Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T11CM02851
Review Name: RESUBMITTAL
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 12/01/2011 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Denied | 1. Need Approved Site Plan. 2. Need County Health Department activity number. SHEET NUMBERS A9.4 AND S4.1 3. Detail numbers 1/A9.4 and 108/S4.1 are the same detail but are contradictory to each other. Please reconcile. END OF REVIEW |
| 12/02/2011 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Second request: revise the font size used on the drawings to a minimum of 3/32-inch high (see sheet P1.1). Reference: Section 106.1.1, IBC 2006. 2. Comment not addressed. Coordinate the location of the entry point for the water service to the building; sheets C3.1 and P1.1 show different entry locations. Reference: Section 103.2.3, UPC 2006. 3. Comment not addressed. Revise the size of the under-floor portion of the vents for the floor sinks located in the equipment room and in the sales floor area; the size of that portion of the vent shall comply with the cleanout size requirements of Table 7-6, UPC 2006. Reference: Section 707.11, UPC 2006. 4. Comment not addressed. Provide additional cleanouts in drainage pipe exceeding 100-feet in developed length (see the building sewer on sheet C3.1). Reference: Section 707.4, UPC 2006. 5. Comment not resolved; the waste and vent schematic shows a mop sink and a floor drain without flow control devices. [Original comment: Each fixture that is connected to a hydromechanical grease interceptor requires a flow control device unless the grease interceptor is equipped with an integral flow control device. Reference: Section 1014.2.1, UPC 2006.] |
| 12/02/2011 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Approved | |
| 12/05/2011 | ANDREW CONNOR | ZONING | REVIEW | Denied | 12/14/2011 Development Services Department Zoning Review Section Terry Stevens Lead Planner Comments: 1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed. 2. Zoning could not verify that the building plan was in compliance with the approved site plan. Please submit two copies of the approved and stamped site, landscape, and NPPO plans with the next building plan submittal. 3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved site plan. Additional comments may be forthcoming. |
| 12/14/2011 | RAY MAJUTA | ELECTRICAL-COMMERCIAL | REVIEW | Approved | |
| 12/29/2011 | GERRY KOZIOL | WWM | REVIEW | Denied | NEED WASTEWATER REVIEW OF LOCATION OF CONNECTION TO PUBLIC SEWER - CHAD AMATEAU - 1ST FLOOR 740-6547 NEED 5TH FLOOR CREDIT EVALUATION FOR DEMO OF EXSISTING BLDG. 740-6602 OR 740-6606 |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 01/04/2012 | FERNE RODRIGUEZ | OUT TO CUSTOMER | Completed |
| 01/04/2012 | SUE REEVES | REJECT SHELF | Completed |