Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T12CM01589
Review Name: COMMERCIAL - TI
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 04/11/2012 | MICHAEL ST. PAUL | ZONING | REVIEW | Approved | |
| 04/11/2012 | MARTIN BROWN | FIRE | REVIEW | Approved | |
| 04/17/2012 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Denied | 1. SHEET a1.0; PROJECT DATA: THE ACCESSIBILITY GUIDELINE USED BY THE CITY OF TUCSON IS THE ICC/ANSI A117.1-2003. REVISE. 2. SHEET a1.0; PROJECT DATA; GENERAL BUILDING SUMMARY: THE GENERAL BUILDING SUMMARY INDICATES TYPE OF CONSTRUCTION AS V-N, WHILE THE PROJECT DATA INDICATES IIIa. CLARIFY. 3. SHEET a1.1; FLOOR PLAN: THE CITY OF TUCSON REQUIRES ALL LETTERING (UPPER AND LOWER CASE) TO BE A MINIMUM OF 3/32" IN HEIGHT. REVISE. 4. SHEET a2.0; DEMOLITION PLAN: DARKEN THE LINES OF ITEMS TO BE DEMOLISHED. 5. SHEET a2.0; DEMOLITION PLAN: ADD A DEMOLITION KEYNOTE THAT INDICATES ALL KEYNOTES MAY NOT BE ON THIS SHEET, AND TO REFERENCE SHEET a2.1 FOR ADDITIONAL DEMOLITION PLAN. 6. SHEETS a2.0 AND a2.1; DEMOLITION KEYNOTES: KEYNOTES 7 AND 10 WERE NOT FOUND ON EITHER PLAN. ADD NOTES TO PLANS OR REMOVE KEYNOTES. 7. SHEET a2.1; DEMOLITION PLAN: ADD A DEMOLITION KEYNOTE THAT INDICATES ALL KEYNOTES MAY NOT BE ON THIS SHEET, AND TO REFERENCE SHEET a2.0 FOR ADDITIONAL DEMOLITION PLAN. 8. SHEET a2.1; DEMOLITION PLAN: A KEYNOTE 14 IS LOCATED ON GRID 9, BUT THERE IS NO KEYNOTE 14. CLARIFY. 9. SHEETS a3.0 AND a3.1; GENERAL ROOF NOTES: ROOF NOTES SHOULD BE REMOVED FROM THESE SHEETS. 10. SHEET a3.0; WALL TYPES: ALL WALL TYPES LISTED ARE NOT ON THIS PLAN. REFERENCE SHEETS a3.1 AND a3.2 FOR ADDITIONAL WALL TYPES, AND REMOVE WALL TYPES NOT USED ON THIS PROJECT. 11. SHEETS a3.0, a3.1, AND a3.2; GENERAL NOTES: WHAT IS NOTE 4 IN REFERENCE TO? CLARIFY. 12. SHEETS a3.0, a3.1, AND a3.2; GENERAL NOTES: IS NOTE 7 REQUIRED FOR THIS PROJECT? IF SO, IDENTIFY THOSE WALLS ON THESE PLANS. 13. SHEETS a3.0, a3.1, AND a3.2; GENERAL NOTES: IS THE REFERENCE 28/a9.1 IN NOTE 10 CORRECT? VERIFY. 14. SHEETS a3.0, a3.1, AND a3.2; GENERAL NOTES: IS THE REFERENCE a8.3 IN NOTE 18 CORRECT? VERIFY. 15. SHEETS a3.0, a3.1, AND a3.2; GENERAL NOTES: IS THE REFERENCE 1108.2.9.1 IN NOTE 22 CORRECT? VERIFY (USING 2006 IBC). 16. SHEETS a3.0, a3.1, AND a3.2; FLOOR PLAN KEY NOTES: IS THE REFERENCE 24/a9.1 IN NOTE 11 CORRECT? VERIFY. 17. SHEETS a3.0, a3.1, AND a3.2; FLOOR PLAN KEY NOTES: REVISE THE REFERENCE a117.1-1998 IN NOTE 25 TO 2003. 18. SHEETS a3.0, a3.1, AND a3.2; FLOOR PLAN KEY NOTES: REVISE THE REFERENCE a117.1-2006 IN NOTES 36 AND 40 TO 2003. 19. SHEETS a3.0, a3.1, AND a3.2; FLOOR PLAN KEY NOTES: IS THE REFERENCE a8.4 IN NOTE 40 CORRECT? VERIFY. 20. SHEET a3.0; FLOOR PLAN KEY NOTES: KEY NOTE 4 IS LOCATED ON THE PLAN IN THE THEATER, BUT THE KEY NOTES INDICATE n.a. CLARIFY. 21. SHEET a3.0; FLOOR PLAN KEY NOTES: ALL KEY NOTES LISTED ARE NOT ON THIS PLAN. REFERENCE SHEET a3.1 AND a3.2 FOR ADDITIONAL KEY NOTES, AND REMOVE KEY NOTES NOT USED ON THIS PROJECT. 22. SHEET a3.0; FLOOR PLAN: AT THE MEN'S RESTROOM 101 AND WOMEN'S RESTROOM 103, THERE IS AN ELEVATION 6/a8.0 INDICATED. IS THIS CORRECT? VERIFY. 23. SHEET a3.0; FLOOR PLAN: AT THE WOMEN'S RESTROOM 102, THERE IS AN ELEVATION 8/a8.0 INDICATED. IS THIS CORRECT? VERIFY. 24. SHEET a3.0; FLOOR PLAN: AT THE WOMEN'S RESTROOM 103, THERE IS AN ELEVATION 21/a8.1 INDICATED. IS THIS CORRECT? VERIFY. 