Permit Number: T12CM05903
Parcel: 10408008C

Review Status: Completed

Review Details: COMMERCIAL - TI

Permit Number - T12CM05903
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
09/28/2012 RONALD BROWN BUILDING-COMMERCIAL REVIEW Denied 1. Please provide a site plan.
2. Details 3/A10 and 17/A3.0: Please provide bracing to structure to comply with a minimum 5psi lateral load as required by the 2006 IBC, section 1607.13.
END OF REVIEW
10/04/2012 ROBERT SHERRY WATER REVIEW Approved
10/04/2012 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied 1. Clarify the plumbing code to be used for this activity. The Code Index on sheet CS refers to the 2006 UPC but the General Plumbing Notes on sheet PME1 refer to the 2012 IPC and the State of Texas. The City of Tucson has adopted both the 2006 UPC and the 2006 IPC and either one may be used. This review has been made using the 2006 IPC.
2. Provide tempered water for the lavatories using approved devices conforming to ASSE 1070. Reference: Section 416.5, IPC 2006.
10/04/2012 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Denied 1. The Code Index on sheet CS refers to the 2006 IMC but the General Mechanical Notes on sheet PME1 refer to the 2012 IMC and the State of Texas. The 2006 International Mechanical Code with City of Tucson Local Amendments is the relevant code for this project.
2. Mechanical keynotes 4 and 5 on sheet M1 do not appear on the mechanical floor plan. If they are part of this activity, show their location. If, however, they do not pertain to this activity remove them from the drawing.
10/09/2012 RAY MAJUTA ELECTRICAL-COMMERCIAL REVIEW Denied 4631 E Oracle RD #175
T12CM05903
TI, Visionworks

1. As per City of Tucson Commercial Submittal Requirements:
provide following

Panel location and main service location
Assign panel circuit numbers to all lighting power and
electrical equipment.
Provide a panel schedule showing loads in watts for all
circuits, and total phase loads in watts and balance phases within 15%
Total connected loads for panel and service.

Ray T Majuta
PDSD, City of Tucson
Electrical Plan Review
10/10/2012
Ray.Majuta@tucsonaz.gov
10/17/2012 GERRY KOZIOL WWM REVIEW Approved

Final Status

Task End Date Reviewer's Name Type of Review Description
11/26/2012 SHANAE POWELL OUT TO CUSTOMER Completed
11/26/2012 SHANAE POWELL REJECT SHELF Completed