Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL - NEW
Permit Number - T11CM02500
Review Name: COMMERCIAL - NEW
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 08/30/2011 | DAVE MANN | FIRE | REVIEW | Denied | Please provide code review analysis, including occupancy classification and type of construction. Please include the following fire sprinkler design criteria to the plans. 1. Flow data (static pressure, residual pressure, GPM) Available from the Fire Department (520) 837-7029 or 837-7030. 2. The standard to be used in development of sprinkler system. (NFPA 13, NFPA 13R, or NFPA 13D) 3. The hazard classification of the building, including any special hazards. 4. The density required of the water supply. |
| 08/30/2011 | GERRY KOZIOL | WWM | REVIEW | Denied | need 3rd floor PCRWRD review of location/method of connection to public sewer - Chad Amateau- 740-6547 need public sewer manhole tap permit - Yvonne Suarez - 740-6733 need 3rd floor capacity review - Kurt Stemm - 740-6607 need to abandon portion of on-site 6" public sewer need WW/IWC reivew & approval of e/one extreme series pre-packaged triplex grinder pump station model WH483 per utility plan C2.1 - Tom Tomchak - 5025 W Ina rd - 443-6200 need DEQ review & approval of lift station - David Amash - 33 N stone 7th floor - 243-7400 |
| 08/31/2011 | JASON GREEN | ENGINEERING | REVIEW | Denied | Building plans will be reviewed once an approved Development Plan is provided; D11-0026. Verify conformance between the 2 plan sets. |
| 09/13/2011 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Denied | 1. Please submit approved Site Development Plan. 2. Please submit a deferred submittal letter to the building official for the assessment of additional plan review fees. 3. Please submit Special Inspection Certifications. 4. Please provide building code Data and submit building code analysis and insure the following information is included: a. Fire wall separations; please provide a plan showing all required rated partitions. b. Code analysis of providing type "A" and "B" accessible apartment units for this project as required by the 2006 IBC, Section 1107.6.2 and ICC/ANSI 117.1 requirements, Chapter 10 Dwelling and Sleeping Units. c. Please show building separation requirements and conclusion. d. Occupancy calculations and total occupancy load as per the 2006 IBC, Section 1004. e. Building Use f. Construction classification and size and height requirements and square footage analysis. SHEET A2.4 5. Detail 6: the shower is not properly oriented and does not have the required clearance as per ICC/ANSI 117.1, Section 1103.11.9 and 1104.11.3.1.3.3. 6. At detail 5, show the 5' turn around circle. 7. Please provide a large scale detail of the non accessible toilet plan and show how they are in compliance with type "B" dwelling units as per ICC/ANSI 117.1, Section 1104.11. 8. There are water dispenser details shown on this sheet but not shown on the any of the floor plans, architectural, plumbing and electrical. Please include on all plans. 9. Please show interior elevations for all different types of toilet plan and kitchen plan layouts. SHEET A2.5 10. Please finish providing all the dimensions on the stair plans and elevations/sections. SHEET A4.0 11. Roof scuppers are not code compliant, reference plumbing notes. SHEET A6.0 12. Please adjust all doors sizes to comply with ICC/ANSI, Chapter 10 for type "A" dwelling units if required and type "B" dwelling units. Reference section 1004.5. SHEET A7.0 13. Note 27 at unit demising wall states that wall is to continue to bottom of deck. Detail shows wall stopping at ceiling. Please reconcile. SHEET A7.1 14. Ditto comment 13 for detail 1/A7.1. SHEET A8.0 15. Detail 1 shows a 1 hour demising wall. The 2006 IBC, Section 708.3 allows for a 1/2 hour dwelling unit separation with a fully sprinkled building. SHEET 10 16. The counter heights at details 3 and 5 are not compliant with ICC/ANSI, Section 606.3. CALCULATIONS 17. Please provide foundation, floor framing and roof framing key plans for reference to calculations. END OF REVIEW |
| 09/14/2011 | ROBERT SHERRY | WATER | REVIEW | Approved | |
