Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T11CM02705
Review Name: COMMERCIAL - TI
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 08/29/2011 | DAVE MANN | FIRE | REVIEW | Approved | |
| 08/31/2011 | ROBERT SHERRY | WATER | REVIEW | Approved | |
| 08/31/2011 | STEVE SHIELDS | ZONING | REVIEW | Denied | DSD TRANSMITTAL FROM: Steve Shields Lead Planner PROJECT: Chase Bank Expansion @Tanque Verde & Sabino Canyon T11CM02705 Building Plan (1st Review) TRANSMITTAL DATE: August 31, 2011 1. The building, plan has been reviewed by Zoning Review Section but cannot approve the plans until all zoning comments or concerns have been addressed. 2. Zoning can not approve the plans until a site plan is provided and approved. 3. Zoning will re-review the plans on the next submittal to insure compliance with the approved and site plan. Additional comments may be forthcoming. If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956 C:\planning\building\t11cm02705.doc RESUBMITTAL OF THE FOLLOWING IS REQUIRED: |
| 08/31/2011 | JASON GREEN | ENGINEERING | REVIEW | Denied | Building plan will be reviewed once an approved site plan is provided. |
| 09/01/2011 | LEERAY HANLY | ELECTRICAL-COMMERCIAL | REVIEW | Approved | ELECTRICAL APPROVAL BY DAN SANTA-CRUZ |
| 09/01/2011 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 2. Provide energy code compliance calculations for the building envelope using the correct climate zone for Pima County < 4,000 feet. Provide sufficient detail on the drawings to evaluate the energy compliance of the building envelope. The information shall, as a minimum, include U-factors of the envelope systems and fenestration components, along with the R-values of the insulation and the SHGC for the fenestration. Reference: Sections 101.4 and 104.2, International Energy Conservation Code 2006. |
| 09/01/2011 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | Provide roof drainage calculations and plans. Include the contribution of the existing roof areas to the drainage requirements of the new roof areas in the calculations. Reference: Sections 1101, 1106 and 1107, IPC 2006. |
| 09/07/2011 | LHANLY1 | WWM | REVIEW | Passed | no new plumbing fixtures |
| 09/07/2011 | LEERAY HANLY | BUILDING-COMMERCIAL | REVIEW | Approv-Cond | pending authorization for minor redline of framing details on arch. pages. |
| 09/07/2011 | BETH GRANT | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Approved |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 09/09/2011 | CPIERCE1 | OUT TO CUSTOMER | Completed |
| 09/09/2011 | SUE REEVES | REJECT SHELF | Completed |