25. SHEET a3.0; FLOOR PLAN: AT THE TANNING ROOM 105, THERE ARE ELEVATIONS 13/14/15/16/a8.0 INDICATED. ARE THESE CORRECT? VERIFY. 26. SHEET a3.0; FLOOR PLAN: AT THE STUDY ROOM c 110, THERE ARE ELEVATIONS 25/26/27/28/a8.0 INDICATED. ARE THESE CORRECT? VERIFY. 27. SHEET a3.0; FLOOR PLAN: AT THE CORRIDOR ADJACENT TO STUDY ROOM a, THERE ARE ELEVATIONS 41/43/a8.0 INDICATED. ARE THESE CORRECT? VERIFY. 28. SHEET a3.0; FLOOR PLAN: IN TWO LOCATIONS, THERE ARE DETAIL INDICATIONS OF 27a/a9.1 AND 27b/a9.1. THERE ARE NO DETAILS 27a AND 27b. VERIFY. 29. SHEET a3.1; FLOOR PLAN KEY NOTES: ALL KEY NOTES LISTED ARE NOT ON THIS PLAN. REFERENCE SHEET a3.0 AND a3.2 FOR ADDITIONAL KEY NOTES, AND REMOVE KEY NOTES NOT USED ON THIS PROJECT. 30. SHEET a3.1; WALL TYPES: ALL WALL TYPES LISTED ARE NOT ON THIS PLAN. REFERENCE SHEETS a3.0 AND a3.2 FOR ADDITIONAL WALL TYPES, AND REMOVE WALL TYPES NOT USED ON THIS PROJECT. 31. SHEET a3.1; FLOOR PLAN KEY NOTES: NOTE 14 INDICATES A COLUMN, FOOTING, AND CABLE. PROVIDE A DETAIL FOR THE FOOTING AND COLUMN. 32. SHEET a3.1; FLOOR PLAN: IN THE COUNTER 132 AREA, KEY NOTE 49 IS INDICATED. IS THIS CORRECT? VERIFY. 33. SHEET a3.1; FLOOR PLAN: IN THE PRIVATE OFFICE 126, THERE ARE ELEVATIONS 69/73/a8.4 INDICATED. ARE THESE CORRECT? VERIFY. 34. SHEET a3.1; FLOOR PLAN: IN THE PRIVATE OFFICE 127, THERE IS AN ELEVATION 64/a8.4 INDICATED. IS THIS CORRECT? VERIFY. 35. SHEET a3.1; FLOOR PLAN: IN THE MEN'S RESTROOM 129, THERE ARE ELEVATIONS 91/92/93/94/a8.3 INDICATED. ARE THESE CORRECT? VERIFY. 36. SHEET a3.1; FLOOR PLAN: IN THE WOMEN'S RESTROOM 130, THERE ARE ELEVATIONS 83/84/85/86/a8.3 INDICATED. ARE THESE CORRECT? VERIFY. 37. SHEET a3.2; WALL TYPES: ALL WALL TYPES LISTED ARE NOT ON THIS PLAN. REFERENCE SHEETS a3.0 AND a3.1 FOR ADDITIONAL WALL TYPES, AND REMOVE WALL TYPES NOT USED ON THIS PROJECT. 38. SHEET a3.2; FLOOR PLAN KEY NOTES: ALL KEY NOTES LISTED ARE NOT ON THIS PLAN. REFERENCE SHEETS a3.0 AND a3.1 FOR ADDITIONAL KEY NOTES, AND REMOVE KEY NOTES NOT USED ON THIS PROJECT. 39. SHEET a3.3; FLOOR PLAN: ALL FINISHES LISTED IN THE FLOORING LEGEND ARE NOT ON THIS PLAN. REFERENCE SHEET a3.4 FOR ADDITIONAL FLOORING FINISHES, AND REMOVE FINISHES NOT USED ON THIS PROJECT. 40. SHEET a3.4; FLOOR PLAN: ALL FINISHES LISTED IN THE FLOORING LEGEND ARE NOT ON THIS PLAN. REFERENCE SHEET a3.3 FOR ADDITIONAL FLOORING FINISHES, AND REMOVE FINISHES NOT USED ON THIS PROJECT. 41. SHEET a4.0; REFLECTED CEILING PLAN: IN THE GYM 100, PROVIDE THE CEILING ELEVATION. 42. SHEET a4.0; LIGHTING SCHEDULE: ALL LIGHTING TYPES LISTED IN THE SCHEDULE ARE NOT ON THIS PLAN. REFERENCE SHEET a4.1 FOR ADDITIONAL LIGHTING TYPES, AND REMOVE TYPES NOT USED ON THIS PROJECT. 43. SHEET a4.1; LIGHTING SCHEDULE: ALL LIGHTING TYPES LISTED IN THE SCHEDULE ARE NOT ON THIS PLAN. REFERENCE SHEET a4.0 FOR ADDITIONAL LIGHTING TYPES, AND REMOVE TYPES NOT USED ON THIS PROJECT. 44. SHEET a8.1; ELEVATION 23: THE TITLE SHOULD INDICATE SOUTH. REVISE. 45. SHEET a8.1; ELEVATION 24: THE TITLE SHOULD INDICATE WEST. REVISE. 46. SHEET a8.5; ELEVATION 76: THE TITLE SHOULD INDICATE SOUTH. REVISE. 47. SHEET a8.5; ELEVATION 77: THE TITLE SHOULD INDICATE WEST. REVISE. 48. SHEET a9.0; DETAIL 15: PROVIDE THE LENGTH OF THE VERTICAL GRAB BAR. 49. SHEET a9.0; DETAIL 15: PROVIDE THE LOCATION OF THE PAPER DISPENSER PER ICC/ANSI A117.1-2003, FIGURE 604.7. 50. SHEET a9.1: THE CITY OF TUCSON REQUIRES ALL LETTERING (UPPER AND LOWER CASE) TO BE A MINIMUM OF 3/32" IN HEIGHT. REVISE. 51. SHEET S3.1 (FRAMING PLAN); FRAMING PLAN NOTES: AT GRIDS 13 AND C, THERE IS A NOTE THAT INDICATES ROOF DECK TO THE SOUTH OF GRID 13. FRAMING PLAN NOTE 1 INDICATES CONCRETE ON PLYWOOD-TYPICAL AT FLOORS. IS THIS FLOOR OR ROOF? VERIFY. 52. GENERAL: PROVIDE WRITTEN RESPONSES TO ALL REVIEW COMMENTS. |
