Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: WALK THRU - COMM
Permit Number - T13CM02494
Review Name: WALK THRU - COMM
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
05/07/2013 | LEERAY HANLY | BUILDING-COMMERCIAL | REVIEW | Reqs Change | provide informtion showing 700 pound loads for A/C units will be acceptable on the roof. |
05/07/2013 | KEN BROUILLETTE | FIRE | REVIEW | Approved | |
05/07/2013 | LEERAY HANLY | MECHANICAL-COMMERCIAL | REVIEW | Approved | |
05/07/2013 | RAY MAJUTA | ELECTRICAL-COMMERCIAL | REVIEW | Denied | T13CM02494 1 E Toole AV 1. The Panel shows a 120/208v ( should also be rated for 120/240v) system with Phase C as high leg. NEC 2011,408.3, the higher voltage leg shall be Phase B. Since this panel is being upgraded, has to be brought to current code. 2. The #12 conductors being tapped from the 300MCM AL conform with the 10' tap rule of 2011 NEC 240..21.B. with 25a divided by 200a fuse at Main disconnect being over the 10% required, however the # 12 conductors must end being protected by an overcurrent device per it's ampacity. 3. Describe the method to be used at junction boxes on the roof used to splice the 300MCM AL, #6 CU and the #12 CU conductors. 4. 2011 NEC requires ampacity adjustments for raceways exposed to Sunlight on roofs per 310.15.B.3.C. Show how installation complies. Distance off roof on conduit to be factor. Ray Majuta Elect Plan Review PDSD, C of Tucson 5/7/2013 |
05/07/2013 | LEERAY HANLY | PLUMBING-COMMERCIAL | REVIEW | Passed |