Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T11CM03491
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
11/09/2011 | STEVE SHIELDS | ZONING | REVIEW | Approved | |
11/10/2011 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | Clarify how ventilation will be supplied to the future tenant from FC-1 which serves both tenant areas but is controlled from the the present tenant's area. Reference: Section 403, IMC 2006. |
11/10/2011 | RONALD BROWN | ADA | REVIEW | Passed | |
11/10/2011 | ROBERT SHERRY | WATER | REVIEW | Denied | Provide a site drawing showing the size and route of the building water supply along with the location and size of both the water meter and the reduced pressure backflow preventer assembly. Reference: Section 106.3.1, IPC 2006. |
11/10/2011 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Denied | 1. Occupant load for Business as per table 1004.1 is 1/100 sf which calculates to a maximum occupant load of 97. To attain an occupant load as indicated on your code data summary of 200, an appeal to the building offical must be obtained. 2. At detail 3/A3.0, please provide vertical grab bar. 3. At detail 1/A3.0: a. Show accessible clearances as required by ICC/ANSI 117.1, 2003 Edition, Chapter 6. b. Show drinking fountains and required clearances as per Section 602. SHEET A/1.0 4. Verify and show required clearances at drinking fountain. SHEET A/3.0 5. Detait A is not as designed on sheet A1.0. Reconcile and resubmit. Generic details are not acceptable. 6. Please provide last approved site Plan. 7. Please provide structural calculations for all new roof top mounted HVAC units and suspended fan coil units, including structural details. END OF REVIEW |
11/10/2011 | LAITH ALSHAMI | ENGINEERING | REVIEW | Approved | |
11/10/2011 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | Provide sufficient information to show that the installation of the new plumbing fixtures will not cause the existing water supply and sanitary waste systems to become overloaded. Reference: Section 102.4, IPC 2006. |
11/10/2011 | MARTIN BROWN | FIRE | REVIEW | Approved | |
11/10/2011 | BETH GRANT | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Completed | |
11/14/2011 | RAY MAJUTA | ELECTRICAL-COMMERCIAL | REVIEW | Approved | |
11/23/2011 | GBONILL1 | WWM | REVIEW | Needs Review |