Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - NEW
Permit Number - T13CM00062
Review Name: COMMERCIAL - NEW
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 01/07/2013 | DAVID RIVERA | ZONING | REVIEW | Denied | DSD TRANSMITTAL FROM: David Rivera Principal Planner PROJECT: T13CM00062 (ref. DP12-0202 DP Site Plan) 3151 S Pantano Road Building Plans for Dollar General TRANSMITTAL DATE: January 7, 2013 COMMENTS: Please resubmit revised drawings along with redlines and a response letter, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed. 1. Zoning has reviewed the plans to verify compliance with the Development Package Site plan as it relates to the Zoning review purview. While the building footprint and heights are in substantial compliance with the un-approved version of the DP Site Plan zoning cannot approve the plans at this time. Zoning will review the building plans on the next submittal and compare them to the DP site plan to ensure compliance with the approved DP and approve the plans if possible. Ensure that any changes to the DP Site Plan or Building Plans are made accordingly to both plans sets to match. |
| 01/08/2013 | PAUL MACHADO | ENGINEERING | REVIEW | Approved | |
| 01/14/2013 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Denied | 1. SHEET T2-D; GOVERNING CODES: SINCE THIS PROJECT WAS SUBMITTED AFTER JANUARY 1, 2013, IT MUST BE DESIGNED UNDER THE 2012 EDITION OF THE IBC, IPC, IMC, IFC, IEC, AND THE INTERNATIONAL FUEL GAS CODE. THE NEC USED IS THE 2011 EDITION, AND THE ICC/ANSI IS THE 2009 EDITION. REVISE ON THE PLANS, AND REVIEW ALL DESIGNS TO ENSURE COMPLIANCE TO THE NEW CODES. 2. SHEET A1-D; KEYED NOTES: PROVIDE THE METAL WALL STUD SPACING IN NOTES 6A AND 6B. 3. SHEET A1-D; KEYED NOTES: NOTES 23 AND 24 WERE NOT LOCATED ON THE PLAN. VERIFY. 4. SHEET A2-D; KEYED NOTES: NOTES 3, 5, AND 22 WERE NOT LOCATED ON THE ELEVATIONS. VERIFY. 5. SHEET A2-D; ELEVATION 3: TWO SECTION CUTS (3 AND 4) REFERENCE SHEET A3.C. REVISE THE SHEET NUMBER. 6. SHEET A2-D; ELEVATION 4: THE SECTION CUT (3/A3.D) IS NOT CORRECT. REVISE. 7. SHEET S-1; DETAIL 3: SHOULD THE SAWED JOINT NOTE (IN BOX) BE INCLUDED ON THIS DETAIL? VERIFY. 8. SHEET S-2; GENERAL STRUCTURAL NOTES: NOTE 3 INDICATES AN ALLOWABLE SOIL BEARING PRESSURE OF 2500 PSF FOR THE PROTOTYPE FOUNDATION DESIGN, BUT LISTS NO VALUE PER THE GEOTECHNICAL REPORT (NOTE 4). LIST THE ALLOWABLE SOIL BEARING PRESSURE ON THE DRAWINGS RECOMMENDED BY THE GEOTECHNICAL REPORT. 9. MID-WEST DRAWINGS (SHEET E1); STRUCTURAL CALCULATIONS (PAGE 2): THESE SOURCES BOTH REFERENCE THE 2006 IBC. REVISE TO THE 2012. 10. GENERAL: PROVIDE WRITTEN RESPONSES TO ALL REVIEW COMMENTS. |
| 01/17/2013 | RAY MAJUTA | ELECTRICAL-COMMERCIAL | REVIEW | Approved | |
| 01/18/2013 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. The 2012 International Plumbing Code has been adopted by the City of Tucson. The use of the 2012 Uniform Plumbing Code is allowed provided an appeal to the building official is filed. There is no charge for this appeal. This review has been performed using the 2012 International Plumbing Code. 2. Revise the water distribution system design criteria to provide a flow pressure of 15 PSI or the flow pressure prescribed by the fixture or appliance manufacturer, which ever is greater. Reference: Section604.3, IPC 2012, as amended by the City of Tucson. 3. Provide tempered water for the lavatories using approved devices conforming to ASSE 1070. Per the manufacturer of the temperature mixing valve shown in detail 2/P2, "When used in an ASSE 1017 application at the hot water source, the Watts Thermostatic Mixing Valve Series MMV cannot be used by itself to control final temperature at fixtures where ASSE Standard 1016-96 or ASSE Standard 1070 listed devices are required." Reference: Sections 303.2 and 416.5, IPC 2012. |
| 01/18/2013 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Demonstrate energy code compliance for the building envelope using calculations based on the current code. Reference: Sections 101.5 and 101.5.1, International Energy Conservation Code 2012. 2. Provide calculations demonstrating adequate ventilation using the current code. Reference: Section 403.2, IMC 2012. 3. Revise the sequence of operation for the restroom exhaust fans so that all of the air supplied to the restrooms will be exhausted with no more than 10% exhausted air being recirculated (i.e. the exhaust fan shall run whenever the HVAC system serving the restrooms is on). Reference: Section 403.2.1 (4), IMC 2012. |
| 01/18/2013 | ROBERT SHERRY | WATER | REVIEW | Approved | |
| 01/22/2013 | KEN BROUILLETTE | FIRE | REVIEW | Reqs Change | Will wait for plans to be changed to 2012 IFC for review. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 01/29/2013 | CPIERCE1 | REJECT SHELF | Completed |