Permit Number: T13CM01789
Parcel: 13816001G

Review Status: Completed

Review Details: COMMERCIAL - NEW

Permit Number - T13CM01789
Review Name: COMMERCIAL - NEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
03/29/2013 DAVID RIVERA ZONING REVIEW Denied DSD TRANSMITTAL

FROM: David Rivera
Principal Planner

PROJECT: T13CM01787 and T13CM01789
Circle K Store - 530 E. Valencia Road
Building Plans for the Store and Fuel Canopy

TRANSMITTAL DATE: March 29, 2013

COMMENTS: Please resubmit revised drawings along with redlines and a response letter, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed.

1. It is acknowledged that the Development Package/rezoning case is still under review and that the development package has not been approved as of this building plan review.

2. Based on the initial information on the development package sheets the information for the GFA of the store building and fuel canopy noted on the cover sheet of the building plans do not match. Also the vehicle parking information on the building plan cover sheet is incorrect. It is suggested that coordination with the professional working on the development package drawings is made to ensure that the zoning data is consistent between the building plans and development package plans sheets and Zoning data.

3. Generally as part of the rezoning process conditions of rezoning are made as part of the site development. The rezoning case is still under process and therefore there are no conditions of rezoning that can be reviewed for purposes reviewing any conditions that may apply to the size of building, colors etc. Additional review will be done of the D.P. by the Zoning reviewer to ensure that the D.P. complies with any conditions of rezoning. If any conditions of rezoning affect the design, size, and location, etc of the Store or Fuel Canopy, ensure that the conditions are incorporated into the building plans.

4. Zoning will review the building plans on the next submittal to ensure compliance with approved development package and rezoning conditions.


If you have any questions about this transmittal, please call David Rivera, (520) 791-5608.

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised building plans and Zoning Data based on the approved D.P.
04/01/2013 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Denied 1. SHEET CA-2; DESIGN LOADS AND FOUNDATION NOTES: NOTES INDICATE THE BUILDING CODE AS THE 2006 IBC. REVISE THE NOTE AND ENSURE THE CANOPY DESIGN MEETS ALL REQUIREMENTS OF THE 2012 IBC. A CITY OF TUCSON AMENDMENT HAS ADDED SECTION 1609.5.1.1, WHICH ADDRESSES FURTHER DESIGN REQUIREMENTS FOR 'UPLIFT RESISTANCE TO MINIMIZE MICROBURST EFFECTS'. VERIFY THIS AMENDMENT HAS BEEN ADDRESSED.
2. STRUCTURAL CALCULATIONS; PAGE 1: THE CODE INDICATED IS THE 2006 IBC. REFER TO THE NOTE 1 COMMENT.
3. SHEET CA-3; DESIGN LOADS: REFER TO THE NOTE 1 COMMENT.
4. GENERAL: PROVIDE WRITTEN RESPONSES TO ALL REVIEW COMMENTS. NO SUBSEQUENT REVIEWS WILL BE PERFORMED UNTIL RESPONSES ARE RECEIVED.
04/03/2013 MARTIN BROWN FIRE REVIEW Denied Unable to approve until Development Plan has been approved by the fire department. We will be looking for proposed and existing fire hydrant location, with dimensions to property lines, in order to determine requirements for fire sprinklers.
04/11/2013 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Approved
04/11/2013 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Passed
04/15/2013 RAY MAJUTA ELECTRICAL-COMMERCIAL REVIEW Denied See comments for T13CM01787, Ray T Majuta, 4/17/2013
04/17/2013 LOREN MAKUS ENGINEERING REVIEW Approved

Final Status

Task End Date Reviewer's Name Type of Review Description
04/18/2013 FERNE RODRIGUEZ OUT TO CUSTOMER Completed