Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - NEW
Permit Number - T11CM03636
Review Name: COMMERCIAL - NEW
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 12/01/2011 | MARTIN BROWN | FIRE | REVIEW | Denied | This comments apply to the job as a whole and will be repeated for all activity numbers. 1) Fire Department approved lock boxes will be required at sliding gates. 2) Fire sprinklers will need to be installed in building A. Reference 2006 IFC, section 903.2.7. 3) An alarm system will be required in all residential buildings except those containing fire sprinklers. Reference 2006 IFC, section 907.3.6. 4) Please provide clarification regarding separation between Building A and Leasing building. Are they connected by a roof structure? Do they require fire wall separation? |
| 12/05/2011 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Clarify the plumbing code to be used for this activity. The plumbing General Notes on sheet P3.1 refer to the 2006 UPC but the Code analysis on sheet T1.1 refers to the 2006 IPC. This review has been made using the 2006 UPC. 2. Indicate the materials to be used in the proposed plumbing systems for this activity. Reference: Sections 103.2.3, 301.1, 604.0, 701.0, 903.0, 1102.0, and 1209.5, UPC 2006. Clarify which new water piping is to be PEX. 3. Correct the equipment tag for the showers in waste and vent isometric 3/P2.1 to coordinate with the plumbing floor plan. Reference: Section 103.2.3, UPC 2006. 4. Provide water pressure and water pipe sizing calculations. Reference: Section 610.1, UPC 2006. 5. The laundry closets appear to be designed to accommodate a stacked washer/dryer; verify that the standpipe waste receptors for the clothes washers will be readily accessible for inspection and cleaning when the stacked washer/dryers are in place. Reference: Section 804.1, UPC 2006. |
| 12/05/2011 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | Show that the door to the laundry closet has a minimum makeup air opening of 100-square inches. Reference: Section 504.5, IMC 2006. |
| 12/05/2011 | ROBERT SHERRY | WATER | REVIEW | Passed | |
| 12/13/2011 | GERRY KOZIOL | WWM | REVIEW | Approved | |
| 12/14/2011 | PAUL MACHADO | ENGINEERING | REVIEW | Denied | Flood Plain use permit required. PM. 12-14-11. |
| 12/14/2011 | PAUL MACHADO | ENGINEERING | REVIEW | Denied | To: architectural design group, inc.DATE: December 29, '11 2510 E. Grant Rd., ste. 140 Tucson, Arizona 85716 Subject: Casa Presidio Apartments, 2002 E. Fort Lowell Rd. Site plan DP11-0015 (First Review) T13S, R14E, Section 32 RESUBMITTAL REQUIRED: Development Package and Drainage Statement. The Development Package (DP) and Drainage Statement (DS) cannot be approved as submitted. Please address the following review comments prior to the next submittal. Site Plan: 1. Please include a response letter to the comments along with the corrected copies of the DP. 2. Please provide property description per D.S. 2-02.2.1.3. 3. Label existing and future sight visibility triangles per D.S. 2-02.2.1.10. The fut. FOC location for a 100' MS and R is 11' from the fut. R/W line. All SVT's begin at the face of curb with the stem side of the SVT is drawn toward the property, not the street. The SVT dimensions for a local st. to an arterial (Ft. Lowell Rd.): NS = 20'x 340', FS = 20'x 125'. The SVT dimensions for a Drive/PAAL to a Local St. (Olson and Wilson Aves.): NS = 20'x 185', FS = 20'x 110'. 4. Show the limits of the 100-year floodplain and water surface elevation per D.S. 2-02.2.1.15. Any const. in the FEMA regulated flood plain requires a Flood Plain Use Permit (FUP). Separate FUP's will be required for Bldg. "A" and Bldg. "B". The FUP for the proposed patio wall in the flood plain will be attached to Bldg. "B's" FUP. Submit 2 sets of the site plan, drainage statement along with the FUP application for both buildings. 5. Construction cost estimates are required or shall be included for any improvements to any structures that are attached to Bldg. "A". This includes Bldg. J, Bldg. L and the associated improvements. 6. The construction cost of the improvements shall not exceed 50% of the total appraised/assessed value of the existing structure, not including the land. An appraisal for each bldg. separate from the cost of the land that is located in the FEMA regulated floodplain shall be included with the cost est. 7. Provide a note on the plans indicating that any future construction (covered parking) in the flood plain shall require separate FUP's. 8. List the total disturbed area in sq. feet on the plans. 9. Please provide Drainage patterns and finished grades per D.S. 2-02.2.1.16. 10. Please list estimated cut & fill quantities per D.S. 2-02.2.1.17. List on the plans if both are "0". 11. Please show dimensioned right-of-way, including any applicable Major Streets and Routes (MS&R) Plan right-of-way per D.S. 2-02.2.1.19. 12. Dimension from street monument lines to existing and proposed curbs, sidewalks, driveways, and utility lines per D.S. 2-02.2.1.21. 13. Provide City of Tucson Datum, including City Field Book and page number per D.S. 2-02.2.1.23. 14. Show all fences, walls, or vegetation for screening and sight visibility by type, material, height, location and spacing per D.S. 2-02.2.1.27. Any const. in the FEMA regulated flood plain requires a FUP. See comment no. 4. Walls constructed in flood plain shall be built with engineered drainage openings. 15. Show Development plan (DP11-0015) number on all sheets per D.S. 2-02.2.1.29. 