Permit Number: T12CM00069
Parcel: 137055270

Review Status: Completed

Review Details: COMMERCIAL - TI

Permit Number - T12CM00069
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
01/11/2012 STEVE SHIELDS ZONING REVIEW Approved
01/11/2012 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Denied 1. Show the size, route, and termination point of the condensate drains. Reference: Section 307.2, IMC 2006 as amended by the City of Tucson.
2. Specify the R-value of the duct insulation. Reference: Section 503.2.7, IECC 2006, as amended by the City of Tucson.
01/11/2012 ERIC NEWCOMB ADA REVIEW Passed
01/11/2012 ROBERT SHERRY WATER REVIEW Approved
01/11/2012 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Denied 1. SHEET A0.0: PROVIDE A LARGER SITE PLAN, INCLUDING THE REQUIREMENTS OF IBC SECTION 106.2.
2. SHEET A1.1; DEMOLITION PLAN: INDICATE THE NORTH ARROW ON THE PLAN.
3. SHEET A2.1; FLOOR PLAN: INDICATE THE NORTH ARROW ON THE PLAN.
4. SHEET A2.1; FLOOR PLAN: ADD NOTE 2 TO THE LEFT EXTERIOR WALL.
01/11/2012 LOREN MAKUS ENGINEERING REVIEW Approved
01/11/2012 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied 1. Provide a design for mounting the water heater above the restroom ceiling along with structural calculations to show that the water heater is safely supported. Reference: Sections 106.3.1 and 301.2, IPC 2006.
2. Provide a vacuum relief valve for bottom-fed storage-type water heater. Reference: Section 504.2, IPC 2006.
3. All storage-type water heaters require a listed expansion tank. Please show expansion tanks on plans. Reference: Section 607.3, IPC 2006 with local amendments. (Note that the specified water heater is not an instantaneous water heater as stated in keynote 8.)
4. Show the size, route and termination of the T&P relief piping. Reference: Section 504, IPC 2006.
5. Show how the temperature of the hot water supply to the public lavatories is controlled. Reference: Section 504.3, IECC 2006.
6. Provide cleanouts for all horizontal drains. Reference: Section 708.3.1, IPC 2006.
7. Provide cleanouts sized per Section 708.7, IPC 2006.
8. Where does key note #9 (sheet M2.1) occur?
9. Specify the materials to be used for the water piping and for the drain and vent piping.
01/11/2012 BETH GRANT COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Passed
01/12/2012 RAY MAJUTA ELECTRICAL-COMMERCIAL REVIEW Denied T12CM00069

Electrical review denied :
1. Sheet E4 shows a feeder of #3 cu conductors coming from the service to panel A which are good for 100 amps, the main service shows a 200 amp main and panel A is 200 amps, the load on the panel shows 134 amps ?
2. City of Tucson Commercial Submittal Requirements require
the size capacity of the main service, a load which includes a total load including this space.



Ray Majuta
Electrical Pln Review,
PDSD, City of Tucson,
1/12/12
Ray.majuta@tucsonaz.gov
01/13/2012 MARTIN BROWN FIRE REVIEW Approved
01/24/2012 CPIERCE1 WWM REVIEW Needs Review