Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T12CM06347
Review Name: COMMERCIAL - TI
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 10/12/2012 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Denied | GENERAL 1. These drawings are insufficient in constructrion drawing detail to obtain a construction permit: a. Need mechanical and plumbing plans signed and sealed by an Arizona registrant. b. Need explanation of existing elements as to proposed modifications. Normally a demolition plan is provided. c. Call out any new fenestration openings and provide structural lintel details and calculations. d. Provide a complete site plan showing all improvements including parking spaces and sidewalks, new and existing. e. Provide typical interior partition section details f. Provide tasting counter elevations and details showing accessibility compliance g. Show toilet elevations with accessibility and finsh compliance. Finsh toilet plans with accessible clearances and dimensions. h. Clean up general notes on the cover sheet and delete all those not having any bearing on this project. i. Provide structural details and calculation for the wall mounted water heater and any new roof mounted HVAC units. j. Provide room finish and door schedules. Include hardware schedule. FLOOR PLAN SHEET 2. At both details A/1: Both toilets do not have the water closet clearance required as per ICC A117.1, Section 604.3. 3. Show the point of use water dispenser. 4. Provide panic bars on all exit doors as required by the 2006 IBC, Section 1008.1.9. 5. Show a service sink. COVER SHEET CODE DATA 6. Toilet fixtures and exiting must be calculated for the worse condition of 160 occupants. Recalculate and make necessary adjustments. 7. Occupancy use is to be a dual use of A2 and F2. END OF REVIEW |
| 10/15/2012 | KEN BROUILLETTE | FIRE | REVIEW | Denied | 1. On sheet COV-1 an occupant load of 160 is noted. Please show calculations. Also, the allowable area calculation is incorrect. 2. Provide a seating plan or indicate that no table or chairs are going to be used. 3. Indicated the exit doors, emergency egress lighting locations and exit sign locations. 4. Indicate type of egress hardware on doors. 5. Indicate the occupant load in the area that is enclosed by a fence with a sliding gate. We need to determine if the sliding gate will be allowed for exiting. 6. Indicate on cover sheet that separate permits will be required for any fire sprinkler or fire alarm work. |
| 10/16/2012 | RAY MAJUTA | ELECTRICAL-COMMERCIAL | REVIEW | Passed | |
| 10/16/2012 | STEVE SHIELDS | ZONING | REVIEW | Denied | PDSD TRANSMITTAL FROM: Steve Shields Lead Planner PROJECT: Sentinel Peak Brewing Company T12CM06347 Building Plan (1st Review) TRANSMITTAL DATE: October 16, 2012 1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until all zoning comments or concerns have been addressed. 2. Zoning can not approve the building plan until a development package has been approved. 3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved development package. Additional comments may be forthcoming. If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956 |
| 10/16/2012 | STEVE SHIELDS | ZONING | REVIEW | Denied | PDSD TRANSMITTAL FROM: Steve Shields Lead Planner PROJECT: Sentinel Peak Brewing Company T12CM06347 Building Plan (1st Review) TRANSMITTAL DATE: October 16, 2012 1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until all zoning comments or concerns have been addressed. 2. Zoning can not approve the building plan until a development package has been approved. 3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved development package. Additional comments may be forthcoming. If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956 |
| 10/17/2012 | JASON GREEN | ENGINEERING | REVIEW | Denied | Building Plan will be stamped approved upon approval of DP12-0177. |
| 10/22/2012 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Provide a site drawing showing the size, route, point of connection to the public sewer system, and the slope of the building sewer (keynote 1, Plumb-1). Reference: Section 103.2.3, UPC 2006. 2. Provide plumbing plans for the new work, including a plumbing floor plan, water isometrics, and waste and vent isometrics. Reference: Section 103.2.3, UPC 2006. 3. Provide the minimum plumbing facilities (i.e. service sink and drinking fountain) required by Table 2902.1 and Section 2902.2, IBC 2006, for factory occupancy. See also, Section 1109.5.1, IBC 2006. 4. Indicate the materials to be used in the proposed plumbing systems for this activity. Reference: Sections 103.2.3, 301.1, 604.0, 701.0, 903.0, 1102.0, and 1209.5, UPC 2006. 5. Provide fixture descriptions for all plumbing fixtures. All plumbing fixtures and fittings shall be listed or labeled by a nationally-recognized, accredited conformity assessment company (e.g. UL, ETL, UPC, etc) Reference: Sections 301.1.1 and 401.1, UPC 2006. 6. Provide a design for the mounting shelf for the water heater along with structural calculations to show that the water heater is safely supported. Reference: Sections 310.0 and 314.5, UPC 2006. 7. Show how the temperature of the hot water supply to the public lavatories is controlled. Reference: Section 413.1, UPC 2006 and Section 504.3, IECC 2006. 8. Provide a detail of the water heater installation, including the excess pressure relief, expansion tank, vacuum relief, and valves. Reference: Sections 103.2.3, 605.5, 608.3, and 608.7 UPC 2006. 9. Provide specifications for the proposed water heater. Reference: Section 501.0, UPC 2006. 10. If the specified water heater is not supplied with integral heat traps, provide heat traps on the supply and discharge piping. Reference: Section 504.4, IECC 2006. 11. If the specified water heater is not supplied with integral heat traps, provide 0.5" of insulation with a maximum conductivity of 0.27 BTU per inch/h F on the first 8 feet of supply and discharge piping. Reference: Section 504.5, IECC 2006. 12. Provide a shut off valve for the water service at the building entrance. Reference: Section 605.2, UPC 2006. 13. Provide for sterilization of the domestic water piping per Section 609.9, UPC 2006. 14. Provide water pressure and water pipe sizing calculations. Reference: Section 610.1, UPC 2006. |
| 10/22/2012 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | Provide a mechanical design for the proposed building improvements and the proposed building addition (i.e. the temperature-controlled fermentation/storage room) that clearly shows that the installation will comply with the requirements of Sections 302, 307, 309, 401, and 601, IMC 2006 and Chapter 5, IECC 2006. Reference: Section 106.3.1, IMC 2006. |
| 10/22/2012 | ROBERT SHERRY | WATER | REVIEW | Denied | 1. Show the location and size of the water service meter. Reference: Section 103.2.3, UPC 2006. 2. Show the location of the reduced pressure backflow assembly on the drawings and indicate the size of the assembly. Reference: Chapter XXVII, Article V, Section 27-72, the Tucson Code, http://cms3.tucsonaz.gov/sites/default/files/water/docs/backflow-ordinance.pdf |
| 10/25/2012 | GERRY KOZIOL | WWM | REVIEW | Denied | 1: BUILDING #2 - SENTINEL PEAK BREWING COMPANY - ADDED 13 FU'S 2: NEED TO SHOW THE SIZES & LOCATION OF ALL WATER METERS ON THE PROPERTY WITH SIZES, LOCATIONS AND METER NUMBERS FROM WATER SUPPLIER FOR SEWER CONNECTION FEE CALCULATION 3: NEED TO CLARIFY LOCATION/METHOD OF CONNECTION TO PUBLIC SEWER 4: MAY NEED WW/IWC PER KRISTIN GREENE - 740-6645 5: EXISTING CONNECTION TO PUBLIC SEWER PER DYE TEST DATED 08/24/74 - NO OTHER INFORMATION 6: NEED ADDRESSING FOR BUILDING #2 |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 11/19/2012 | CPIERCE1 | OUT TO CUSTOMER | Completed |
| 11/19/2012 | CPIERCE1 | REJECT SHELF | Completed |