16. Show refuse container location, size, and access thereto fully dimensioned per D.S. 2-02.2.1.32 and D.S. 6-01.0. Call out that any new construction done to the existing refuse enclosures shall be per COT Development Standard 6-01.0. 17. A permit or a private improvement agreement will be necessary for any work performed within the Right-of-way. Contact Permits and Codes at (520) 791-5100 for permit information. 18. Please show a typical cross section of the P.A.A.L. or call out the percentage of slopes. Call out the GB at the D/W, if applicable. 19. Please show the proposed roof drainage patterns, 100% of the 10-year flow must be conveyed under the sidewalks including any other site drainage as well. Please provide supporting calculations to demonstrate compliance with D.S. 3-01.4.4. If the location(s) of the roof scuppers and/or sidewalk scuppers have not yet been decided, a general note indicating sidewalk scuppers will be used when the roof drain/sidewalk scupper locations have been designed and located and that the 10-year flow must be conveyed under any other sidewalks and/or pedestrian paths will suffice. 20. List the consulting engineer and the owner/developer on the plans with the pertinent information. 21. A floodplain use permit is required. 22. Add note: "Depress all landscaped areas 6" maximum for water harvesting". 23. "A grading permit may be required for this project depending on the earthwork quantities listed plan. See note no. 10. A grading permit may not be issued prior to site plan approval. Subsequent comments may be necessary, depending upon the nature and extent of revisions that occur to the plans". 24. If you would like to discuss the comments prior to the re-submittal of the DP, a meeting can be scheduled to do so. The contact information is listed below. Drainage Statement: 1. Please include a response letter to the comments along with the corrected copies of the DS. 2. Show the limits of the 100-year floodplain and water surface elevation in the DS. 3. The construction cost of the improvements shall not exceed 50% of the total appraised/assessed value of the existing structure, not including the land. An appraisal for each bldg. separate from the cost of the land that is located in the FEMA regulated floodplain shall be included with the cost est. 4. Any const. in the FEMA regulated flood plain requires a Flood Plain Use Permit (FUP). Separate FUP's will be required for Bldg. "A" and Bldg. "B". The proposed patio wall in the flood plain will be attached to Bldg. "B's" FUP. Submit 2 sets of the site plan, drainage statement along with the FUP application for both buildings. 5. A Drainage Statement is a brief description of drainage conditions applicable for a site which are not affected by 100 year flows of 100 cfs, of more……per S.M.D.D.F.M., chap. II, 2.1.2. The DS must be submitted with the re-submittal of the DP. 6. The content and format of the Drainage Statement should follow S.M.D.D.F.M., chap. II, 2.2. 7. Show the project address or administration address on the cover sheet of the DS. If you have any questions, I can be reached at 837-4932 or Paul.Machado@tucsonaz.gov Paul P. Machado Senior Engineering Associate City of Tucson - Planning and Development Services Department 201 N. Stone Avenue P.O. Box 27210 Tucson, Arizona 85726-7210 (520) 837-4932 office (520) 879-8010 fax C:/ 2002 E. Fort Lowell Rd. Site-DP |
| 12/15/2011 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Denied | GENERAL 1. Several sheets through out this submittal have lettering smaller than the COT standard for all document submittals of 3/32" minimum for all lower and upper case. Please revise all sheets that are non-compliant and resubmit. 2. The line weight of existing building elements to remain is too light. Please make the lines darker and resubmit. 3. The scope of work needs to be more clearly defined: a. Please provide 1st and 2nd floor plans of all of the existing apartment buildings showing clearly those building elements to remain and those building elements to be demolished. Show all 1st floor walkways and stairways. Show all balconies and stairways. b. Please provide 1st and 2nd floor plans of all of the modified apartment buildings showing clearly the existing building elements and the new building elements. Show all 1st floor walkways and stairways. Show all balconies and stairways. 4. Provide construction details and large scale elevations for new balcony railings. Show complinace with the 2006 IBC, Sections 1013 and 1606.7.1. 5. Provide structural calculations for all roof top mounted HVAC equipment. 6. Provide full roof framing plans and details for all new clerestory roof framing. 7. Provide elevations for all new toilet room and new kitchen plans. END OF REVIEW |
| 12/23/2011 | TERRY STEVENS | ZONING | REVIEW | Denied | 12/23/2011 Development Services Department Zoning Review Section Terry Stevens Lead Planner Comments: 1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed. 2. Zoning could not verify that the building plan was in compliance with the approved site plan. Please submit two copies of the approved and stamped site, landscape, and NPPO plans with the next building plan submittal. 3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved site plan. Additional comments may be forthcoming. |
| 12/28/2011 | KEN VAN KARSEN | ELECTRICAL-COMMERCIAL | REVIEW | Approved |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 01/09/2012 | CINDY AGUILAR | OUT TO CUSTOMER | Completed |