Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T13CM02208
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
04/15/2013 | MICHAEL ST. PAUL | ZONING | REVIEW | Approved | |
04/15/2013 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Clarify keynote A; where does it apply? 2. Provide calculations demonstrating adequate ventilation using the current code, the actual occupancy (retail, not veterinary office, and with the correct number of A/C units. Reference: Section 403.2, IMC 2012. 3. Provide information on the sequence of operation for the restroom exhaust fans to show that all of the air supplied to the restrooms will be exhausted with no more than 10% exhausted air being recirculated. Reference: Section 403.2.1 (4), IMC 2012. |
04/15/2013 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Show how the temperature of the hot water supply to the public lavatories is controlled. Reference: Sections 416.5 and 607.1.2, IPC 2012 and Section C404.3, IECC 2012. 2. Provide an approved anti-siphon device (e.g. vacuum relief valve) for storage-type water heaters located above any fixture outlets. Reference: Section 504.1, IPC 2012. 3. The temperature and pressure relief piping shall not terminate "to the back of lav drain". Reference: Section 504.6 (2), IPC 2012. |
04/15/2013 | ROBERT SHERRY | WATER | REVIEW | Approved | |
04/15/2013 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Denied | 1. SHEET A-1; DETAIL C: PROVIDE THE BRACING SIZE AND CONNECTION TO THE EXISTING ROOF FRAMING. 2. SHEET A-1; DETAIL A: IS THE 5/8" GYPSUM BOARD ON EACH SIDE OF THE WALL STUDS? VERIFY. 3. STRUCTURAL CALCULATIONS; SHEET A1 (SOIL): A REFERENCE IS MADE TO THE IBC TABLE 1804.2 FOR PRESUMPTIVE SOIL BEARING. REVISE THE REFERENCE TO THE 2012 IBC. 4. GENERAL: PROVIDE WRITTEN RESPONSES TO ALL REVIEW COMMENTS. |
04/15/2013 | LAITH ALSHAMI | ENGINEERING | REVIEW | Approved | |
04/15/2013 | KEN BROUILLETTE | FIRE | REVIEW | Approved | |
04/15/2013 | ERIC NEWCOMB | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | |
04/16/2013 | RAY MAJUTA | ELECTRICAL-COMMERCIAL | REVIEW | Denied | T13CM02208 1. The 2012 IECC report is required to be sealed and signed. 2. The Mechanical Plans Examiner is requiring for the ex-fans in restrooms to come on when supplied air on, switching will leave fan off if switch off. 3. The IECC Lighting Compliance report indicates 3 lamps to be used in F type fixtures, the plan shows 2 lamps. 4. Circuit 13 used in plan marked spare in panel. 5. Fault current values given are for service location, what is the fault current value at panel A and B ? 6. Need two suite numbers on permit application, due to two meters requiring clearance to TEP. Ray T Majuta Elect Plan Review DSD, Tucson 4/16/2013 Ray.Majuta@tucsonaz.gov |
04/23/2013 | SPOWELL1 | WWM | REVIEW | Needs Review |