| 09/14/2011 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Provide energy code compliance calculations for the building envelope; use the climate zone for Pima County < 4,000 feet. Provide sufficient detail on the drawings to evaluate the energy compliance of the building envelope. The information shall, as a minimum, include U-factors of the envelope systems and fenestration components, along with the R-values of the insulation and the SHGC for the fenestration. Reference: Sections 101.4 and 104.2, International Energy Conservation Code 2006. 2. Clarify the size of the dryer exhaust duct; it is noted as being 6" on sheet M1.1 and 4" in detail 6/M2.1. It is not clear if there is a single duct serving both dryer or if two independent ducts are proposed. If only one exhaust duct is proposed, provide a design for the operation of the exhaust system. Reference: Sections 504.6 and 504.7, IMC 2006. |
| 09/15/2011 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. A separate plumbing permit, including approval from the Pima County department of Environmental Quality, will be required for the installation of a private sewer collection system with a capacity greater than 3,000 gallons per day and a lift station. 2. Provide a floor drain in the common laundry area. Show that the floor slopes toward the floor drain. Reference: Sections 411.2.3 and 411.4, UPC 2006. 3. Provide information to show that the ADA-shower control valves conform to the requirements of ASSE 1016. Reference: Section 418.0, UPC 2006. 4. The Powers model F473 pressure-balanced shower/tub valve appears to be an obsolete product. Provide information to show that the listing of this valve is still current. Reference: Sections 301.1.1 and 418.0, UPC 2006. 5. Provide a watertight pan of corrosion-resistant material under the water heaters located on the second floor with a drain to an approved location. Reference: Section 508.4, UPC 2006. 6. Show the size, route, and termination of the T&P relief pipes from the water heaters. Reference: Section 608.5, UPC 2006. 7. Provide cleanouts sized per Section 707.11, UPC 2006. 8. Clarify the arrangement of the scuppers and overflows noted on sheet P1.2 and coordinate with the architectural detail 4/A4.0 (the "scupper overflow drain" shown in detail 4/A4.0 only provides overflow protection for the collector box, not for the roof). Reference: Sections 103.2.3 and 1101.11.1, and Table 11-1, UPC 2006. 9. Provide drainage for the roof over the small flat-roofed enclosure on the southeast end of the building. Reference: Section 1101.11.1 and Table 11-1, UPC 2006. 10. Provide roof drainage plans for the pitched roof. All roof areas shall be drained by roof drains, scuppers, or gutters. Reference: Section 1101.11.1, UPC 2006. |
| 09/19/2011 | STEVE SHIELDS | ZONING | REVIEW | Denied | DSD TRANSMITTAL FROM: Steve Shields Lead Planner PROJECT: 1900 W SPEEDWAY BL T11CM02499, T11CM02500 Building Plan (1st Review) TRANSMITTAL DATE: September 16, 2011 1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until all zoning comments or concerns have been addressed. 2. Zoning can not approve the building plan until the development plan has been approved by all PDSD agencies. 3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved and stamped site plan. Additional comments may be forthcoming. If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956 C:\planning\grading\t11cm02499.doc RESUBMITTAL OF THE FOLLOWING IS REQUIRED: |
| 09/22/2011 | LEERAY HANLY | ELECTRICAL-COMMERCIAL | REVIEW | Denied | THE ELECTRICAL REVIEW FOR THIS PROJECT HAS BEEN COMPLETED BY DAN SANTA-CRUZ. FOR QUESTIONS ABOUT THE REVIEW HE MAY BE CONTACTED AT 909-5173. 1) PROVIDE IECC COMPLIANCE CERTIFICATE 2) PROVIDE INFORMATION, INCLUDING CUT SHEETS FOR EXTERIOR LIGHTS, TO SHOW COMPLIANCE WITH THE OUTDOOR LIGHTING CODE. 3) LIGHT MISSING IN NORTH STAIRWAY BUILDING 'A'. 4) ERRATA---TYPO ON 1 LINE E3.1; PANEL HP SHOULD BE 200 AMP |
| 09/26/2011 | BETH GRANT | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Needs Review |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 09/29/2011 | SUE REEVES | OUT TO CUSTOMER | Completed |
| 09/29/2011 | SUE REEVES | REJECT SHELF | Completed |