Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Number: T12CM00298
Parcel: 115202610

Review Status: Completed

Review Details: COMMERCIAL - NEW

Permit Number - T12CM00298
Review Name: COMMERCIAL - NEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
02/10/2012 MARTIN BROWN FIRE REVIEW Denied 1.) Several sheets are marked "Not For Construction". Remove.
2.) Sheets A1.1 and A1.3 show 3 buildings, all named "Building 1". Please clarify.
02/10/2012 TERRY STEVENS ZONING REVIEW Denied 02/10/2012

Development Services Department
Zoning Review Section

Terry Stevens
Lead Planner

Comments:

1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed.

2. Zoning could not verify that the building plan was in compliance with the approved development plan. Please submit two copies of the approved and stamped development, landscape, and NPPO plans with the next building plan submittal.

3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved site/development plan. Additional comments may be forthcoming.
02/16/2012 RONALD BROWN BUILDING-COMMERCIAL REVIEW Denied GENERAL
1. Please provide a code analysis data sheet for each building indicating the following:
a. Occupancy load
b. Building s.f. plus covered patio/porch s.f.
2. Please provide a copy of the approved development plan.
3. For the purpose of assessing additional plan review fees, please provide a deferred summary letter to the building official, Mr. Ron Boose.
4. Please provide special inspection certifications.
5. For all Building Reference Plans, please show the porch shade structure column.
6. For all Building Elevations please show the column of the porch shade structure.
SHEET A1.1
7. Please provide a code analysis summary explaining how this apartment complex design meets the 2006 IBC code requirements of Section 1107.6.2, Occupancy Group R2, Dwelling and Sleeping Units Type "A" and "B".
8. The Unit Schedule has an Awning schedule and refers to details 9/A6.1, 10/A6.1 and 2/A3.3. Please provide structural details and calculations for the awnings and the porch shade structure.
SHEET A2.1
9. The building section reference 1/A3.0 is incorrect. Should not it be 7/A5.2?
10. The building section reference 7/A5.2 is not similar.
a. Please provide full structural details and specifications for this guy wire suspended porch awning as depleted on exterior elevations 8 and 9 A2.3
11. What is the little circle in the courtyard just north west of door 13? It looks like a column. Please clarify.
12. Just south of the three double doors of the Community Room and Library are indicated a row of six columns supporting a roof structure as per section 7/A5.2. Please provide full structural details and calculation of this roof projection and metal roof extension.
13. The Unisex toilet in the lobby and staff Work area is not accessible for public use. Please reference ICC A117.1, Section 604 and 2006 IBC, Section 1109.2 and 1109.2.1.
14. At the community room, the exit door separation does not meet minimum code requirements of the 2006 IBC, section 1015.2, exception 2.
SHEET A2.2
15. Where is key note 10.37?
16. What is the little circle in the courtyard just north west of door 13? It looks like a column. Please clarify.
SHEET A2.3
17. Please show patio roof columns at Detail 5 as depleted per details 1/A2.1 and 1/A2.2.
18. At details 8 and 9 please define the tall pole looking element that has a 10'-0" T.O.Wall elevation marker.
SHEET A2.4
19. At detail 2, please reference the porch roof cover detail.
SHEET A2.5
20. Detail 7 has floating patio roof element.
SHEET A3.1
21. Please provide details for the shower, controls, grab bars, seats, drains, slopes and etc. for all unit floor plans.
SHEET A3.3
22. At detail 4, the unisex toilet does not meet accessible standards for public use toilets.
23. Provide structural details and calculations for details 3, 4, 5, and 6.
SHEET P2.3
24. Please provide structural calculations for details WH4 and WH5.
SHEET S2.1
25. Provide structural details and calculations for all roof areas referred to as awnings.
26. Provide structural details and calculations for the roof/awning porch roof just out side the lobby.
SHEET S2.3
27. Provide lintel LT1 at both sides of the building just after the wall turns inward near a detail reference 203.
END OF REVIEW
02/16/2012 BETH GRANT COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Completed
02/17/2012 ELIZABETH LEIBOLD ENGINEERING REVIEW Denied Silverwood Senior Housing bldg permits can not be approved for Engineering review until base plan D11-0032 is approved and grading permit T11BU01259 is approved and issued.
03/01/2012 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied 1. A separate permit is required for the installation of a private sewer collection system and private manholes. Reference: Title 18, R18-9-E302, 4.02 General Permit, Arizona Administrative Code.
2. Provide a sealed copy of the civil site (utility) plan showing the size, route and slope of the building sewers, including the location of all cleanouts, as referenced on sheet P1.2. Reference: Section 106.3.1, IPC 2006.
3. Clarify the identification of fixture P5 for buildings 2 through 10; should it actually be P8? Reference: Section 106.3.1, IPC 2006.
4. Provide quality requirements (e.g. third-party listed or certified, conforming to the standards cited in the 2006 IPC) for all plumbing fixtures and appliances being provided by others. Reference: Sections 303.4 and 402.1, IPC 2006. (Note: print the heading information on the plumbing fixture schedule for buildings 3 through 10.)
5. The plumbing fixture schedule on sheet P3.1 states that the pipe sizing calculations are based on Appendix A, UPC 2006 and the bathroom group fixture units are from Appendix L, UPC 2006. If this is the intent, revise the calculations to use the fixture units from Appendices A and L, UPC 2006, not from Appendix E, IPC 2006. Reference: Section 604.1, IPC 2006. (Note: print the heading information on the plumbing fixture schedule for buildings 3 through 10.)
6. Revise the size of the "wet-v" shown in details 1 and 3/P2.1 from 2" to 3" if the 3" cleanout is to remain. Reference: Section 704.2, IPC 2006.
7. Provide roof drainage calculations and dimensional information for the gutters and downspouts. Reference: Sections 1106 and 1107, IPC 2006.
03/01/2012 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Denied Clarify the ventilation method to be used for dwelling units A and B; the mechanical floor plan implies mechanical ventilation but the fan coil schedule and the ventilation calculations indicate that natural ventilation will be used. Reference: Section 401.2, IMC 2006.
03/01/2012 ROBERT SHERRY WATER REVIEW Approved
03/09/2012 LEERAY HANLY ELECTRICAL-COMMERCIAL REVIEW Approved
03/14/2012 GERRY KOZIOL WWM REVIEW Denied - NEED WASTEWATER 3RD FLOOR REVIEW OF LOCATION/METHOD OF CONNECTION TO PUBLIC SEWER CHAD AMATEAU 740-6547
- NEED 1ST FLOOR MANHOLE CONSTRUCTION PERMIT APPROVAL - NEED DEQ REVIEW & APPROVAL TO CONSTRUCT ON SITE PRIVATE SEWER WITH MANHOLES DAVID AMASH 243-7400 33N STONE AV 7TH FLOOR BANK OF AMERICA BLDG - NEED COPY OF PRIVATE SEWER PLANS FOR BASE MAP UPDATE
- NEED PCRWRD/3RD FLOOR CAPACITY REVIEW - KURT STEMM 740-6534

Final Status

Task End Date Reviewer's Name Type of Review Description
03/27/2012 FERNE RODRIGUEZ OUT TO CUSTOMER Completed