Permit Number: T11CM01902
Parcel: 13329015B

Review Status: Completed

Review Details: COMMERCIAL - NEW

Permit Number - T11CM01902
Review Name: COMMERCIAL - NEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
06/24/2011 MARTIN BROWN FIRE REVIEW Denied Fire sprinklers required due to distance from fire hydrants and lack of Fire Department access. Refer to C.O.T amendments to the 2006 IFC, section 508.5.1.
06/29/2011 TERRY STEVENS ZONING REVIEW Denied 06/29/2011

Development Services Department
Zoning Review Section

Terry Stevens
Lead Planner

Comments:

1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed.

2. Zoning could not verify that the building plan was in compliance with the approved site plan. Please submit two copies of the approved and stamped site, landscape, and NPPO plans with the next building plan submittal.

3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved site plan. Additional comments may be forthcoming.
06/30/2011 ERIC NEWCOMB BUILDING-COMMERCIAL REVIEW Denied 1. SHEET T1.1 (PARKING CALCULATIONS); SHEET AS1.1 (SITE PLAN): THE PARKING CALCULATIONS INDICATE 48 SPACES PROVIDED WITH 2 HANDICAP SPACES FOR THE ENTIRE SITE. THE SITE PLAN DOES NOT INDICATE THE SAME. VERIFY.
2. SHEET T1.1; CODE ANALYSIS (MINIMUM PLUMBING FACILITIES): THE DRAWING INDICATES ONLY ONE WATER CLOSET IS REQUIRED AND PROVIDED. IBC TABLE 2902.1 AND SECTION 2902.2 INDICATE SEPARATE FACILITIES FOR EACH SEX ARE REQUIRED. VERIFY. IBC SECTION 2902.4.1 MAY BE USED, BUT THIS SHOULD BE ADDRESSED ON THE DRAWINGS.
3. SHEET AS1.1; SITE PLAN: NO HANDICAP PARKING SPACE, ACCESS AISLE, OR RAMP ARE INDICATED FOR THE NEW ADDITION. VERIFY.
4. SHEET S1.4 (SHEAR WALL SCHEDULE); STRUCTURAL CALCULATIONS (SHEET 25): THE CALCULATIONS INDICATE 5/8" DIAMETER ANCHOR BOLTS IN THE SHEAR WALLS, WHILE THE SCHEDULE INDICATES 1/2" DIAMETER ANCHOR BOLTS. CLARIFY.
5. GENERAL: ALL DEFERRED SUBMITTALS MUST BE APPROVED IN WRITING BY RON BOOSE OR LEERAY HANLY BEFORE THOSE SUBMITTALS WILL BE REVIEWED.
6. GENERAL: PROVIDE WRITTEN RESPONSES TO ALL REVIEW COMMENTS.
07/06/2011 GERRY KOZIOL WWM REVIEW Denied NEED ADDRESSING REVIEW- SEPARATE LOT
NEED TO SHOW LOCATION/METHOD OF CONNECTION TO PUBLIC SEWER
07/08/2011 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Denied Provide energy code compliance calculations for the building envelope using the climate zone for Pima County < 4,000 feet. Provide sufficient detail on the drawings to evaluate the energy compliance of the building envelope. The information shall, as a minimum, include U-factors of the envelope systems and fenestration components, along with the R-values of the insulation and the SHGC for the fenestration. Reference: Sections 101.4 and 104.2, International Energy Conservation Code 2006.
07/08/2011 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied 1. Show the inverts and slope of the building sewer line on drawing. Reference: Section 106.3.1, IPC 2006.
2. Coordinate the location of the water service entrance to the building with the civil site plan. Reference: Section 106.3.1, IPC 2006.
3. Provide the minimum plumbing facilities required by Table 2902.1 and Section 2902.2, IBC 2006, for educational occupancy (i.e. separate facilities for each sex).
07/08/2011 ROBERT SHERRY WATER REVIEW Denied 1. Verify the size of the proposed water meter (3/4") is available from Tucson Water.
2. Show the location of the proposed reduced pressure backflow preventer (RPBP). Reference: Section 106.3.1 IPC 2006.
07/14/2011 LAITH ALSHAMI ENGINEERING REVIEW Denied Laith Alshami, Engineering and Floodplain Review, 07/14/2011,

The building plan can not be approved until the site plan is approved.
07/15/2011 RAY MAJUTA ELECTRICAL-COMMERCIAL REVIEW Approved

Final Status

Task End Date Reviewer's Name Type of Review Description
07/22/2011 GERARDO BONILLA REJECT SHELF Completed