Permit Number: T12CM04064
Parcel: 12106401B

Review Status: Completed

Review Details: COMMERCIAL - TI

Permit Number - T12CM04064
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
07/19/2012 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Denied 1. SHEET D1.1; DEMOLITION KEYNOTES: KEYNOTE 6 WAS NOT FOUND ON THE PLANS. VERIFY.
2. SHEET A2.1; KEYNOTES: THE TITLE FOR THE UPPER KEYNOTES (HEXAGONAL SYMBOL) INDICATES ROOF PLAN KEYNOTES. REVISE TO REFLECTED CEILING KEYNOTES.
3. SHEET A3.1; SECTION KEYNOTES: KEYNOTES 2, 13, 19, 20, AND 21 WERE NOT FOUND ON THE SECTIONS. VERIFY.
4. SHEET S2.1 (FRAMING PLAN); SHEET S4.1 (DETAIL 410): DOES THE EXISTING STEEL BEAM INDICATED IN DETAIL 410 EXTEND THROUGH THE OPEN AREA SHOWN ON THE PLAN? VERIFY.
5. ARCHITECTURAL GENERAL: PROVIDE A PLAN OF THE EXISTING MEZZANINE AND THE MEZZANINE ADDITION. INCLUDE SECTIONS/DETAILS AS REQUIRED.
6. ARCHITECTURAL GENERAL: PROVIDE A DETAIL FOR THE SUPPORT OF THE WATER HEATER ABOVE THE SERVICE SINK. INCLUDE MEMBER SIZES, SPACING, AND ALL PERTINENT CONNECTIONS.
7. GENERAL: PROVIDE WRITTEN RESPONSES TO ALL REVIEW COMMENTS.
07/26/2012 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Denied Provide energy code compliance calculations for the additions to the building envelope; use the climate zone for Pima County < 4,000 feet. Provide sufficient detail on the drawings to evaluate the energy compliance of the additions to the building envelope. The information shall, as a minimum, include U-factors of the envelope systems and fenestration components, along with the R-values of the insulation and the SHGC for the fenestration. Reference: Sections 101.4, 101.4.3, and 104.2, International Energy Conservation Code 2006.
07/26/2012 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied 1. Clarify keynote #6 on sheet P1.0: is a floor drain really outside of the building?
2. Clarify keynote #9 on sheet P1.0: the specified water heater is not normally installed with a temperature & pressure relief. If a temperature & pressure relief is desired, show how it is to be installed on the installation detail. Reference: Section 103.2.3, UPC 2006.
3. Install the specified water heater in accordance with its listing information. This water heater must not be installed above the level of any of the hot water outlets it serves. Correct detail 201 to correspond to the piping configuration of the specified water heater. Reference: Section 310.4, UPC 2006.
07/26/2012 ROBERT SHERRY WATER REVIEW Approved
07/27/2012 RAY MAJUTA ELECTRICAL-COMMERCIAL REVIEW Denied T12CM04064

1. The Insta Hot water heater shown in Sheet P-1 is 7.5KW
240 v, the panel schedule shows one 20 CB, also the load is incorrect.

Ray T Majuta
Elect Pln Review
PDSD, C of Tuc
7/27/2012
Ray.Majuta@tucson az.gov
07/30/2012 TERRY STEVENS ZONING REVIEW Denied Zoning cannot approve the buliding plan until the development package has been approved.
08/02/2012 JASON GREEN ENGINEERING REVIEW Denied Building plan will be stamped approved by the ENG Section after approval of the DP Package DP12-0100.
08/07/2012 GBONILL1 WWM REVIEW Approved