Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T11CM02799
Review Name: COMMERCIAL - TI
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 08/29/2011 | ERIC NEWCOMB | ADA | REVIEW | Passed | |
| 08/29/2011 | STEVE SHIELDS | ZONING | REVIEW | Approved | |
| 08/29/2011 | BETH GRANT | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | |
| 08/29/2011 | JASON GREEN | ENGINEERING | REVIEW | Approved | |
| 08/29/2011 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Denied | 1. SHEET A-101: NOTE 14 INDICATES TO RETAIN THE EXISTING GRAB BARS. PROVIDE A DETIAL ON THE DRAWINGS INDICATING GRAB BAR AND DISPENSER LOCATION PER THE ICC/ANSI FIGURES 604.5.1, 604.5.2, AND 604.7. 2. SHEETS A-101, A-103, A-104, AND A-201; DRAWING NOTES: REFERENCE IS MADE TO AN AUGUST 2010 MANUAL FOR TYPICAL SPECIFICATIONS AND DETAILS. PROVIDE THOSE THAT ARE PERTINENT TO THIS PROJECT. 3. SHEET A-104: IBC SECTION 1109.11 REQUIRES 5% OF SEATING/STANDING SPACE TO BE ACCESSIBLE. INDICATE THOSE LOCATIONS ON THE PLAN. 4. SHEET A-201; NOTE 5: THE INTERIOR WALL MUST MEET THE IBC SECTION 1607.13 FOR HORIZONTAL LOADING. PROVIDE A DETAIL INDICATING BRACING SIZE AND SPACING AT THE TOP OF THE WALL. SHOW THE CONNECTION DETAIL OF THE BRACE TO THE TOP OF THE WALL AND TO THE EXISTING ROOF STRUCTURE. |
| 08/30/2011 | ROBERT SHERRY | WATER | REVIEW | Approved | |
| 08/30/2011 | DAVE MANN | FIRE | REVIEW | Approved | |
| 08/30/2011 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Passed | |
| 08/30/2011 | RAY MAJUTA | ELECTRICAL-COMMERCIAL | REVIEW | Denied | Electrical notes: Sheet A 201 shows a quantity of fixtures to be replaced, how will this effect the existing loads ? Will the new loads be lower or higher,please indicate on plan. RT Majuta Elect Pln Ck PDSD, Cof Tuc. 8/30/11 |
| 08/30/2011 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Approved | |
| 09/07/2011 | CAGUILA1 | WWM | REVIEW | Needs Review |