| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 07/09/2012 | MARTIN BROWN | FIRE | REVIEW | Denied | A) Please include the following fire sprinkler design criteria to the plans. 1. Flow data (static pressure, residual pressure, GPM) Available from the Fire Department (520) 837-7029 or 837-7030. 2. The standard to be used in development of sprinkler system. (NFPA 13, NFPA 13R, or NFPA 13D) 3. The hazard classification of the building, including any special hazards. 4. The density required of the water supply. B) The riser diagram on sheet P2.2 shows a double check valve assembly. Tucson Fire would prefer a single check valve in the riser. Please update the sheet or incur the extra expense of the double check valve assembly. |
| 07/11/2012 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Denied | GENERAL 1. Please provide structural calculations for the new roof top mounted HVAC units and the fan coil units. 2. Redefine the building occupancy uses to "B" and "A3". a. Recalculate the building occupancy load with the conference room use of A3 of 1 to every 15 s.f. b. Recalculate the number of toilet fixtures required for the new occupancy load. c. Recalculate the required number of exits using the new occupancy load for both spaces; office and assembly. SHEET A1 3. As per the 2006 IBC, Table 508.3.3, a 1 hour separation is required. 4. New calculations for the conference room provide an occupant load of 60. a. Please provide two exits as required by table 1015.1. b. Please provide two toilet rooms as required by 2006 IBC, section 2902.2. 5. The office building also needs two accessibly compliant toilet rooms. The one toilet shown inside the building is not compliant with ICC A117.1, Section 604.3 and 606.3. 6. Please provide a hardware schedule. 7. Door 6 is non compliant with ICC A117.1, Section 404.2.3.1. 8. Where is the Service Sink? SHEET A3.1 9. At detail 3, please provide lateral bracing from top of partition to structure above for a minimum of 5 psi lateral loading as required by the 2006 IBC, Section 1607.13. SHEET A4.1 10. All detail title 3/16" scale references needs to be changed to 3/8" scale. 11. All toilet elevation needs to show wall finished as required by the 2006 IBC, Section 1202.2. 12. At detail F please provide vertical grab bar as required by ICC A117.1, section 604.5.1. 13. At details D, H and L please show top of lavatory counter from finished floor to be 2'-10" as required by ICC A117.1, section 606.3. SHEET S02 14. Please provide a letter to Mr. Ron Boose, the building official, for approval of a deferred submittal for the wood trusses. END OF REVIEW |
| 07/18/2012 | ROBERT SHERRY | WATER | REVIEW | Approved | |
| 07/18/2012 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | Provide energy code compliance calculations for the building envelope; use the climate zone for Pima County < 4,000 feet and show that the building conforms to the requirements of Chapter 5, IECC 2006 (commercial building, not residential). Provide sufficient detail on the drawings to evaluate the energy compliance of the building envelope. The information shall, as a minimum, include U-factors of the envelope systems and fenestration components, along with the R-values of the insulation, and the projection factors and SHGC for the fenestration. Reference: Sections 101.4 and 104.2, International Energy Conservation Code 2006. |
| 07/19/2012 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | One of the specified fixtures (Water closet P2) requires a minimum pressure greater than the 20-PSI used in the water pipe sizing calculations. Revise calculations as necessary. Reference: Section 608.1, UPC 2006. |
| 07/24/2012 | RAY MAJUTA | ELECTRICAL-COMMERCIAL | REVIEW | Approved | |
| 07/25/2012 | TERRY STEVENS | ZONING | REVIEW | Denied | Zoning cannot approve until the development package has been approved. |
| 07/26/2012 | PAUL MACHADO | ENGINEERING | REVIEW | Approved | |
| 08/01/2012 | GERRY KOZIOL | WWM | REVIEW | Denied | 1. SKYLINE PEDIATRICS, P.C. -DP12-0094 2. CONNECTING TO EXISTING 8" PUBLIC SEWER WITH 4" HCS- CONNECTING TO 1"C.W. 3. NEED APPROVED WATER PLAN SHOWING LOCATION & SIZE OF WATER METER FOR THIS NEW COMMERCIAL BUILDING FOR CALCULATION OF WASTEWATER CONNECTION FEES 4. NEED DP PLAN APPROVAL - 740-6647 PCRWRD/CHAD AMATEAU |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 08/17/2012 | FERNE RODRIGUEZ | OUT TO CUSTOMER | Completed |