Permit Number: T12CM00722
Parcel: 12504079A

Review Status: Completed

Review Details: COMMERCIAL - TI

Permit Number - T12CM00722
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
02/29/2012 KBROUIL1 FIRE REVIEW Approved
03/09/2012 RONALD BROWN BUILDING-COMMERCIAL REVIEW Denied GENERAL
1. For the purpose of assessing additional plan review fees, please provide a written summary of all the intended deferred submittals on an 8.5 x 11 letter head stationary and submit same to the building official, Mr. Ron Boose.
2. Please provide special inspection certifications as required by the 2006 IBC, Section 1704.1.
3. Please provide the health department activity number.
SHEET A002
4. Please provide a complete project occupant load analysis with grand total.
SHEET A101
5. Please provide large scale floor plan references.
SHEET A091
6. Because door 106A is a required exit, the gate leading to the alley must have emergency exit hardware as required by 1008.1.9.
7. Detail 8:
a. Provide handrails on both sides of the stairs.
b. Provide dimensions for the ramp.
c. Provide finished floor elevations for both the stairs and ramp.
SHEET A 105
8. Please reference structural details for all the steel stairs and platforms shown on the roof plan. If none are provided, then please provide full structural details and calculations for all the steel platforms and stairs.
SHEET A200
9. Detail 2: Please insure the urinal stall has a minimum of 3'-0" clear width as required by ICC A, 117.1, Sections, 605 and 305.7.
SHEET AD012:
10. Please clarify how wall finish WC103 meets the requirements of the 2006 IBC, Section 1210.2.
END OF REVIEW
03/15/2012 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Denied 1. Provide the installed weight of the guest room and public space fan coils. Reference: Section 106.3.1, IMC 2006.
2. Show how the fan coils are being connected to the building structure and provide calculations to show that the building structure is not being adversely affected. Reference: Section 302.1, IMC 2006.
3. Condensate drains may not terminate over a roof drain unless the roof drain terminates at or above grade in an area capable of absorbing the condensate flow without surface drainage. Reference: Section 307.2.1, IMC 2006, as amended by the City of Tucson.
4. Revise the sequence of operation for the exhaust fans serving the public restrooms so that all of the air supplied to the restrooms will be exhausted (i.e. exhaust will continue as long as air is being supplied to the restrooms by the HVAC system). Reference: Section 403.2.1 (4), IMC 2006.
5. The occupant densities in the lobby and the food bar are quite different from the occupant density in the lounge. Revise the ventilation calculations based on the appropriate occupant density criteria as shown in Table 6-1, ASHRAE Standard 62.1-2004. Reference: Section 403.3, IMC 2006, as amended by the City of Tucson.
6. Revise the termination points of exhaust fans EF-B-1 and EF-B-4 to terminate outside of the building. Reference: Section 501.2.1 (3), IMC 2006.
7. Revise the termination point of the commercial dryer exhausts to terminate outside of the building. Reference: Section 504.4, IMC 2006.
8. Provide smoke detectors in the return air ducts, upstream of any outside air connections, for all air distribution systems with a capacity greater than 2,000 CFM. (Additional smoke detectors may be installed in the supply ducts but they are not required.) Reference: Section 606.1, IMC 2006.
9. Revise the combustion air openings for the pool equipment room to comply with the sizing requirements of Sections 304.5.3.1 and 304.10, IFGC 2006.
10. Show how the vent for the pool heater has been sized; provide the vent materials, the total vent height, offset dimensions, and the size of the draft hood on the pool heater. Show the construction of the architectural enclosure. Reference: Sections 503.6.9, 504.2.2, and 504.2.9, IFGC 2006.
11. Provide a detail of the pool heater vent, including the termination of the flue along with its clearance dimensions. Reference: Section 503.6.4, IFGC 2006.
12. Provide listing information for the "decorative rain cap" for the pool heater flue. Reference: Section 503.6.4.1, IFGC 2006.
03/15/2012 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied 1. Provide a natural gas piping design, including the existing loads and developed pipe lengths as well as showing the sizes, loads and developed lengths of the new piping. Reference: Section 106.3.1, IFGC 2006.
2. Provide the size of the water meter serving this building. Reference: Section 106.3.1, IPC 2006.
3. Show how the temperature of the hot water supply to the public lavatories is to be controlled. Reference: Section 416.5, IPC 2006 and Section 504.3, IECC 2006.
4. Provide backflow protection for the water make-up to the water feature located in the vestibule (101). Reference: Section 608.1, IPC 2006.
5. Provide a detail showing that there is an indirect connection for the sanitizing compartments of the 3-compartment sinks and a direct waste connection for the wash and rinse sections of the 3-compartment sinks. Reference: Section 802.1, IPC 2006.
6. Provide a detail showing that the installation of the open hub drains meets the requirements of Section 802.3.2, IPC 2006.
7. Provide roof drainage calculations and plans. Show that the overflow drainage channels and the emergency scuppers are adequately sized. Reference: Sections 1101, 1106 and 1107, IPC 2006.
03/15/2012 ROBERT SHERRY WATER REVIEW Denied Revise the site drawing to show the size and route of the building water service along with the location and size of both the water meter and the reduced pressure backflow preventer assembly. Reference: Section 106.3.1, IPC 2006.
03/15/2012 STEVE SHIELDS ZONING REVIEW Denied PDSD TRANSMITTAL

FROM: Steve Shields
Lead Planner

PROJECT: ALOFT Hotel
T12CM00722
Building Plan (1st Review)

TRANSMITTAL DATE: March 15, 2012

1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until all zoning comments or concerns have been addressed.

2. Zoning can not approve the building plan until the development package has been approved.

3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved development package. Additional comments may be forthcoming.

If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956
03/20/2012 DAN SANTA CRUZ ELECTRICAL-COMMERCIAL REVIEW Denied 1. Plan sheet E401 does not indicate new or existing electrical equipment as noted on Demo plans, note #1.
2.Riser diagram is to indicate : A. Voltage and phase. B. Panel sizes. C.Feeder loads. D. Circuit breaker size and AIC rating. E. Complete fault current analysis.
Dan Santa Cruz
Plan review
04/13/2012 GERRY KOZIOL WWM REVIEW Denied 1. ALOFT HOTEL RENOVATION
2. CONNECTING TO EXISTING ON SITE SEWER
3. RECOUNTED ALL WATEWATER PLUMBING FIXTURES - 1248FU @SFR RATE (1203FU DEMO @ SFR RATE) 45 FU NET @ SFR RATE = $11,907.45 AND 189FU @ COMMERCIAL RATE = $48,171.76 FOR A TOTAL SEWER FEE OF $60,079.21
4. NEED WW/IWC REVIEW OF 30LF GREASE INTERCEPTOR AND ELEVATOR SUMP SP2 THAT DISCHARGES OVER AN EXISTING LAUNDRY TRENCH DRAIN AND A 2" VISTIBULE HUB DRAIN FOR A WATER FEATURE