Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Plan Review Detail
Review Status: Completed
Review Details: PIA - RESUBMITTAL
Plan Number - T12PI00013
Review Name: PIA - RESUBMITTAL
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 01/04/2013 | JOSE ORTIZ | DOT TRAFFIC | REVIEW | Approv-Cond | ACTIVITY NUMBER: T12PI00013 PROJECT NAME: Senior Care Facility Tanque Verde & Catalina PROJECT ADDRESS: PROJECT REVIEWER: Matthew Geweke, Traffic Eng Tech Conditional Acceptance: Traffic Engineering recommends conditional approval of the PIA Plan; therefore a revised PIA Plan is not necessarily required for re-submittal but the following items must be revised or added to the plan. Just an email response with an exchange of PDF's is acceptable in lieu of a re-submittal if needed. 1. See redlines on the submitted drawings and address the additional redline comments on Sht: 3 (creating a 3' wide mini-gore area in the reverse curve between left turn bays. Place one WS12 stripe with 6 type 'H' RPM's centered on stripe to create a tactile alert to motorists. Best field fit possible. I will be glad to be present in the field on the day of striping to assist lay-out with the striping crew and answers concerns. ) 2 See Traffic Eng note attached to the plans, Sht. #3. If you have any questions, I can be reached at 791-4259 x76665 or email Matthew.Geweke@tucsonaz.gov |
| 01/07/2013 | RICHARD LEIGH | DOT ENGINEERING | REVIEW | Approv-Cond | January 7, 2013 SUBJECT: Tanque Verde Rd and Catalina Highway - I-2012-012, T12PI00013 PROJECT REVIEWER: Richard Leigh, DOT, Permits and Codes Section Permits and Codes Section has reviewed the PIA Plan and recomends a conditional approval of the PIA Plan. The following comments need to be addressed to submitting the mylars for final review and approval. 1. Clearly reference the the pavement sections to be used for the driveway and in Tanque Verde Rd. in the plan view. |
| 01/07/2013 | GARY WITTWER | DOT LANDSCAPE | REVIEW | Approved | |
| 01/08/2013 | LANCE PETERSON | DOT STREET MAINTENANCE | REVIEW | Approved | |
| 02/06/2013 | BLANCA ESPINO | PIA COORDINATOR | CUSTOMER CALLED; PLANS @ AMBASSADOR | Completed | |
| 02/06/2013 | BLANCA ESPINO | PIA COORDINATOR | OUT TO CUSTOMER | Completed | |
| 12/14/2012 | BESPINO1 | UTILITY CLEARANCES | QUEST COMMUNICATION | Completed | |
| 12/14/2012 | BESPINO1 | UTILITY CLEARANCES | TUCSON ELECTRIC POWER CO | Completed | |
| 12/14/2012 | BESPINO1 | UTILITY CLEARANCES | COX COMMUNICATION | Completed | |
| 12/14/2012 | BESPINO1 | UTILITY CLEARANCES | SOUTHWEST GAS CORP | Completed | |
| 12/14/2012 | BESPINO1 | UTILITY CLEARANCES | EL PASO NATURAL GAS | Completed | |
| 12/14/2012 | BESPINO1 | UTILITY CLEARANCES | KINDER MORGAN ENERGY | Completed | |
| 12/14/2012 | BESPINO1 | UTILITY CLEARANCES | COT STREETS DIVISION | Completed | |
| 12/14/2012 | BESPINO1 | UTILITY CLEARANCES | COT WATER NEW DEVELOPMENT | Completed | |
| 12/21/2012 | BESPINO1 | UTILITY CLEARANCES | PC WASTEWATER MGMT | Completed |