Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - NEW
Permit Number - T11CM03929
Review Name: COMMERCIAL - NEW
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 01/13/2012 | LEERAY HANLY | ELECTRICAL-COMMERCIAL | REVIEW | Approved | |
| 01/13/2012 | LOREN MAKUS | ENGINEERING | REVIEW | Approved | |
| 01/20/2012 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Denied | SHEET A1 1. As per the 2006 IBC, section 1109.5, please provide another water fountain. 2. Toilet 110 is not accessible as required by the 2006 IBC, Section 1109.2. Please provide a large scale floor plan and elevations showing all required accessibility requirements such as dimensions, clearances, heights, accessories and fixtures. 3. The second floor is not defined in these documents in either architectural plans nor structural plans. Please provide full plans and details for second level floor plan. a. Please provide occupancy use of the second floor plan area and egress elements such as stairs etc. b. Please provide structural calculations for the fan coil unit plus mounting details. 4. Please provide a detail of all interior partitions that are scheduled not to go to the bottom of the deck and how they comply with 2006 IBC, Section 1607.13. Please provide structural calculations. 5. Please show laterial reinforcement of the 4'-0" high pony wall. Please provide structural calculations. SHEET A4 6. Please show roof slope for all canopies. SHEET A6 7. At detail "A": provide accessible service counter as required by ICC/ANSI 117.1, Section 904. END OF REVIEW |
| 01/24/2012 | TERRY STEVENS | ZONING | REVIEW | Denied | 01/25/2012 Development Services Department Zoning Review Section Terry Stevens Lead Planner Comments: 1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed. 2. Zoning could not verify that the building plan was in compliance with the approved site plan. Please submit two copies of the approved and stamped site, landscape, and NPPO plans with the next building plan submittal. 3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved site plan. Additional comments may be forthcoming. |
| 01/25/2012 | GERRY KOZIOL | WWM | REVIEW | Denied | 1. PARKER AUTOMOTIVE SPECIALISTS 2. APPROVED ONLY FOR CONNECTION TO EXISTING ON - SITE PRIVATE SEWER & EXISTING HCS PER CUSTOMER SITE DRAWING AS2- NO NEW CONNECTION TO 18" PUBLIC SEWER 3. NEED WASTEWATER 5TH FLOOR CREDIT EVALUATION- 740-6602 OR 740-6606 |
| 01/27/2012 | LEERAY HANLY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1) ENVELOPE COMPLIANCE CERTIFICATE LISTS PIMA ARIZONA AS LOCATION. IT SHOULD BE PIMA COUNTY NOT THE CITY OF PIMA 2) PROVIDE SEQUENCE OF OPERATION FOR EXHAUST FANS IN RESTROOMS TO SHOW OPERATION IF A/C IS ON. (NOTED IN MECHANICAL PLANS AS ON WHEN BUILDING OCCUPIED, BUT METHOD NOT SHOWN ON ELECTRICAL PAGES) 3) SPECIFY R VALUE OF DUCT INSULATION 3) |
| 01/27/2012 | RMYERS1 | WATER | REVIEW | Denied | 1. Revise the site drawing to include the following information: a.the location and size of the water meter b.the location of the main water lines and fire hydrants c.The location of the gas meter d.the location and size of the public sanitary sewer and e the location, invert, and rim elevation of all manholes and cleanouts. Reference: City of Tucson Development Standard No. 2-01.1.0 2 3.8 D and Section 103.2.3, UPC 2006. |
| 01/27/2012 | RICK MYERS | PLUMBING-COMMERCIAL | REVIEW | Denied | Revise the site drawing to include the following information: f.the location and size of the water meter g.the location of the main water lines and fire hydrants h.The location of the gas meter i.the location and size of the public sanitary sewer and j.the location, invert, and rim elevation of all manholes and cleanouts. Reference: City of Tucson Development Standard No. 2-01.1.0 2 3.8 D and Section 103.2.3, UPC 2006. 2. Provide roof drainage calculations and plans. All roof areas shall be drained by roof drains, scuppers, or gutters. Reference: Section 1101.11.1 UPC 2006. 3. Include a material schedule. DWV, sewer, water, condensate, gas piping, and any other material types. 4. Show how the domstic water piping meets requirements of the 2006 IECC. Insulation of service water piping. 5. Include the method of sterilization. Reference: 609.9 2006 UPC. 6. See sheet P-1. The water heater has been omitted on the floor plan. Include the water heater in the Fixture Schedule, and provide a detail for the water heater installation. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 01/30/2012 | CPIERCE1 | OUT TO CUSTOMER | Completed |