Permit Number: T11CM03131
Parcel: 13609014B

Review Status: Completed

Review Details: RESUBMITTAL - SITE

Permit Number - T11CM03131
Review Name: RESUBMITTAL - SITE
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
10/27/2011 ANDREW CONNOR LANDSCAPE REVIEW Denied Landscape / NPPO can not approve plans until SCZ review is complete. Include approval documentation with next submittal.
10/27/2011 ANDREW CONNOR NPPO REVIEW Denied Landscape / NPPO can not approve plans until SCZ review is complete. Include approval documentation with next submittal.
11/03/2011 MICHAEL ST. PAUL ZONING REVIEW Denied CDRC TRANSMITTAL


FROM: Michael St.Paul, Planning Technician

PROJECT:
T11CM03131 (T11SA00393 SCZ)
10355 East 29th Street
Parking structures with photovoltaic systems on roof
Religious Use


TRANSMITTAL: November 3, 2011


COMMENTS: Please attach a response letter with the next submittal, which states how all Zoning Review Section comments regarding the Land Use Code (LUC) and Development Standards were addressed. This site review is based upon Development Standards 2-02 (DS 2-02).

1.) A Scenic Corridor Zone (SCZ) has also been submitted for review (T11SA00393). Approval of the SCZ plan is required for final approval of this site plan.

2.) The site is located in the SR zone (LUC Section 2.2.4). The Development Designator for Religious Use in this zone is "6" (LUC Sections 2.2.4.2.C.1 & 3.2.3.2.A). The Perimeter Yard Indicator is FF (LUC Sections 3.2.3.2.A & 3.2.6.4).

3.) Identify the zoning of the adjacent parcels (DS 2-02.2.1.A.28).

4.) Provide the street names on the site plan (DS 2-02.2.1.A.18).

5.) Dimension the right-of-way (ROW). Include the Major Streets and Routes (MS&R) information with the future ROW and curb locations on the site plan (DS 2-02.2.1.A.19). (See comments for the SCZ submittal.)

6.) Provide the existing and future sight visibility triangles (SVTs) on the site plan (DS2-02.2.1.A.10).

7.) Dimension the points of egress and ingress on the site plan (DS 2-02.2.1.A.11).

8.) Provide a dimensioned parking space detail for both the standard and handicapped parking spaces (DS 2-02.2.1.A.8).

9.) Provide the information required for the Scenic Corridor Zone on this site plan. (See the comments for T11SA00393.)

10.) There may be additional comments for information provided or required with subsequent submittals.