| 04/19/2012 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Provide structural calculations to verify that the existing roof is capable of supporting the additional dead load due to the installation of the ten new roof top units. Reference: Section 302.1, IMC 2006. 2. Show how the fan coils are being connected to the building structure and provide calculations to show that the building structure is not being adversely affected. Reference: Section 302.1, IMC 2006. 3. Show the size, routing, and termination of the condensate drains for the new fan coil units. Reference: Section 307.2, IMC 2006 as amended by the City of Tucson. 4. Clarify how the outside air intakes are to be protected from the weather and also comply with the requirements of Table 401.5, IMC 2006. 5. Clarify the type of diffusers or registers that are being used; many of the new diffusers and registers are not labeled with a symbol from the schedule on sheet m9.1. Reference: Section 106.3.1, IMC 2006. 6. Show how fan coils FC-4, FC-6, and FC-7 are being supplied with outside air and provide balancing data for the outside air. Reference: Sections 106.3.1 and 403.1, IMC 2006. 7. Provide balancing data (e.g. outside air) for fan coils FC1, FC-2, FC-8, FC-9, and FC-10. Reference: Sections 106.3.1 and 403.1, IMC 2006. |
| 04/19/2012 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Clarify the plumbing code to be used for this activity. The Plumbing Specifications on sheet m9.2 refer to the 2006 UPC but the Project Data on sheet A1.0 refers to both the 2006 UPC and the 2006 IPC. This review has been made using the 2006 UPC. 2. The drain pipe downstream of the grease interceptor (P8) is 3" but P8 is specified as having both a 4" inlet and a 4" outlet. Any fitting or connection in a drainage system that results in a reduction of the pipe area is prohibited. Reference: Section 316.4.1, UPC 2006. 3. Provide upper terminal cleanouts on horizontal drainage pipe over 5 feet in length (e.g. P7 in the south end of room 132). Reference: Section 707.4, UPC 2006. 4. Provide an accessible cleanout in the vertical portion of the foot vent for the island sink. Reference: Section 909.0, UPC 2006. 5. Provide a design for the sleeves for the underground gas pipes; show the locations for the vents and show how they will be capable of preventing the entrance of water or insects. Reference: Section 1211.1.6, UPC 2006. |
| 04/19/2012 | ROBERT SHERRY | WATER | REVIEW | Approved | |
| 05/02/2012 | DAN SANTA CRUZ | ELECTRICAL-COMMERCIAL | REVIEW | Approv-Cond | need legible seal from EE |
| 05/10/2012 | GERRY KOZIOL | WWM | REVIEW | Denied | 1. SEASONS 2. NEED WW/IWC F.T. "RUSTY" RICCABONI, JR REVIEW OF 220LB 50 GPM GREASE INTERCEPTOR - 3035 W EL CAMINO DEL CERRO - 520-724-6211 3. 6FU CREDIT FOR REMOVAL OF 1 TOILET & 1LAV PER DEMO PLAN A2.1 AND FIXTURES SCHEDULE M9.2 |