Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - TI
Permit Number - T11CM02660
Review Name: COMMERCIAL - TI
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
08/25/2011 | SREEVES1 | ADA | REVIEW | Passed | |
08/25/2011 | GERRY KOZIOL | WWM | REVIEW | Denied | NEED TO CLARIFY DRAWINGS SHOWING EXSISTING WASTEWATER PLUMBING FIXTURES REMOVED FOR CREDIT NEED 5TH FLOOR CREDIT EVALUATION |
08/25/2011 | BETH GRANT | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | |
08/26/2011 | DAVE MANN | FIRE | REVIEW | Approved | |
08/29/2011 | LEERAY HANLY | ELECTRICAL-COMMERCIAL | REVIEW | Denied | Provide 1-line diagrams and completed panel schedules for all new work. Any panel with additional loads must also have complete panel schedule and load calcs for any upstream feeder panels. Each panel shall be phase balanced within 15% per C.O.T. ordinance Clarify removed loads v. added loads & total loads at each panel. |
08/30/2011 | LHANLY1 | WATER | REVIEW | Approved | |
08/30/2011 | LEERAY HANLY | PLUMBING-COMMERCIAL | REVIEW | Denied | General notes indicate you are using the 2006 IPC and the 1997 UPC while cover sheet calls for 2006 UPC. Pick either the 2006 UPC or the 2006 IPC for all new work. Clarify if hot water system is recirculating or not. 1/2" of insulation on hot water piping may be insuficient (GN 6.3) Clarify lack of information for fixtures P4 & P5 and added information for unused P3. Provide details for new shower installation to include domestic water piping, waste piping, controls, etc. |
08/30/2011 | LEERAY HANLY | BUILDING-COMMERCIAL | REVIEW | Denied | PP A-2 a) keynote 2....provide panic hardware. Signage per IBC 1008.1.8.3 is for main exits only. b) what is keynote 5 by office 111? Should it be keynote 6? c) keynote 9...Please provide details for listed 3 hour assembly at exit passageway infill d) keynote 11 "provide ADA compliant...", do you mean accessible? Please provide cut sheets or details for prefabricated shower insert...to include threshold detail. PPA-4 a) If you are going to list minimum or maximum dimensions then you must also show associated maximum or minimum dimensions as applicable. If you use a dimension within the allowed range then please delete extraneous, misleading notations. eg..water closet is not 18" minimum from side wall as noted, but should be 18" or 16" min-18" max. |
08/30/2011 | LEERAY HANLY | MECHANICAL-COMMERCIAL | REVIEW | Denied | PP M-002 a) Explain reference to drawing M2.1 in keynote 1. No such drawings supplied for reference. b) Keynote 4 data does not match info shown on floor plan c) Data on floor plans soes not coordinate with data in keynotes. d) Where do keynotes actually apply as many oare outside of const area, and some appear to be required at 2 locations. e) Please clarify keynote 12 as plans do not indicate any new duct work at specified location. f) Please clarify how outside air requirements are going to be met. Where is OA inlet and what should it be set at? |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
09/09/2011 | CPIERCE1 | OUT TO CUSTOMER | Completed |
09/09/2011 | SUE REEVES | REJECT SHELF | Completed |