Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T13CM03120
Review Name: COMMERCIAL - TI
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 05/30/2013 | KEN BROUILLETTE | FIRE | REVIEW | Approv-Cond | Building plans and alarm plans must be submitted to the Office of the State Fire Marshall for approval |
| 05/31/2013 | RAY MAJUTA | ELECTRICAL-COMMERCIAL | REVIEW | Denied | T13CM03120 1. Sheet E-4 shows the total new load for new panels P1,P2 and P3 = 272 amps. There are 4 other 100 amp services on this 400 amp service. What are other loads, include in total. 2. Addressing situation needs to be addressed, all new services will have to be cleared to Utility and they all show existing Suite 116 ? This issue needs to cleared with permitting counter so all addresses can be on permit issued. Ray T Majuta Elect Plan Review PDSD, Tucson 5/31/2013 Ray.Majuta@tucsonaz.gov |
| 05/31/2013 | JASON GREEN | ENGINEERING | REVIEW | Approved | ENG will stamp the building plan approved upon approval of the DP Package. JG |
| 06/03/2013 | STEVE SHIELDS | ZONING | REVIEW | Denied | PDSD TRANSMITTAL FROM: Steve Shields Lead Planner PROJECT: LA Fitness Expanson T13CM03120 Structural Plan (1st Review) TRANSMITTAL DATE: April 19, 2013 1. The structural plans have been reviewed by Zoning Review Section but cannot approve the plan until all zoning comments or concerns have been addressed. 2. Zoning can not approve the structural plans until the development package has been approved. 3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved development package. Additional comments may be forthcoming. If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956 |
| 06/04/2013 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Denied | 1. SHEET A1.1 (FLOOR PLAN); SHEET A6.1 (DOOR SCHEDULE): ARE DOORS 111 AND THE EXISTING DOOR ON THE WEST WALL FIRE RATED PER IBC TABLE 716.5? THE DOOR SCHEDULE DOES NOT SHOW FIRE RATING AT THOSE LOCATIONS. VERIFY. 2. SHEET A1.2; DETAIL 2: ADD A REFERENCE TO NOTE 4 FOR THE WALL BRACING DETAILS 2 AND 3 ON SHEET A5.1. 3. SHEET A1.3; KEYNOTES: ADD A REFERENCE TO NOTE 5 FOR THE ROOF EQUIPMENT CURB DETAIL 2 ON SHEET A1.3. 4. SHEET A4.1; RESTROOM ELEVATIONS 3 AND 4: PROVIDE GRAB BAR DIMENSIONS AND LOCATIONS ON THE DRAWINGS PER THE ICC/ANSI FIGURES 604.5.1 AND 604.5.2. 5. SHEET A4.1; RESTROOM ELEVATIONS 3, 4, 8, AND 9: REVISE THE WATER CLOSET SEAT HEIGHTS ON THE DRAWINGS TO MATCH ICC/ANSI FIGURE 604.4. 6. SHEET A4.1; RESTROOM ELEVATIONS 3 AND 8: PROVIDE THE LOCATION OF THE PAPER DISPENSER ON THE DRAWINGS PER THE ICC/ANSI FIGURE 604.7. 7. SHEET A4.1: PROVIDE DETAILS ON THE DRAWINGS FOR THE HIGH/LOW DRINKING FOUNTAIN PER THE ICC/ANSI FIGURE 602.5. 8. GENERAL: PROVIDE THE 'DATE SIGNED' ON THE STAMP OF THE ARCHITECT OF RECORD ON ALL SHEETS. 9. GENERAL: PROVIDE WRITTEN RESPONSES TO ALL REVIEW COMMENTS. NO SUBSEQUENT REVIEWS WILL BE PERFORMED WITHOUT THE RESPONSES. |
| 06/05/2013 | RICK MYERS | PLUMBING-COMMERCIAL | REVIEW | Approved | |
| 06/06/2013 | RMYERS1 | WATER | REVIEW | Approved | |
| 06/07/2013 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Coordinate the supply air flow rates shown on sheet M1.1 for AC-2, AC-4, and AC-6 with the scheduled supply air flow rates. 2. Correct the ventilation calculations for AC-3, AC-4, AC-5, and AC-6; the total outside air requirement needs to include the CFM per square foot component. Reference: Section 403.3, IMC 2012. 3. Coordinate detail 1/M7.1 with the keynotes 7 and 8 on sheet M1.1. 4. Coordinate detail 2/M7.1 with the HVAC design; the detail shows a plenum return but the HVAC design shows a ducted return system. 5. Show that each rooftop unit has a thermostatic control that provides for off-hour and set-back control, automatic shutdown, automatic start-up control and, if the control does not require manual changeover from the heating and cooling modes, restricts set point overlap. Reference: Section C403.2.4, IECC 2012. 6. Show how the HVAC controls are capable of reducing the outside air to the minimum flow rates required by Chapter 4, IMC 2012. Reference: Section C403.2.5, IECC 2012. 7. Provide means for relieving the excess air from the building during economizer operation. Reference: Section C403.3.1.1.4, IECC 2012. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 07/01/2013 | CPIERCE1 | OUT TO CUSTOMER | Completed |
| 07/01/2013 | CPIERCE1 | REJECT SHELF | Completed |