Review Status: Completed
Review Details: COMMERCIAL - BLDG/FIRE/ZONING/ENG
Permit Number - T11CM03342
Review Name: COMMERCIAL - BLDG/FIRE/ZONING/ENG
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 10/24/2011 | DAVE MANN | FIRE | REVIEW | Approved | |
| 10/27/2011 | RAY MAJUTA | ELECTRICAL-COMMERCIAL | REVIEW | Denied | See review comments for T11CM02581, Ray T Majuta Elect Pln Review, PDSD,CoT, 10/30/11 |
| 10/27/2011 | TERRY STEVENS | ZONING | REVIEW | Denied | 10/27/2011 Development Services Department Zoning Review Section Terry Stevens Lead Planner Comments: 1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed. 2. Zoning could not verify that the building plan was in compliance with the approved site plan. Please submit two copies of the approved and stamped site, landscape, and NPPO plans with the next building plan submittal. 3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved site plan. Additional comments may be forthcoming. |
| 11/01/2011 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Denied | 1. GEOTECHNICAL INVESTIGATION REPORT: PROVIDE AN ALLOWABLE END BEARING CAPACITY TABLE IN THE REPORT FOR DRILLED SHAFT DESIGN (SIMILAR TO PROJECT T11CM03205). 2. SHEET CA-1; CANOPY PLAN: KEY NOTE 2 INDICATES TO SEE STRUCTURAL DRAWINGS FOR THE CONCRETE PAVING. WHERE IS THAT LOCATED ON THE DRAWINGS SUBMITTED? 3. SHEET CA-4; SECTION C: A NOTE INDICATES TO SEE SHEET E1 FOR THE TUBE COLUMN SIZE. REVISE THE NOTE (NO SHEET E1). 4. SHEET CA-4.1; SECTION E: A NOTE INDICATES TO SEE SHEET E1 FOR THE TUBE COLUMN SIZE. REVISE THE NOTE (NO SHEET E1). 5. GENERAL: ALL DEFERRED SUBMITTALS MUST BE APPROVED IN WRITING BY RON BOOSE (BUILDING OFFICIAL) BEFORE THOSE SUBMITTALS WILL BE REVIEWED. RON.BOOSE@TUCSONAZ.GOV. 6. GENERAL: PROVIDE WRITTEN RESPONSES TO ALL REVIEW COMMENTS. |
| 11/09/2011 | LOREN MAKUS | ENGINEERING | REVIEW | Approved |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 11/30/2011 | CPIERCE1 | OUT TO CUSTOMER | Completed |
| 11/30/2011 | CPIERCE1 | REJECT SHELF | Completed |