans must be reviewed by PDSD Engineering Engineer and may include discussion, details, or a revised plan. Call PDSD Engineering at 791-5550 to discuss any revisions.
12) If grading construction is expected to last longer than expiration date of permit, contact PDSD to renew/extend permits. If Final Grading Inspection has not been completed before permits expires, and permits have not been renewed, additional fees and reviews may be required. Requests for permit extensions may be submitted to Planning & Development Services Department (attn: Claudia Buford), prior to permit expiration dates, for consideration of plan extension approval.
13) Permitee shall notify PDSD when grading operation is ready for final grading inspection. Final grading approval shall not be given until all work, including installation of all improvements and their permanent protective devices, and all erosion control measures have been completed in accordance with approved plans and permits, and all conditions of permit are completed.
14) After interim controls are removed, permanent erosion controls are required on all disturbed areas, in form of vegetative cover, gravel, and/or other approved controls.
15) If as-builts are not already submitted to another department, as-builts will be required to be submitted under activity number DP13-0120 to PDSD permit clerks. They will be reviewed and then if acceptable, a copy will be provided to PDSD Engineering Inspector for final grading inspections. For Development Package Permit Project Closure documentation, submit: one copy of original plans, 2 copies of as-builts, letters of substantial completion for overall project. As-built data shall include: any finished pad elevation for buildings, depth of erosion protection, and any general grades as determined by RLS to show substantial completion for project.
If you have questions, call me at 837-4934.
Elizabeth Leibold, PE, CPM, CFM
Civil Engineer
Engineering Division
Development Services Department
City of Tucson