Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T11CM02410
Review Name: RESUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
10/04/2011 | JASON GREEN | ENGINEERING | REVIEW | Denied | DATE: October 4, 2011 REVIEWER: Jason Green, CFM ACTIVITY: T11CM02410 (Building Plan) SUMMARY: Engineering Division of Planning & Development Services Department has received the building plan (T11CM02410). Engineering Division does not recommend approval of the building plan applications at this time. The following items need to be addressed: BUILDING PLAN COMMENTS: 1) Engineering could not verify that the building plan was in compliance with a stamped approved Development Plan Package (D11-0031). Please submit a copy of the stamped approved Development Plan, landscape, and NPPO plans with the next building plan submittal. 2) Engineering will re-review the building plan on the next submittal to insure compliance with the approved and stamped Development Plan. Additional comments may be forthcoming. GENERAL COMMENTS: Please provide the building plan with a copy of the last approved Development Plan (D11-0031). Further comments may be generated upon resubmittal of the building plan review. For questions or to schedule an appointment I can be reached at 837-4929. Jason Green, CFM Senior Engineer Associate Engineering Division Planning & Development Services |
10/12/2011 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Approved | |
10/18/2011 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Revise the overflow protection for the collector boxes serving the new scuppers. The overflow protection for the collector boxes must be capable of the passing the same flow as the primary scuppers. Reference: Sections 1101, 1106 and 1107, IPC 2006 and Section 1611.1, IBC 2006. 2. Clarify the configuration of the rainwater conductors connected to the roof drains and overflow drains located between columns M and P along column line 2B (sheet P1.0). Reference: Sections 106.3.1 and 1106.1, IPC 2006. |
10/19/2011 | STEVE SHIELDS | ZONING | REVIEW | Denied | PDSD TRANSMITTAL FROM: Steve Shields Lead Planner PROJECT: B/E Aerospace T11CM02410 Building Plan (2nd Review) TRANSMITTAL DATE: October 19, 2011 1. The building, plan has been reviewed by Zoning Review Section but cannot approve the plans until all zoning comments or concerns have been addressed. 2. Zoning can not approve the plans until the development package has been approved.. 3. Zoning will re-review the plans on the next submittal to insure compliance with the approved and development package. Additional comments may be forthcoming. If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956 C:\planning\building\t11cm02410.doc RESUBMITTAL OF THE FOLLOWING IS REQUIRED: |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
10/20/2011 | DELMA ROBEY | OUT TO CUSTOMER | Completed |
10/20/2011 | SUE REEVES | REJECT SHELF | Completed |